Home / Browse projects / Ahmedabad, Gujarat / RASHMI ANGAN

Valid until 4 Feb 2023 Residential/Group Housing project

RASHMI ANGAN

By RASHMI ENGICON PRIVATE LIMITED

RG-GJ-33844 · RERA PR/GJ/AHMEDABAD/SANAND/AUDA/RAA01038/EX2/210622 · Last updated on GujRERA portal: 6 Jan 2023

Source: official GujRERA filing

Red flags

  • Completion date moved by 24 months
  • 2 extensions taken

Clear

  • Nothing verified clear yet
Feb 2023Possession promisedmoved 24 months from the original
56 of 56Construction stages doneacross 8 buildings; every applicable stage filed complete
66 of 180Units unsoldnot recorded sold or booked
Jump to the 44 documents Report an error

RASHMI ANGAN is a Residential/Group Housing project by RASHMI ENGICON PRIVATE LIMITED in Ahmedabad, Gujarat, registered with GujRERA as PR/GJ/AHMEDABAD/SANAND/AUDA/RAA01038/EX2/210622 on 16 Dec 2017. Possession is promised by 4 Feb 2023. The completion date has moved by 24 months from the original filing. 114 of the 180 units on this registration are recorded sold or booked, and 56 of 56 construction stages are filed complete.

At a glance

Project

  • NameRASHMI ANGAN
  • TypeResidential/Group Housing
  • Location
    • RASHMI ANGAN
    • SANAND VIRMGAM HIGHWAY SANAND
    • Sanand
    • Ahmedabad
    • 382170
  • Pincode382170
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/AHMEDABAD/SANAND/AUDA/RAA01038/EX2/210622
  • ReraGenie IDRG-GJ-33844

Builder

  • NameRASHMI ENGICON PRIVATE LIMITED
  • Entity typeCOMPANY
  • Other registrations1 more →

Key dates

this monthRegisteredDec 2017First promiseFeb 2021Revised toFeb 2023

Key facts

Registration and timeline

  • StatusValid until 4 Feb 2023
  • Registered on16 Dec 2017
  • Promised completion4 Feb 2023
  • Revised completionRevised to 4 Feb 2023 (originally 4 Feb 2021)
  • Buildings8 building records
  • Documents filed44 files

Current status

63%114 of 180 units booked
100.0%Of the estimated cost spent so far

Figures as on 6 Jan 2023, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
H---30030
A---20020
B---20020
C---30030
D---20020
E---20020
F---20020
G---20020

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building8

As on 6 Jan 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

56 of 56 construction stages are filed complete across 8 buildings.

H100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
A100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
B100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
C100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
D100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
E100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
F100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
G100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 6 Jan 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes100%
Water conservation, rain water harvestingYes100%
Energy managementYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,888 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 15.55 cr
Cost incurredRs 15.55 cr
Spent of the estimate100.0%
BuildingWingEstimatedIncurred
ANARs 1.94 crRs 1.94 cr
BNARs 1.94 crRs 1.94 cr
CNARs 1.94 crRs 1.94 cr
DNARs 1.94 crRs 1.94 cr
ENARs 1.94 crRs 1.94 cr
FNARs 1.94 crRs 1.94 cr
GNARs 1.94 crRs 1.94 cr
HNARs 1.94 crRs 1.94 cr

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/AHMEDABAD/SANAND/AUDA/RAA01038/EX1/220421Applied Feb 2021; approved Apr 2021
PR/GJ/AHMEDABAD/SANAND/AUDA/RAA01038/EX2/210622Applied Jun 2022; approved Jun 2022

Documents filed44

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/AHMEDABAD/SANAND/AUDA/RAA01038/EX2/210622 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)6 Jan 2023
Engineer's certificate (Form 2)6 Jan 2023
Engineer's certificate annexure6 Jan 2023
Accountant's certificate (Form 3)6 Jan 2023
Site photograph, H6 Jan 2023
Site photograph, A6 Jan 2023
Site photograph, B6 Jan 2023
Site photograph, C6 Jan 2023
Site photograph, D6 Jan 2023
Site photograph, E6 Jan 2023
Site photograph, F6 Jan 2023
Site photograph, G6 Jan 2023
RERA registration certificate16 Dec 2017
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Ahmedabad

63%of this project is bookeddistrict median 53%
14%of Ahmedabad projects moved their completion datethis one moved by 24 months

Computed across the 5,400+ Ahmedabad projects on ReraGenie, from their own filings.

Keep RASHMI ANGAN on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Sanand5,400+ in Ahmedabad

2 kmRASHMI ANGANOther 51Dot size: filed unitsN

Filed coordinates, straight-line distance. 51 registered projects within 2 km.

Builder: RASHMI ENGICON PRIVATE LIMITED

RASHMI ENGICON PRIVATE LIMITED has 2 registrations on GujRERA, including RASHMI ANGAN and RASHMI ANTELIA. Read the full track record. See more projects on the Ahmedabad district page.

Frequently asked questions

What are my rights if RASHMI ANGAN is delayed beyond 4 Feb 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of RASHMI ANGAN?

The registered promoter entity is RASHMI ENGICON PRIVATE LIMITED, a company as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in RASHMI ANGAN?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

What should I check before booking in RASHMI ANGAN?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About RASHMI ANGAN. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save RASHMI ANGAN to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.