Home / Browse projects / Valsad, Gujarat / Shivam Eternity

Valid until 30 Apr 2031 Residential/Group Housing project

Shivam Eternity

By URBAN HOUSE REALTORS LLP

RG-GJ-62460 · RERA PR/GJ/VALSAD/PARDI/Others/RAA10444/140722 · Last updated on GujRERA portal: 2 Oct 2024

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Apr 2031Possession promisedno revision filed
28 of 54Construction stages doneacross 6 buildings; furthest along: External plumbing and external plaster, 90%
201 of 286Units unsoldnot recorded sold or booked
Jump to the 38 documents Report an error

Shivam Eternity is a Residential/Group Housing project by URBAN HOUSE REALTORS LLP in Valsad, Gujarat, registered with GujRERA as PR/GJ/VALSAD/PARDI/Others/RAA10444/140722 on 14 Jul 2022. Possession is promised by 30 Apr 2031. 85 of the 286 units on this registration are recorded sold or booked, and 28 of 54 construction stages are filed complete.

At a glance

Project

  • NameShivam Eternity
  • TypeResidential/Group Housing
  • Location
    • Survey No. 1274 and 3533
    • Opp. Big Bazar
    • Kevdi Falia Road
    • Chala
    • Vapi.
    • Pardi
    • Valsad
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VALSAD/PARDI/Others/RAA10444/140722
  • ReraGenie IDRG-GJ-62460

Builder

  • NameURBAN HOUSE REALTORS LLP
  • Entity typeLIMITED LIABILITY PARTNERSHIP FIRM
  • Other registrations1 more →

Key dates

this monthRegisteredJul 2022PromisedApr 2031

Key facts

Registration and timeline

  • StatusValid until 30 Apr 2031
  • Registered on14 Jul 2022
  • Promised completion30 Apr 2031
  • Revised completionNone
  • Buildings6 building records
  • Documents filed38 files

Current status

30%85 of 286 units booked
47.8%Of the estimated cost spent so far

Figures as on 2 Oct 2024, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A Building---40040
B Building---40040
C Building---40040
D Building---40040
E Building---50050
F Building---76076

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building6

As on 2 Oct 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

28 of 54 construction stages are filed complete across 6 buildings. The stage furthest along is External plumbing and external plaster, at 90%.

A Building100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
B Building0%
ActivityProgress
Excavation0%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
C Building26%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure30%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
D Building46%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats60%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
E Building73%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats30%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing30%
F Building99%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing90%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities23

As on 2 Oct 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes30%
Water supplyYes30%
Sewerage (chamber, lines, septic tank, STP)Yes30%
Storm water drainsNoNot applicable
Landscaping and tree plantingYes20%
Street lightingYes10%
Community buildingsYes0%
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingYes0%
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes0%
Letter boxNoNot applicable
Compound wallYes0%
Plinth protectionYes0%
Water tankYes15%
Other requirementsYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area7,369 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 53.00 cr
Cost incurredRs 25.34 cr
Spent of the estimate47.81%
BuildingWingEstimatedIncurred
F BuildingNARs 11.64 crRs 10.96 cr
E BuildingNARs 9.85 crRs 5.12 cr
A BuildingNARs 7.99 crRs 7.99 cr
C BuildingNARs 7.90 cr-
D BuildingNARs 7.90 crRs 1.26 cr
B BuildingNARs 7.71 cr-

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKushkuvar Y. Shah
EngineerDipali M.Desai

Documents filed38

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VALSAD/PARDI/Others/RAA10444/140722 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineer's certificate (Form 2)2 Oct 2024
Engineer's certificate annexure2 Oct 2024
RERA registration certificate14 Jul 2022
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Valsad

30%of this project is bookeddistrict median 45%
23%of Valsad projects moved their completion datethis one has not

Computed across the 390+ Valsad projects on ReraGenie, from their own filings.

Keep Shivam Eternity on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Valsad390+ in Valsad

2 kmShivam EternityOther 65Dot size: filed unitsN

Filed coordinates, straight-line distance. 65 registered projects within 2 km.

Builder: URBAN HOUSE REALTORS LLP

URBAN HOUSE REALTORS LLP has 2 registrations on GujRERA, including Shivam Eternity and Shivam Srushti. Read the full track record. See more projects on the Valsad district page.

Frequently asked questions

What are my rights if Shivam Eternity is delayed beyond 30 Apr 2031?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of Shivam Eternity?

The registered promoter entity is URBAN HOUSE REALTORS LLP, a limited liability partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in Shivam Eternity?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Shivam Eternity?

The professionals named in the filing: Architect: Kushkuvar Y. Shah; Engineer: Dipali M.Desai. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Shivam Eternity?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Shivam Eternity. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Shivam Eternity to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.