Home / Browse projects / Rajkot, Gujarat / Shree Bileshwar Heights

Valid until 30 Apr 2027 Mixed Development project

Shree Bileshwar Heights

By Narendrabhai Maganlal Solanki Proprietor Narendrakumar & Co.

RG-GJ-97354 · RERA PR/GJ/RAJKOT/RAJKOT/Others/MAA09155/111021 · Last updated on GujRERA portal: 22 Oct 2024

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Apr 2027Possession promisedno revision filed
40 of 63Construction stages doneacross 7 buildings; furthest along: Internal walls, 90%
146 of 248Units unsoldnot recorded sold or booked
Jump to the 38 documents Report an error

Shree Bileshwar Heights is a Mixed Development project by Narendrabhai Maganlal Solanki Proprietor Narendrakumar & Co. in Rajkot, Gujarat, registered with GujRERA as PR/GJ/RAJKOT/RAJKOT/Others/MAA09155/111021 on 11 Oct 2021. Possession is promised by 30 Apr 2027. 102 of the 248 units on this registration are recorded sold or booked, and 40 of 63 construction stages are filed complete.

At a glance

Project

  • NameShree Bileshwar Heights
  • TypeMixed Development
  • Location
    • Survey No 56 P
    • Plot No. 4
    • Oppo. Sarkari Nursary
    • 80ft Main Road
    • Vavdi
    • Rajkot
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/RAJKOT/RAJKOT/Others/MAA09155/111021
  • ReraGenie IDRG-GJ-97354

Builder

  • NameNarendrabhai Maganlal Solanki Proprietor Narendrakumar & Co.
  • Entity typeIndividual/Propritorship
  • Other registrations1 more →

Key dates

this monthRegisteredOct 2021PromisedApr 2027

Key facts

Registration and timeline

  • StatusValid until 30 Apr 2027
  • Registered on11 Oct 2021
  • Promised completion30 Apr 2027
  • Revised completionNone
  • Buildings7 building records
  • Documents filed38 files

Current status

41%102 of 248 units booked
78.1%Of the estimated cost spent so far

Figures as on 22 Oct 2024, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Wing C2---36036
Wing C3---34034
Shops---04040
Wing A---34034
Wing B1---34034
Wing B2---36036
Wing C1---34034

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building7

As on 22 Oct 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

40 of 63 construction stages are filed complete across 7 buildings. The stage furthest along is Internal walls, at 90%.

Wing C291%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats78%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing65%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing72%
Wing C389%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats71%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing65%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing62%
Shops91%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats80%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing60%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing80%
Wing A86%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats90%
Sanitary fittings within the flats74%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing60%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing65%
Wing B190%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats76%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing60%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing76%
Wing B289%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats72%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing60%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing69%
Wing C190%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats74%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing65%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing68%

Progress on shared amenities23

As on 22 Oct 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsNoNot applicable
Water supplyYes0%
Sewerage (chamber, lines, septic tank, STP)Yes0%
Storm water drainsNoNot applicable
Landscaping and tree plantingNoNot applicable
Street lightingNoNot applicable
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingYes0%
Drinking water facilitiesYes0%
Emergency evacuationNoNot applicable
Use of renewable energyYes0%
SecurityYes0%
Letter boxYes0%
Compound wallYes0%
Plinth protectionYes0%
Water tankYes0%
Other requirementsYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,474 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 19.54 cr
Cost incurredRs 15.27 cr
Spent of the estimate78.14%
BuildingWingEstimatedIncurred
ShopsNARs 2.79 crRs 1.17 cr
Wing ANARs 2.79 crRs 2.10 cr
Wing B1NARs 2.79 crRs 2.35 cr
Wing B2NARs 2.79 crRs 2.48 cr
Wing C1NARs 2.79 crRs 2.35 cr
Wing C2NARs 2.79 crRs 2.48 cr
Wing C3NARs 2.79 crRs 2.34 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDhwani Divyesh Badani
EngineerChetan Sayani

Documents filed38

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/RAJKOT/RAJKOT/Others/MAA09155/111021 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineer's certificate (Form 2)22 Oct 2024
Engineer's certificate annexure22 Oct 2024
RERA registration certificate11 Oct 2021
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Rajkot

41%of this project is bookeddistrict median 56%
13%of Rajkot projects moved their completion datethis one has not

Computed across the 1,800+ Rajkot projects on ReraGenie, from their own filings.

Keep Shree Bileshwar Heights on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Rajkot1,800+ in Rajkot

2 kmShree Bileshwar HeightsOther 229Dot size: filed unitsN

Filed coordinates, straight-line distance. 229 registered projects within 2 km.

Builder: Narendrabhai Maganlal Solanki Proprietor Narendrakumar & Co.

Narendrabhai Maganlal Solanki Proprietor Narendrakumar & Co. has 2 registrations on GujRERA, including Shree Bileshwar Heights and Shree Dwarkesh Nagari. Read the full track record. See more projects on the Rajkot district page.

Frequently asked questions

What are my rights if Shree Bileshwar Heights is delayed beyond 30 Apr 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of Shree Bileshwar Heights?

The registered promoter entity is Narendrabhai Maganlal Solanki Proprietor Narendrakumar & Co., an individual/propritorship as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in Shree Bileshwar Heights?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Shree Bileshwar Heights?

The professionals named in the filing: Architect: Dhwani Divyesh Badani; Engineer: Chetan Sayani. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Shree Bileshwar Heights?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Shree Bileshwar Heights. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Shree Bileshwar Heights to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.