SHILP GARDEN

By PRO LIFE PROPERTIES

RG-GJ-48049 · RERA PR/GJ/RAJKOT/KOTDA SANGANI/Rajkot Urban Development Authority/RN89AA09989/230622 · Last updated on GujRERA portal: 5 Oct 2024

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Jul 2027Possession promisedno revision filed
17 of 45Construction stages doneacross 5 buildings; furthest along: External plumbing and external plaster, 65%
87 of 140Units unsoldnot recorded sold or booked
Jump to the 39 documents Report an error

SHILP GARDEN is a Residential/Group Housing project by PRO LIFE PROPERTIES in Rajkot, Gujarat, registered with GujRERA as PR/GJ/RAJKOT/KOTDA SANGANI/Rajkot Urban Development Authority/RN89AA09989/230622 on 23 Jun 2022. Possession is promised by 31 Jul 2027. 53 of the 140 units on this registration are recorded sold or booked, and 17 of 45 construction stages are filed complete.

At a glance

Project

  • NameSHILP GARDEN
  • TypeResidential/Group Housing
  • Location
    • OPP TILADA PATEL SAMAJ
    • SHAPAR-DHOLRA ROAD
    • SHAPAR-360024
    • SHAPAR
    • Kotda Sangani
    • Rajkot
    • 360024
  • Pincode360024
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/RAJKOT/KOTDA SANGANI/Rajkot Urban Development Authority/RN89AA09989/230622
  • ReraGenie IDRG-GJ-48049

Builder

  • NamePRO LIFE PROPERTIES
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredJun 2022PromisedJul 2027

Key facts

Registration and timeline

  • StatusValid until 31 Jul 2027
  • Registered on23 Jun 2022
  • Promised completion31 Jul 2027
  • Revised completionNone
  • Buildings5 building records
  • Documents filed39 files

Current status

38%53 of 140 units booked
36.4%Of the estimated cost spent so far

Figures as on 5 Oct 2024, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
D---28028
F---28028
A---28028
B---28028
C---28028

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building5

As on 5 Oct 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

17 of 45 construction stages are filed complete across 5 buildings. The stage furthest along is External plumbing and external plaster, at 65%.

D100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
F0%
ActivityProgress
Excavation0%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
A0%
ActivityProgress
Excavation0%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
B0%
ActivityProgress
Excavation0%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
C96%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing65%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities23

As on 5 Oct 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes40%
Water supplyYes40%
Sewerage (chamber, lines, septic tank, STP)Yes40%
Storm water drainsYes40%
Landscaping and tree plantingYes40%
Street lightingYes40%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes25%
Electrical meter room, sub-station, receiving stationNoNot applicable
Fire fightingYes25%
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes25%
Letter boxNoNot applicable
Compound wallYes40%
Plinth protectionYes40%
Water tankYes40%
Other requirementsNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,281 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 9.00 cr
Cost incurredRs 3.28 cr
Spent of the estimate36.4%
BuildingWingEstimatedIncurred
ANARs 1.80 cr-
BNARs 1.80 cr-
CNARs 1.80 crRs 1.48 cr
DNARs 1.80 crRs 1.80 cr
FNARs 1.80 cr-

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectBhargav Bhikhalal Gajera
EngineerASHWINKUMAR MANILAL LODHIYA

Documents filed39

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/RAJKOT/KOTDA SANGANI/Rajkot Urban Development Authority/RN89AA09989/230622 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineer's certificate (Form 2)5 Oct 2024
Engineer's certificate annexure5 Oct 2024
RERA registration certificate23 Jun 2022
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Drainage affidavit-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Approved sanctioned plan-
Approved layout plan-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Declaration in Form B-
Approved building or plotting plan-
NOCs from authorities-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Proforma sale deed-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Rajkot

38%of this project is bookeddistrict median 56%
13%of Rajkot projects moved their completion datethis one has not

Computed across the 1,800+ Rajkot projects on ReraGenie, from their own filings.

Keep SHILP GARDEN on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near SHAPAR1,800+ in Rajkot

Builder: PRO LIFE PROPERTIES

PRO LIFE PROPERTIES has 1 registration on GujRERA, including SHILP GARDEN. Read the full track record. See more projects on the Rajkot district page.

Frequently asked questions

What are my rights if SHILP GARDEN is delayed beyond 31 Jul 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of SHILP GARDEN?

The registered promoter entity is PRO LIFE PROPERTIES, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in SHILP GARDEN?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SHILP GARDEN?

The professionals named in the filing: Architect: Bhargav Bhikhalal Gajera; Engineer: ASHWINKUMAR MANILAL LODHIYA. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHILP GARDEN?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHILP GARDEN. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHILP GARDEN to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.