Home / Browse projects / Ahmedabad, Gujarat / SAI GREEN VALLEY 2

Valid until 30 Jun 2021 Mixed Development project

SAI GREEN VALLEY 2

By Sai Green Buildcon

RG-GJ-60229 · RERA PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA03256/A1M/290119 · Last updated on GujRERA portal: 15 Jun 2021

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
  • Separate project account declared
Jun 2021Possession promisedno revision filed
54 of 54Construction stages doneacross 6 buildings; every applicable stage filed complete
17 of 211Units unsoldnot recorded sold or booked
Jump to the 44 documents Report an error

SAI GREEN VALLEY 2 is a Mixed Development project by Sai Green Buildcon in Ahmedabad, Gujarat, registered with GujRERA as PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA03256/A1M/290119 on 27 Jul 2018. Possession is promised by 30 Jun 2021. 194 of the 211 units on this registration are recorded sold or booked, and 54 of 54 construction stages are filed complete.

At a glance

Project

  • NameSAI GREEN VALLEY 2
  • TypeMixed Development
  • Location
    • Sai Green Valley 2
    • Near Vibhusha Bunglows
    • B/h Kabir Enclave
    • Ghuma
    • Ghuma
    • Ahmedabad City
    • Ahmedabad
    • 380058
  • Pincode380058
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA03256/A1M/290119
  • ReraGenie IDRG-GJ-60229

Builder

  • NameSai Green Buildcon
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredJul 2018PromisedJun 2021

Key facts

Registration and timeline

  • StatusValid until 30 Jun 2021
  • Registered on27 Jul 2018
  • Promised completion30 Jun 2021
  • Revised completionNone
  • Buildings6 building records
  • Documents filed44 files

Current status

92%194 of 211 units booked
100.0%Of the estimated cost spent so far

Figures as on 15 Jun 2021, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---28028
B---28028
C---28028
D---28533
E+F---56460
G---28634

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building6

As on 15 Jun 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

54 of 54 construction stages are filed complete across 6 buildings.

A100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
B100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
C100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
D100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
E+F100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
G100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 15 Jun 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)NoNot applicable
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes100%
Letter boxYes100%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,553 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 26.28 cr
Cost incurredRs 26.28 cr
Spent of the estimate100.0%
BuildingWingEstimatedIncurred
ANARs 4.38 crRs 4.38 cr
BNARs 4.38 crRs 4.38 cr
CNARs 4.38 crRs 4.38 cr
DNARs 4.38 crRs 4.38 cr
E+FNARs 4.38 crRs 4.38 cr
GNARs 4.38 crRs 4.38 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNrupesh Shah
EngineerKetav P Joshi

Documents filed44

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA03256/A1M/290119 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)15 Jun 2021
Architect's certificate (Form 1)14 Jun 2021
Engineer's certificate (Form 2)14 Jun 2021
Engineer's certificate annexure14 Jun 2021
Site photograph, A14 Jun 2021
Site photograph, B14 Jun 2021
Site photograph, C14 Jun 2021
Site photograph, D14 Jun 2021
Site photograph, E+F14 Jun 2021
Site photograph, E+F14 Jun 2021
Site photograph, G14 Jun 2021
RERA registration certificate27 Jul 2018
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Ahmedabad

92%of this project is bookeddistrict median 53%
14%of Ahmedabad projects moved their completion datethis one has not

Computed across the 5,400+ Ahmedabad projects on ReraGenie, from their own filings.

Keep SAI GREEN VALLEY 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Ghuma5,400+ in Ahmedabad

2 kmSAI GREEN VALLEY 2Other 140Dot size: filed unitsN

Filed coordinates, straight-line distance. 140 registered projects within 2 km.

Builder: Sai Green Buildcon

Sai Green Buildcon has 1 registration on GujRERA, including SAI GREEN VALLEY 2. Read the full track record. See more projects on the Ahmedabad district page.

Frequently asked questions

What are my rights if SAI GREEN VALLEY 2 is delayed beyond 30 Jun 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of SAI GREEN VALLEY 2?

The registered promoter entity is Sai Green Buildcon, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in SAI GREEN VALLEY 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SAI GREEN VALLEY 2?

The professionals named in the filing: Architect: Nrupesh Shah; Engineer: Ketav P Joshi. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SAI GREEN VALLEY 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SAI GREEN VALLEY 2. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SAI GREEN VALLEY 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.