Home / Browse projects / Rajkot, Gujarat / SANKALP SIDDH

Valid until 30 Nov 2023 Residential/Group Housing project

SANKALP SIDDH

By MITUL DILIPBHAI GOSWAMI

RG-GJ-53473 · RERA PR/GJ/RAJKOT/RAJKOT/Others/RAA07101/050620 · Last updated on GujRERA portal: 6 Dec 2021

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
  • Separate project account declared
Nov 2023Possession promisedno revision filed
8 of 8Construction stages doneevery applicable stage filed complete
1 of 25Units unsoldnot recorded sold or booked
Jump to the 41 documents Report an error

SANKALP SIDDH is a Residential/Group Housing project by MITUL DILIPBHAI GOSWAMI in Rajkot, Gujarat, registered with GujRERA as PR/GJ/RAJKOT/RAJKOT/Others/RAA07101/050620 on 5 Jun 2020. Possession is promised by 30 Nov 2023. 24 of the 25 units on this registration are recorded sold or booked, and 8 of 8 construction stages are filed complete.

At a glance

Project

  • NameSANKALP SIDDH
  • TypeResidential/Group Housing
  • Location
    • KAILASH PARK STREET 13
    • NEAR GOPAL CHOWK SADHUVASVANO ROAD RAJKOT
    • Raiya
    • Rajkot
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/RAJKOT/RAJKOT/Others/RAA07101/050620
  • ReraGenie IDRG-GJ-53473

Builder

  • NameMITUL DILIPBHAI GOSWAMI
  • Entity typeIndividual/Propritorship

Key dates

this monthRegisteredJun 2020PromisedNov 2023

Key facts

Registration and timeline

  • StatusValid until 30 Nov 2023
  • Registered on5 Jun 2020
  • Promised completion30 Nov 2023
  • Revised completionNone
  • Buildings1 building record
  • Documents filed41 files

Current status

96%24 of 25 units booked
100.0%Of the estimated cost spent so far

Figures as on 6 Dec 2021, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SANKALP SIDDH---25025

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 6 Dec 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 8 construction stages are filed complete.

SANKALP SIDDH: 100% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 6 Dec 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsNoNot applicable
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingNoNot applicable
Street lightingNoNot applicable
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes100%
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationNoNot applicable
Fire fightingYes100%
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes100%
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area227 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 86.25 lakh
Cost incurredRs 86.25 lakh
Spent of the estimate100.0%
BuildingWingEstimatedIncurred
SANKALP SIDDHNARs 86.25 lakhRs 86.25 lakh

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectJAYESH BAXI
EngineerKETAN S DAVE

Documents filed41

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/RAJKOT/RAJKOT/Others/RAA07101/050620 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)6 Dec 2021
Engineer's certificate (Form 2)6 Dec 2021
Engineer's certificate annexure6 Dec 2021
Accountant's certificate (Form 3)6 Dec 2021
Site photograph, SANKALP SIDDH6 Dec 2021
RERA registration certificate5 Jun 2020
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Rajkot

96%of this project is bookeddistrict median 56%
13%of Rajkot projects moved their completion datethis one has not

Computed across the 1,800+ Rajkot projects on ReraGenie, from their own filings.

Keep SANKALP SIDDH on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Raiya1,800+ in Rajkot

2 kmSANKALP SIDDHOther 293Dot size: filed unitsN

Filed coordinates, straight-line distance. 293 registered projects within 2 km.

Builder: MITUL DILIPBHAI GOSWAMI

MITUL DILIPBHAI GOSWAMI has 1 registration on GujRERA, including SANKALP SIDDH. Read the full track record. See more projects on the Rajkot district page.

Frequently asked questions

What are my rights if SANKALP SIDDH is delayed beyond 30 Nov 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of SANKALP SIDDH?

The registered promoter entity is MITUL DILIPBHAI GOSWAMI, an individual/propritorship as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in SANKALP SIDDH?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SANKALP SIDDH?

The professionals named in the filing: Architect: JAYESH BAXI; Engineer: KETAN S DAVE. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SANKALP SIDDH?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SANKALP SIDDH. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SANKALP SIDDH to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.