Home / Browse projects / Ahmedabad, Gujarat / Sakar Sparsh

Valid until 6 May 2019 Residential/Group Housing project

Sakar Sparsh

By Sakar Buildcon

RG-GJ-48629 · RERA PR/GJ/AHMEDABAD/SANAND/AUDA/RAA01698/190218 · Last updated on GujRERA portal: 10 May 2019

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
  • Separate project account declared
May 2019Possession promisedno revision filed
624 of 624Construction stages doneacross 104 buildings; every applicable stage filed complete
Jump to the 139 documents Report an error

Sakar Sparsh is a Residential/Group Housing project by Sakar Buildcon in Ahmedabad, Gujarat, registered with GujRERA as PR/GJ/AHMEDABAD/SANAND/AUDA/RAA01698/190218 on 19 Feb 2018. Possession is promised by 6 May 2019.

At a glance

Project

  • NameSakar Sparsh
  • TypeResidential/Group Housing
  • Location
    • Sakar Sparsh
    • Behind Ganesh Park Society
    • Sanand Bavla Road
    • Sanand
    • Sanand
    • Ahmedabad
    • 382170
  • Pincode382170
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/AHMEDABAD/SANAND/AUDA/RAA01698/190218
  • ReraGenie IDRG-GJ-48629

Builder

  • NameSakar Buildcon
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredFeb 2018PromisedMay 2019

Key facts

Registration and timeline

  • StatusValid until 6 May 2019
  • Registered on19 Feb 2018
  • Promised completion6 May 2019
  • Revised completionNone
  • Buildings104 building records
  • Documents filed139 files

Current status

100.0%Of the estimated cost spent so far

Figures as on 10 May 2019, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
1-----1
2-----1
3-----1
4-----1
5-----1
6-----1
7-----1
8-----1
9-----1
10-----1
11-----1
12-----1
12A-----1
14-----1
15-----1
16-----1
17-----1
18-----1
19-----1
20-----1
21-----1
22-----1
23-----1
24-----1
25-----1
26-----1
27-----1
28-----1
29-----1
30-----1
31-----1
32-----1
33-----1
34-----1
35-----1
36-----1
37-----1
38-----1
39-----1
40-----1
41-----1
42-----1
43-----1
44-----1
45-----1
46-----1
47-----1
48-----1
49-----1
50-----1
51-----1
52-----1
53-----1
54-----1
55-----1
56-----1
57-----1
58-----1
59-----1
60-----1
61-----1
62-----1
63-----1
64-----1
65-----1
66-----1
67-----1
68-----1
69-----1
70-----1
71-----1
72-----1
73-----1
74-----1
75-----1
76-----1
77-----1
78-----1
79-----1
80-----1
81-----1
82-----1
83-----1
84-----1
85-----1
86-----1
87-----1
88-----1
89-----1
90-----1
91-----1
92-----1
93-----1
94-----1
95-----1
96-----1
97-----1
98-----1
99-----1
100-----1
101-----1
102-----1
103-----1
104-----1

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building20

As on 10 May 2019, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 104 buildings; the table lists the first 20.

624 of 624 construction stages are filed complete across 104 buildings.

1100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
2100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
3100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
4100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
5100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
6100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
7100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
8100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
9100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
10100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
11100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
12100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
12A100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
14100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
15100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
16100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
17100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
18100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
19100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
20100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 10 May 2019, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsYes100%
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes100%
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area12,127 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 9.43 cr
Cost incurredRs 9.43 cr
Spent of the estimate100.0%
BuildingWingEstimatedIncurred
1NARs 9.07 lakhRs 9.07 lakh
2NARs 9.07 lakhRs 9.07 lakh
3NARs 9.07 lakhRs 9.07 lakh
4NARs 9.07 lakhRs 9.07 lakh
5NARs 9.07 lakhRs 9.07 lakh
6NARs 9.07 lakhRs 9.07 lakh
7NARs 9.07 lakhRs 9.07 lakh
8NARs 9.07 lakhRs 9.07 lakh
9NARs 9.07 lakhRs 9.07 lakh
10NARs 9.07 lakhRs 9.07 lakh
11NARs 9.07 lakhRs 9.07 lakh
12NARs 9.07 lakhRs 9.07 lakh

Documents filed139

As listed on the registration, under the names the promoter filed them with; the newest 80 of 139 are shown. The files themselves are available at source: search the registration number PR/GJ/AHMEDABAD/SANAND/AUDA/RAA01698/190218 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)10 May 2019
Site photograph, 110 May 2019
Site photograph, 210 May 2019
Site photograph, 310 May 2019
Site photograph, 410 May 2019
Site photograph, 510 May 2019
Site photograph, 610 May 2019
Site photograph, 710 May 2019
Site photograph, 810 May 2019
Site photograph, 910 May 2019
Site photograph, 1010 May 2019
Site photograph, 1110 May 2019
Site photograph, 1210 May 2019
Site photograph, 12A10 May 2019
Site photograph, 1410 May 2019
Site photograph, 1510 May 2019
Site photograph, 1610 May 2019
Site photograph, 1710 May 2019
Site photograph, 1810 May 2019
Site photograph, 1910 May 2019
Site photograph, 2010 May 2019
Site photograph, 2110 May 2019
Site photograph, 2210 May 2019
Site photograph, 2310 May 2019
Site photograph, 2410 May 2019
Site photograph, 2510 May 2019
Site photograph, 2610 May 2019
Site photograph, 2710 May 2019
Site photograph, 2810 May 2019
Site photograph, 2910 May 2019
Site photograph, 3010 May 2019
Site photograph, 3110 May 2019
Site photograph, 3210 May 2019
Site photograph, 3310 May 2019
Site photograph, 3410 May 2019
Site photograph, 3510 May 2019
Site photograph, 3610 May 2019
Site photograph, 3710 May 2019
Site photograph, 3810 May 2019
Site photograph, 3910 May 2019
Site photograph, 4010 May 2019
Site photograph, 4110 May 2019
Site photograph, 4210 May 2019
Site photograph, 4310 May 2019
Site photograph, 4410 May 2019
Site photograph, 4510 May 2019
Site photograph, 4610 May 2019
Site photograph, 4710 May 2019
Site photograph, 4810 May 2019
Site photograph, 4910 May 2019
Site photograph, 5010 May 2019
Site photograph, 5110 May 2019
Site photograph, 5210 May 2019
Site photograph, 5310 May 2019
Site photograph, 5410 May 2019
Site photograph, 5510 May 2019
Site photograph, 5610 May 2019
Site photograph, 5710 May 2019
Site photograph, 5810 May 2019
Site photograph, 5910 May 2019
Site photograph, 6010 May 2019
Site photograph, 6110 May 2019
Site photograph, 6210 May 2019
Site photograph, 6310 May 2019
Site photograph, 6410 May 2019
Site photograph, 6510 May 2019
Site photograph, 6610 May 2019
Site photograph, 6710 May 2019
Site photograph, 6810 May 2019
Site photograph, 6910 May 2019
Site photograph, 7010 May 2019
Site photograph, 7110 May 2019
Site photograph, 7210 May 2019
Site photograph, 7310 May 2019
Site photograph, 7410 May 2019
Site photograph, 7510 May 2019
Site photograph, 7610 May 2019
Site photograph, 7710 May 2019
Site photograph, 7810 May 2019
Site photograph, 7910 May 2019

How this compares with Ahmedabad

14%of Ahmedabad projects moved their completion datethis one has not

Computed across the 5,400+ Ahmedabad projects on ReraGenie, from their own filings.

Keep Sakar Sparsh on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Sanand5,400+ in Ahmedabad

2 kmSakar SparshOther 83Dot size: filed unitsN

Filed coordinates, straight-line distance. 83 registered projects within 2 km.

Builder: Sakar Buildcon

Sakar Buildcon has 1 registration on GujRERA, including Sakar Sparsh. Read the full track record. See more projects on the Ahmedabad district page.

Frequently asked questions

What are my rights if Sakar Sparsh is delayed beyond 6 May 2019?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of Sakar Sparsh?

The registered promoter entity is Sakar Buildcon, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in Sakar Sparsh?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

What should I check before booking in Sakar Sparsh?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Sakar Sparsh. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Sakar Sparsh to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.