SHIVANT ARENA
RG-GJ-52512 · RERA PR/GJ/SURAT/SURAT CITY/Surat Municipal Corporation/RAA14721/230125/300629 · Last updated on GujRERA portal: 23 Jan 2025
Source: official GujRERA filing
Red flags
- No red flags in this filing
Clear
- Completion date never moved
Saved.
SHIVANT ARENA is a Residential/Group Housing project by MARUTI ENTERPRISE in Surat, Gujarat, registered with GujRERA as PR/GJ/SURAT/SURAT CITY/Surat Municipal Corporation/RAA14721/230125/300629 on 23 Jan 2025. Possession is promised by 30 Oct 2029. 8 of the 266 units on this registration are recorded sold or booked, and 10 of 45 construction stages are filed complete.
At a glance
Project
- NameSHIVANT ARENA
- TypeResidential/Group Housing
- Location
- Block No. 95/A
- T.P.S.No 85 (Sarthana-Pasodara-Laskana)
- F.P No.87/Sub Plot No-2
- City Survey No. NA95/A/2
- Village: Sarthana
- Tal. Surat City
- Surat.
- ...
- Pincode395013
- MapView location on Google Maps (as filed on RERA)
- RERA no.PR/GJ/SURAT/SURAT CITY/Surat Municipal Corporation/RAA14721/230125/300629
- ReraGenie IDRG-GJ-52512
Builder
- NameMARUTI ENTERPRISE
- Entity typePARTNERSHIP FIRM
- Other registrations10 more →
Key dates
Key facts
Registration and timeline
- StatusValid until 30 Oct 2029
- Registered on23 Jan 2025
- Promised completion30 Oct 2029
- Revised completionNone
- Buildings5 building records
- Documents filed19 files
Current status
Figures as on 23 Jan 2025, this project's latest GujRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A | - | - | - | 56 | 0 | 56 |
| B | - | - | - | 56 | 0 | 56 |
| C | - | - | - | 56 | 0 | 56 |
| D | - | - | - | 56 | 0 | 56 |
| E | - | - | - | 42 | 0 | 42 |
The full filing
Everything below is from the project's own GujRERA filing, free to read.
Construction progress by building5
As on 23 Jan 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
10 of 45 construction stages are filed complete across 5 buildings. The stage furthest along is Slabs of Super Structure, at 46%.
A27%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 38% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 7% |
| Sanitary fittings within the flats | 0% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 0% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 0% |
B26%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 31% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 0% |
| Sanitary fittings within the flats | 0% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 0% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 0% |
C26%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 31% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 0% |
| Sanitary fittings within the flats | 0% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 0% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 0% |
D29%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 46% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 14% |
| Sanitary fittings within the flats | 0% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 0% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 0% |
E26%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 38% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 0% |
| Sanitary fittings within the flats | 0% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 0% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 0% |
Progress on shared amenities23
As on 23 Jan 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal roads and footpaths | Yes | 0% |
| Water supply | Yes | 0% |
| Sewerage (chamber, lines, septic tank, STP) | Yes | 0% |
| Storm water drains | Yes | 0% |
| Landscaping and tree planting | Yes | 0% |
| Street lighting | Yes | 0% |
| Community buildings | No | Not applicable |
| Treatment and disposal of sewage and sullage water | Yes | 0% |
| Solid waste management and disposal | Yes | 0% |
| Water conservation, rain water harvesting | Yes | 0% |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Fire fighting | Yes | 0% |
| Drinking water facilities | Yes | 0% |
| Emergency evacuation | Yes | 0% |
| Use of renewable energy | Yes | 0% |
| Security | Yes | 0% |
| Letter box | Yes | 0% |
| Compound wall | Yes | 0% |
| Plinth protection | Yes | 0% |
| Water tank | Yes | 0% |
| Other requirements | Yes | 0% |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| A | NA | Rs 6.75 cr | Rs 70,000 |
| B | NA | Rs 6.75 cr | Rs 70,000 |
| C | NA | Rs 6.75 cr | Rs 70,000 |
| D | NA | Rs 6.75 cr | Rs 70,000 |
| E | NA | Rs 6.00 cr | Rs 70,000 |
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Haniket Umeshbhai Patel |
| Engineer | DIVYESH KISHORBHAI GEDIYA |
Documents filed19
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/SURAT/SURAT CITY/Surat Municipal Corporation/RAA14721/230125/300629 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| RERA registration certificate | 23 Jan 2025 |
| Engineer's certificate (Form 2) | 20 Jan 2025 |
| Engineer's certificate annexure | 20 Jan 2025 |
| Project specific document | - |
| Drainage affidavit | - |
| Approved sanctioned plan | - |
| Approved layout plan | - |
| Land location | - |
| Encumbrance certificate | - |
| Area development document | - |
| Brochure | - |
| Declaration in Form B | - |
| Approved building or plotting plan | - |
| NOCs from authorities | - |
| Title clearance certificate | - |
| Title report | - |
| Property card | - |
| Statutory document | - |
| Project photograph | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Surat
Computed across the 2,600+ Surat projects on ReraGenie, from their own filings.
Keep SHIVANT ARENA on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near SARTHANA2,600+ in Surat
Filed coordinates, straight-line distance. 165 registered projects within 2 km.
SMIT RESIDENCY
J EKLERA REALTY
J EKLERA BUSINESS HUB
J EKLERA BUSINESS HUB
HARIKRUSHNA VISTAS
SHREE GOPINATHJI DEVELOPERS
EDEN EVOQ & EMPIRE
EVOQ INFRA
KARUNESH FLORA
FLORA BUILDCON
SKY LIGHT
B N CORPORATION
See every Surat project, with the district possession charts
Builder: MARUTI ENTERPRISE
MARUTI ENTERPRISE has 11 registrations on GujRERA, including DECORA WEST HILL and NANDANVAN STYLES. Read the full track record. See more projects on the Surat district page.
Frequently asked questions
What are my rights if SHIVANT ARENA is delayed beyond 30 Oct 2029?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.
How do I verify and contact the developer of SHIVANT ARENA?
The registered promoter entity is MARUTI ENTERPRISE, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.
Is my payment protected in SHIVANT ARENA?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at SHIVANT ARENA?
The professionals named in the filing: Architect: Haniket Umeshbhai Patel; Engineer: DIVYESH KISHORBHAI GEDIYA. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SHIVANT ARENA?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.