SHIVALAY
RG-GJ-26480 · RERA PR/GJ/BHAVNAGAR/BHAVNAGAR/Others/MAA00599/EX1/170519 · Last updated on GujRERA portal: 29 Oct 2020
Source: official GujRERA filing
Red flags
- Completion date moved by 12 months
- 1 extension taken
Clear
- Separate project account declared
Saved.
SHIVALAY is a Mixed Development project by SIDDHIVINAYAK BUILDCON in Bhavnagar, Gujarat, registered with GujRERA as PR/GJ/BHAVNAGAR/BHAVNAGAR/Others/MAA00599/EX1/170519 on 6 Nov 2017. Possession is promised by 29 Apr 2020. The completion date has moved by 12 months from the original filing. 26 of the 48 units on this registration are recorded sold or booked, and 18 of 18 construction stages are filed complete.
At a glance
Project
- NameSHIVALAY
- TypeMixed Development
- Location
- PLOT NO 1192 A/1
- AMBAWADI
- KRISHNANAGAR
- Aambavadi
- Bhavnagar
- 364001
- Pincode364001
- MapView location on Google Maps (as filed on RERA)
- RERA no.PR/GJ/BHAVNAGAR/BHAVNAGAR/Others/MAA00599/EX1/170519
- ReraGenie IDRG-GJ-26480
Builder
- NameSIDDHIVINAYAK BUILDCON
- Entity typePARTNERSHIP FIRM
- Other registrations4 more →
Key dates
Key facts
Registration and timeline
- StatusValid until 29 Apr 2020
- Registered on6 Nov 2017
- Promised completion29 Apr 2020
- Revised completionRevised to 29 Apr 2020 (originally 30 Apr 2019)
- Buildings2 building records
- Documents filed39 files
Current status
Figures as on 29 Oct 2020, this project's latest GujRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A | - | - | - | 15 | 18 | 33 |
| B | - | - | - | 15 | 0 | 15 |
The full filing
Everything below is from the project's own GujRERA filing, free to read.
Construction progress by building2
As on 29 Oct 2020, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
18 of 18 construction stages are filed complete across 2 buildings.
A100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
B100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
Progress on shared amenities19
As on 29 Oct 2020, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal roads and footpaths | No | Not applicable |
| Water supply | Yes | 100% |
| Sewerage (chamber, lines, septic tank, STP) | Yes | 100% |
| Storm water drains | Yes | 100% |
| Landscaping and tree planting | No | Not applicable |
| Street lighting | No | Not applicable |
| Community buildings | No | Not applicable |
| Treatment and disposal of sewage and sullage water | No | Not applicable |
| Solid waste management and disposal | No | Not applicable |
| Water conservation, rain water harvesting | No | Not applicable |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Fire fighting | No | Not applicable |
| Drinking water facilities | No | Not applicable |
| Emergency evacuation | No | Not applicable |
| Use of renewable energy | No | Not applicable |
| Security | No | Not applicable |
| Letter box | No | Not applicable |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| A | NA | Rs 2.31 cr | Rs 2.31 cr |
| B | NA | Rs 2.31 cr | Rs 2.31 cr |
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SANKET RATHOD |
| Engineer | BHAVESH VYAS |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Documents filed39
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/BHAVNAGAR/BHAVNAGAR/Others/MAA00599/EX1/170519 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect's certificate (Form 1) | 29 Oct 2020 |
| Engineer's certificate (Form 2) | 29 Oct 2020 |
| Engineer's certificate annexure | 29 Oct 2020 |
| Accountant's certificate (Form 3) | 29 Oct 2020 |
| Site photograph, A | 29 Oct 2020 |
| Site photograph, B | 29 Oct 2020 |
| RERA registration certificate | 6 Nov 2017 |
| Proforma agreement for sale | - |
| Auditor's report (1 of 3) | - |
| Auditor's report (2 of 3) | - |
| Auditor's report (3 of 3) | - |
| Income tax return (1 of 3) | - |
| Income tax return (2 of 3) | - |
| Income tax return (3 of 3) | - |
| Project specific document | - |
| Directors' report (1 of 3) | - |
| Directors' report (2 of 3) | - |
| Directors' report (3 of 3) | - |
| Commencement certificate | - |
| Approved sanctioned plan | - |
| Approved layout plan | - |
| Agreement | - |
| Land location | - |
| Encumbrance certificate | - |
| Area development document | - |
| Proforma allotment letter | - |
| Brochure | - |
| Project related document | - |
| Declaration in Form B | - |
| Project photograph | - |
| Audited balance sheet (1 of 3) | - |
| Audited balance sheet (2 of 3) | - |
| Audited balance sheet (3 of 3) | - |
| Audited profit and loss statement (1 of 3) | - |
| Audited profit and loss statement (2 of 3) | - |
| Audited profit and loss statement (3 of 3) | - |
| Cash flow statement (1 of 3) | - |
| Cash flow statement (2 of 3) | - |
| Cash flow statement (3 of 3) | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bhavnagar
Computed across the 730+ Bhavnagar projects on ReraGenie, from their own filings.
Keep SHIVALAY on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Aambavadi730+ in Bhavnagar
Filed coordinates, straight-line distance. 303 registered projects within 2 km.
SARDAR DIAMOND BOURSE
SARDAR DIAMOND HUB LLP
ASHTAVINAYAK-7
INDRASINHBAPUBHAGOHIL
Shiv Aaditya
GAMBHIRSINH AMARSINH PARMAR AND OTHERS
BHAVNAGAR DIAMOND BOURSE
SHARMIN DEVELOPERS LLP
VICTORIA PLATINUM
ORCHID & CO.
JUSTICE HORIZON TOWER
Dipak ganeshbhai nakrani proprietor of dee
See every Bhavnagar project, with the district possession charts
Builder: SIDDHIVINAYAK BUILDCON
SIDDHIVINAYAK BUILDCON has 5 registrations on GujRERA, including SHIVALAY and SUKOON 1. Read the full track record. See more projects on the Bhavnagar district page.
Frequently asked questions
What are my rights if SHIVALAY is delayed beyond 29 Apr 2020?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.
How do I verify and contact the developer of SHIVALAY?
The registered promoter entity is SIDDHIVINAYAK BUILDCON, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.
Is my payment protected in SHIVALAY?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at SHIVALAY?
The professionals named in the filing: Architect: SANKET RATHOD; Engineer: BHAVESH VYAS. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SHIVALAY?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.