Home / Browse projects / Jamnagar, Gujarat / SATYAM STATUS

Valid until 30 Jun 2026 Mixed Development project

SATYAM STATUS

By ASHA DEVELOPERS

RG-GJ-13185 · RERA PR/GJ/JAMNAGAR/JAMNAGAR/Others/MAA05966/EX1/220925/300626 · Last updated on GujRERA portal: 4 Sep 2025

Source: official GujRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • Nothing verified clear yet
Jun 2026Possession promisedmoved 12 months from the original
23 of 36Construction stages doneacross 4 buildings; furthest along: Sanitary fittings within the flats, 70%
44 of 81Units unsoldnot recorded sold or booked
Jump to the 44 documents Report an error

SATYAM STATUS is a Mixed Development project by ASHA DEVELOPERS in Jamnagar, Gujarat, registered with GujRERA as PR/GJ/JAMNAGAR/JAMNAGAR/Others/MAA05966/EX1/220925/300626 on 29 Aug 2019. Possession is promised by 30 Jun 2026. The completion date has moved by 12 months from the original filing. 37 of the 81 units on this registration are recorded sold or booked, and 23 of 36 construction stages are filed complete.

At a glance

Project

  • NameSATYAM STATUS
  • TypeMixed Development
  • Location
    • R.S.NO 161
    • FINAL PLOT NO 70/01
    • PLOT NO 01
    • VILLAGE VIBHAPAR
    • JAMNAGAR RAJKOT ROAD
    • Vibhapar
    • Jamnagar
    • 361007
  • Pincode361007
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/JAMNAGAR/JAMNAGAR/Others/MAA05966/EX1/220925/300626
  • ReraGenie IDRG-GJ-13185

Builder

  • NameASHA DEVELOPERS
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredAug 2019First promiseJun 2025Revised toJun 2026

Key facts

Registration and timeline

  • StatusValid until 30 Jun 2026
  • Registered on29 Aug 2019
  • Promised completion30 Jun 2026
  • Revised completionRevised to 30 Jun 2026 (originally 30 Jun 2025)
  • Buildings4 building records
  • Documents filed44 files

Current status

46%37 of 81 units booked
78.0%Of the estimated cost spent so far

Figures as on 4 Sep 2025, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BLOCK 1---141125
BLOCK 2---14014
BLOCK 3---21021
BLOCK 4---21021

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building4

As on 4 Sep 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

23 of 36 construction stages are filed complete across 4 buildings. The stage furthest along is Sanitary fittings within the flats, at 70%.

BLOCK 189%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
BLOCK 268%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats70%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing70%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
BLOCK 368%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats70%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing70%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
BLOCK 481%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing30%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 4 Sep 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes0%
Water supplyYes0%
Sewerage (chamber, lines, septic tank, STP)NoNot applicable
Storm water drainsYes40%
Landscaping and tree plantingYes70%
Street lightingYes0%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes0%
Water conservation, rain water harvestingYes0%
Energy managementYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingYes0%
Drinking water facilitiesYes0%
Emergency evacuationYes0%
Use of renewable energyNoNot applicable
SecurityYes0%
Letter boxYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,958 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 7.14 cr
Cost incurredRs 5.57 cr
Spent of the estimate78.01%
BuildingWingEstimatedIncurred
BLOCK 3NARs 1.90 crRs 1.00 cr
BLOCK 4NARs 1.90 crRs 1.90 cr
BLOCK 1NARs 1.67 crRs 1.67 cr
BLOCK 2NARs 1.67 crRs 1.00 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectCHETAN PANCHOLI
EngineerNILAYSINH M CHAUHAN

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/JAMNAGAR/JAMNAGAR/Others/MAA05966/EX1/220925/300626Applied Jun 2025; approved Sep 2025

Documents filed44

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/JAMNAGAR/JAMNAGAR/Others/MAA05966/EX1/220925/300626 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)4 Sep 2025
Architect's certificate (Form 1)28 Jun 2025
Engineer's certificate (Form 2)28 Jun 2025
Engineer's certificate annexure28 Jun 2025
Site photograph, BLOCK 128 Jun 2025
Site photograph, BLOCK 228 Jun 2025
Site photograph, BLOCK 328 Jun 2025
Site photograph, BLOCK 428 Jun 2025
RERA registration certificate29 Aug 2019
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Jamnagar

46%of this project is bookeddistrict median 24%
7%of Jamnagar projects moved their completion datethis one moved by 12 months

Computed across the 220+ Jamnagar projects on ReraGenie, from their own filings.

Keep SATYAM STATUS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Vibhapar220+ in Jamnagar

2 kmSATYAM STATUSOther 30Dot size: filed unitsN

Filed coordinates, straight-line distance. 30 registered projects within 2 km.

Builder: ASHA DEVELOPERS

ASHA DEVELOPERS has 1 registration on GujRERA, including SATYAM STATUS. Read the full track record. See more projects on the Jamnagar district page.

Frequently asked questions

What are my rights if SATYAM STATUS is delayed beyond 30 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of SATYAM STATUS?

The registered promoter entity is ASHA DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in SATYAM STATUS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SATYAM STATUS?

The professionals named in the filing: Architect: CHETAN PANCHOLI; Engineer: NILAYSINH M CHAUHAN. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SATYAM STATUS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SATYAM STATUS. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SATYAM STATUS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.