SARATHI BUNGALOWS

By SARATHI BUILDCON

RG-GJ-37576 · RERA PR/GJ/AHMEDABAD/AHMEDABAD CITY/Ahmedabad Municipal Corporation/RAA16060/041125/300627 · Last updated on GujRERA portal: 4 Nov 2025

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Oct 2027Possession promisedno revision filed
51 of 180Construction stages doneacross 20 buildings; furthest along: Stilt Floor, 50%
44 of 44Units unsoldnot recorded sold or booked
Jump to the 50 documents Report an error

SARATHI BUNGALOWS is a Residential/Group Housing project by SARATHI BUILDCON in Ahmedabad, Gujarat, registered with GujRERA as PR/GJ/AHMEDABAD/AHMEDABAD CITY/Ahmedabad Municipal Corporation/RAA16060/041125/300627 on 4 Nov 2025. Possession is promised by 30 Oct 2027. 0 of the 44 units on this registration are recorded sold or booked, and 51 of 180 construction stages are filed complete.

At a glance

Project

  • NameSARATHI BUNGALOWS
  • TypeResidential/Group Housing
  • Location
    • TP-81
    • FP-46/1
    • OPP. KRISH BUNGLOW
    • NEW TP ROAD
    • NAROL-ASALALI HIGHWAY
    • LAMBHA
    • AHMEDABAD
    • LAXMIPURA
    • Ahmedabad City
    • Ahmedabad
    • 382405
  • Pincode382405
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/AHMEDABAD/AHMEDABAD CITY/Ahmedabad Municipal Corporation/RAA16060/041125/300627
  • ReraGenie IDRG-GJ-37576

Builder

  • NameSARATHI BUILDCON
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredNov 2025PromisedOct 2027

Key facts

Registration and timeline

  • StatusValid until 30 Oct 2027
  • Registered on4 Nov 2025
  • Promised completion30 Oct 2027
  • Revised completionNone
  • Buildings20 building records
  • Documents filed50 files

Current status

0%0 of 44 units booked
12.8%Of the estimated cost spent so far

Figures as on 4 Nov 2025, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A UNIT 2 4---202
B UNIT 15 17 19 21---404
A UNIT 3---101
C UNIT 36 38 40 42---404
B UNIT 14 16 18 20---404
F UNIT 34---101
C UNIT 37 39 41 43---404
E UNIT 22---101
D UNIT 13---101
B UNIT 25 27 29 31 33---505
G UNIT 35---101
A1 UNIT 12---101
B UNIT 24 26 28 30 32---505
A UNIT 1---101
A1 UNIT 6---101
B UNIT 23---101
A UNIT 5---101
A1 UNIT 7 9 11---303
C UNIT 44---101
A1 UNIT 8 10---202

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building20

As on 4 Nov 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

51 of 180 construction stages are filed complete across 20 buildings. The stage furthest along is Stilt Floor, at 50%.

A UNIT 2 437%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure33%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
B UNIT 15 17 19 2128%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor50%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
A UNIT 337%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure33%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
C UNIT 36 38 40 4233%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
B UNIT 14 16 18 2028%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor50%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
F UNIT 3428%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor50%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
C UNIT 37 39 41 4333%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
E UNIT 2228%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor50%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
D UNIT 1328%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor50%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
B UNIT 25 27 29 31 3328%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor50%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
G UNIT 3528%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor50%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
A1 UNIT 1237%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure33%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
B UNIT 24 26 28 30 3228%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor50%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
A UNIT 137%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure33%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
A1 UNIT 637%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure33%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
B UNIT 2328%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor50%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
A UNIT 537%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure33%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
A1 UNIT 7 9 1137%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure33%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
C UNIT 4433%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
A1 UNIT 8 1037%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure33%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%

Progress on shared amenities19

As on 4 Nov 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes0%
Water supplyYes0%
Sewerage (chamber, lines, septic tank, STP)Yes0%
Storm water drainsYes0%
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsYes0%
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes0%
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingNoNot applicable
Drinking water facilitiesYes0%
Emergency evacuationNoNot applicable
Use of renewable energyYes0%
SecurityYes0%
Letter boxYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,674 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 9.32 cr
Cost incurredRs 1.20 cr
Spent of the estimate12.85%
BuildingWingEstimatedIncurred
C UNIT 36 38 40 42NARs 96.13 lakhRs 13.43 lakh
C UNIT 37 39 41 43NARs 96.13 lakhRs 13.43 lakh
B UNIT 25 27 29 31 33NARs 86.21 lakhRs 3.44 lakh
B UNIT 24 26 28 30 32NARs 86.21 lakhRs 3.44 lakh
A1 UNIT 7 9 11NARs 76.32 lakhRs 18.27 lakh
B UNIT 15 17 19 21NARs 68.97 lakhRs 2.75 lakh
B UNIT 14 16 18 20NARs 68.97 lakhRs 2.75 lakh
A1 UNIT 8 10NARs 50.88 lakhRs 12.18 lakh
A UNIT 2 4NARs 50.70 lakhRs 12.14 lakh
A1 UNIT 12NARs 27.23 lakhRs 3.80 lakh
A1 UNIT 6NARs 26.73 lakhRs 6.40 lakh
A UNIT 5NARs 25.40 lakhRs 6.08 lakh

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectManish Kanjibhai Parmar
EngineerAKASHSINH RAJANSINH VARMA

Documents filed50

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/AHMEDABAD/AHMEDABAD CITY/Ahmedabad Municipal Corporation/RAA16060/041125/300627 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
RERA registration certificate4 Nov 2025
Accountant's certificate (Form 3)27 Oct 2025
Architect's certificate (Form 1)24 Sep 2025
Engineer's certificate (Form 2)24 Sep 2025
Engineer's certificate annexure24 Sep 2025
Site photograph, A UNIT 2 424 Sep 2025
Site photograph, B UNIT 15 17 19 2124 Sep 2025
Site photograph, A UNIT 324 Sep 2025
Site photograph, C UNIT 36 38 40 4224 Sep 2025
Site photograph, B UNIT 14 16 18 2024 Sep 2025
Site photograph, F UNIT 3424 Sep 2025
Site photograph, C UNIT 37 39 41 4324 Sep 2025
Site photograph, E UNIT 2224 Sep 2025
Site photograph, D UNIT 1324 Sep 2025
Site photograph, B UNIT 25 27 29 31 3324 Sep 2025
Site photograph, G UNIT 3524 Sep 2025
Site photograph, A1 UNIT 1224 Sep 2025
Site photograph, B UNIT 24 26 28 30 3224 Sep 2025
Site photograph, A UNIT 124 Sep 2025
Site photograph, A1 UNIT 624 Sep 2025
Site photograph, B UNIT 2324 Sep 2025
Site photograph, A UNIT 524 Sep 2025
Site photograph, A1 UNIT 7 9 1124 Sep 2025
Site photograph, C UNIT 4424 Sep 2025
Site photograph, A1 UNIT 8 1024 Sep 2025
Proforma agreement for sale-
Auditor's report (3 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (3 of 3)-
Approved sanctioned plan-
Approved layout plan-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Declaration in Form B-
Approved building or plotting plan-
NOCs from authorities-
Title clearance certificate-
Title report-
Property card-
Statutory document-
Other document-
Project photograph-
Proforma sale deed-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (3 of 3)-

How this compares with Ahmedabad

0%of this project is bookeddistrict median 53%
14%of Ahmedabad projects moved their completion datethis one has not

Computed across the 5,400+ Ahmedabad projects on ReraGenie, from their own filings.

Keep SARATHI BUNGALOWS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near LAXMIPURA5,400+ in Ahmedabad

2 kmSARATHI BUNGALOWSOther 141Dot size: filed unitsN

Filed coordinates, straight-line distance. 141 registered projects within 2 km.

Builder: SARATHI BUILDCON

SARATHI BUILDCON has 1 registration on GujRERA, including SARATHI BUNGALOWS. Read the full track record. See more projects on the Ahmedabad district page.

Frequently asked questions

What are my rights if SARATHI BUNGALOWS is delayed beyond 30 Oct 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of SARATHI BUNGALOWS?

The registered promoter entity is SARATHI BUILDCON, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in SARATHI BUNGALOWS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SARATHI BUNGALOWS?

The professionals named in the filing: Architect: Manish Kanjibhai Parmar; Engineer: AKASHSINH RAJANSINH VARMA. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SARATHI BUNGALOWS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SARATHI BUNGALOWS. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SARATHI BUNGALOWS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.