ReraGenieLog inGet a buyer report

Home / Browse projects / Surat, Gujarat / Santvan Skyon

Valid until 30 Jun 2022 Residential/Group Housing project

Santvan Skyon

By MARUTI CORPORATION

RG-GJ-51991 · RERA PR/GJ/SURAT/SURAT CITY/SUDA/RAA01181/020118 · Last updated on GujRERA portal: 5 Feb 2022

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
  • Separate project account declared
Jun 2022Possession promisedno revision filed
24 of 24Construction stages doneacross 3 buildings; every applicable stage filed complete
0 of 168Units unsoldnot recorded sold or booked
Jump to the 40 documents Report an error

Santvan Skyon is a Residential/Group Housing project by MARUTI CORPORATION in Surat, Gujarat, registered with GujRERA as PR/GJ/SURAT/SURAT CITY/SUDA/RAA01181/020118 on 2 Jan 2018. Possession is promised by 30 Jun 2022. 168 of the 168 units on this registration are recorded sold or booked, and 24 of 24 construction stages are filed complete.

At a glance

Project

  • NameSantvan Skyon
  • TypeResidential/Group Housing
  • Location
    • F.P.24
    • T.P.9(Palanpore)
    • Palanpore
    • Palanpor
    • Surat City
    • Surat
    • 395009
  • Pincode395009
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/SURAT/SURAT CITY/SUDA/RAA01181/020118
  • ReraGenie IDRG-GJ-51991

Builder

  • NameMARUTI CORPORATION
  • Entity typePARTNERSHIP FIRM
  • Other registrations6 more →

Key dates

this monthRegisteredJan 2018PromisedJun 2022

Key facts

Registration and timeline

  • StatusValid until 30 Jun 2022
  • Registered on2 Jan 2018
  • Promised completion30 Jun 2022
  • Revised completionNone
  • Buildings3 building records
  • Documents filed40 files

Current status

100%168 of 168 units booked
100.0%Of the estimated cost spent so far

Figures as on 5 Feb 2022, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---56056
B---56056
C---56056

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building3

As on 5 Feb 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

24 of 24 construction stages are filed complete across 3 buildings.

A100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
B100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
C100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 5 Feb 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsNoNot applicable
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)NoNot applicable
Storm water drainsNoNot applicable
Landscaping and tree plantingNoNot applicable
Street lightingNoNot applicable
Community buildingsYes100%
Treatment and disposal of sewage and sullage waterYes100%
Solid waste management and disposalYes100%
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,109 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 19.21 cr
Cost incurredRs 19.21 cr
Spent of the estimate100.0%
BuildingWingEstimatedIncurred
ANARs 6.40 crRs 6.40 cr
BNARs 6.40 crRs 6.40 cr
CNARs 6.40 crRs 6.40 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
Architectchirag sheta
Engineerramesh n shingala

Documents filed40

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/SURAT/SURAT CITY/SUDA/RAA01181/020118 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)5 Feb 2022
Engineer's certificate (Form 2)5 Feb 2022
Engineer's certificate annexure5 Feb 2022
Accountant's certificate (Form 3)5 Feb 2022
Site photograph, A5 Feb 2022
Site photograph, B5 Feb 2022
Site photograph, C5 Feb 2022
RERA registration certificate2 Jan 2018
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Surat

100%of this project is bookeddistrict median 39%
15%of Surat projects moved their completion datethis one has not

Computed across the 2,600+ Surat projects on ReraGenie, from their own filings.

Keep Santvan Skyon on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Palanpor2,600+ in Surat

2 kmSantvan SkyonOther 187Dot size: filed unitsN

Filed coordinates, straight-line distance. 187 registered projects within 2 km.

Builder: MARUTI CORPORATION

MARUTI CORPORATION has 7 registrations on GujRERA, including DREAM HEAVEN and Santvan Skyon. Read the full track record. See more projects on the Surat district page.

Frequently asked questions

What are my rights if Santvan Skyon is delayed beyond 30 Jun 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of Santvan Skyon?

The registered promoter entity is MARUTI CORPORATION, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in Santvan Skyon?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Santvan Skyon?

The professionals named in the filing: Architect: chirag sheta; Engineer: ramesh n shingala. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Santvan Skyon?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Santvan Skyon. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Santvan Skyon to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.