Valid until 28 Feb 2024 Residential/Group Housing project

Rikti Complex

By Rikti Corporation

RG-GJ-16575 · RERA PR/GJ/VALSAD/PARDI/Others/RAA06462/EX1/270923 · Last updated on GujRERA portal: 7 Mar 2023

Source: official GujRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • Separate project account declared
Feb 2024Possession promisedmoved 12 months from the original
5 of 7Construction stages donefurthest along: Internal walls, 80%
20 of 20Units unsoldnot recorded sold or booked
Jump to the 41 documents Report an error

Rikti Complex is a Residential/Group Housing project by Rikti Corporation in Valsad, Gujarat, registered with GujRERA as PR/GJ/VALSAD/PARDI/Others/RAA06462/EX1/270923 on 12 Dec 2019. Possession is promised by 28 Feb 2024. The completion date has moved by 12 months from the original filing. 0 of the 20 units on this registration are recorded sold or booked, and 5 of 7 construction stages are filed complete.

At a glance

Project

  • NameRikti Complex
  • TypeResidential/Group Housing
  • Location
    • City Survey No. 1479/B
    • Gayatri Society
    • Near Phynayle Factory
    • Near N.H. No. 8
    • Killa Pardi
    • Pardi
    • Valsad
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VALSAD/PARDI/Others/RAA06462/EX1/270923
  • ReraGenie IDRG-GJ-16575

Builder

  • NameRikti Corporation
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredDec 2019First promiseFeb 2023Revised toFeb 2024

Key facts

Registration and timeline

  • StatusValid until 28 Feb 2024
  • Registered on12 Dec 2019
  • Promised completion28 Feb 2024
  • Revised completionRevised to 28 Feb 2024 (originally 28 Feb 2023)
  • Buildings1 building record
  • Documents filed41 files

Current status

0%0 of 20 units booked
56.7%Of the estimated cost spent so far

Figures as on 7 Mar 2023, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Rikti Complex---20020

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 7 Mar 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 7 construction stages are filed complete. The stage furthest along is Internal walls, at 80%.

Rikti Complex: 83% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats80%
Sanitary fittings within the flatsNot applicable
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%

Progress on shared amenities19

As on 7 Mar 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsNoNot applicable
Landscaping and tree plantingYes0%
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingYes0%
Drinking water facilitiesYes0%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area713 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 2.19 cr
Cost incurredRs 1.24 cr
Spent of the estimate56.73%
BuildingWingEstimatedIncurred
Rikti ComplexNARs 2.19 crRs 1.24 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKushkuvar Y. Shah
EngineerManish A. Shah

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/VALSAD/PARDI/Others/RAA06462/EX1/270923Applied Mar 2023; approved Sep 2023

Documents filed41

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VALSAD/PARDI/Others/RAA06462/EX1/270923 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)7 Mar 2023
Site photograph, Rikti Complex7 Mar 2023
Engineer's certificate (Form 2)7 Jan 2023
Engineer's certificate annexure7 Jan 2023
Accountant's certificate (Form 3)7 Jan 2023
RERA registration certificate12 Dec 2019
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Valsad

0%of this project is bookeddistrict median 45%
23%of Valsad projects moved their completion datethis one moved by 12 months

Computed across the 390+ Valsad projects on ReraGenie, from their own filings.

Keep Rikti Complex on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Pardi390+ in Valsad

2 kmRikti ComplexOther 25Dot size: filed unitsN

Filed coordinates, straight-line distance. 25 registered projects within 2 km.

Builder: Rikti Corporation

Rikti Corporation has 1 registration on GujRERA, including Rikti Complex. Read the full track record. See more projects on the Valsad district page.

Frequently asked questions

What are my rights if Rikti Complex is delayed beyond 28 Feb 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of Rikti Complex?

The registered promoter entity is Rikti Corporation, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in Rikti Complex?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Rikti Complex?

The professionals named in the filing: Architect: Kushkuvar Y. Shah; Engineer: Manish A. Shah. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Rikti Complex?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Rikti Complex. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Rikti Complex to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.