Home / Browse projects / Banaskantha, Gujarat / Shivam Green

Valid until 30 Apr 2027 Residential/Group Housing project

Shivam Green

By LABH DEVELOPERS

RG-GJ-11001 · RERA PR/GJ/BANASKANTHA/PALANPUR/Others/RAA10261/310522 · Last updated on GujRERA portal: 17 Jul 2026

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Apr 2027Possession promisedno revision filed
1 of 9Construction stages donefurthest along: Stilt Floor, 90%
25 of 36Units unsoldnot recorded sold or booked
Jump to the 41 documents Report an error

Shivam Green is a Residential/Group Housing project by LABH DEVELOPERS in Banaskantha, Gujarat, registered with GujRERA as PR/GJ/BANASKANTHA/PALANPUR/Others/RAA10261/310522 on 31 May 2022. Possession is promised by 30 Apr 2027. 11 of the 36 units on this registration are recorded sold or booked, and 1 of 9 construction stages are filed complete.

At a glance

Project

  • NameShivam Green
  • TypeResidential/Group Housing
  • Location
    • Shivam Green
    • Behind Cozy Complex
    • Dundhiya Wadi Road
    • Tajpura
    • Palanpur
    • Palanpur
    • Banaskantha
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/BANASKANTHA/PALANPUR/Others/RAA10261/310522
  • ReraGenie IDRG-GJ-11001

Builder

  • NameLABH DEVELOPERS
  • Entity typePARTNERSHIP FIRM
  • Other registrations6 more →

Key dates

this monthRegisteredMay 2022PromisedApr 2027

Key facts

Registration and timeline

  • StatusValid until 30 Apr 2027
  • Registered on31 May 2022
  • Promised completion30 Apr 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed41 files

Current status

31%11 of 36 units booked
91.0%Of the estimated cost spent so far

Figures as on 17 Jul 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
One---36036

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 17 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 9 construction stages are filed complete. The stage furthest along is Stilt Floor, at 90%.

One: 78% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor90%
Slabs of Super Structure90%
Internal walls, internal plaster, floorings, doors and windows within flats85%
Sanitary fittings within the flats85%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks85%
External plumbing and external plaster, elevation, completion of terraces with waterproofing85%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing85%

Progress on shared amenities19

As on 17 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes0%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsNoNot applicable
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterYes100%
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes50%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingNoNot applicable
Drinking water facilitiesYes100%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,553 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 2.70 cr
Cost incurredRs 2.46 cr
Spent of the estimate91.0%
BuildingWingEstimatedIncurred
OneNARs 2.70 crRs 2.46 cr

Certifying professionals and partners1

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
EngineerHarsh Patel

Documents filed41

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/BANASKANTHA/PALANPUR/Others/RAA10261/310522 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)17 Jul 2026
Engineer's certificate (Form 2)17 Jul 2026
Engineer's certificate annexure17 Jul 2026
Accountant's certificate (Form 3)17 Jul 2026
Site photograph, One17 Jul 2026
RERA registration certificate31 May 2022
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Banaskantha

31%of this project is bookeddistrict median 40%
13%of Banaskantha projects moved their completion datethis one has not

Computed across the 93 Banaskantha projects on ReraGenie, from their own filings.

Keep Shivam Green on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Banaskantha93 in Banaskantha

2 kmShivam GreenOther 26Dot size: filed unitsN

Filed coordinates, straight-line distance. 26 registered projects within 2 km.

Builder: LABH DEVELOPERS

LABH DEVELOPERS has 7 registrations on GujRERA, including MEGHA HEIGHTS and Prayosha Heights. Read the full track record. See more projects on the Banaskantha district page.

Frequently asked questions

What are my rights if Shivam Green is delayed beyond 30 Apr 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of Shivam Green?

The registered promoter entity is LABH DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in Shivam Green?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Shivam Green?

The professionals named in the filing: Engineer: Harsh Patel. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Shivam Green?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Shivam Green. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Shivam Green to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.