Valid until 31 Dec 2023 Plotted Development project

Ramdev Park 1

By BHARTIBENPARBATBHAIODEDRA AND OTHERS

RG-GJ-50380 · RERA PR/GJ/JUNAGADH/KESHOD/Others/PAA07799/181220 · Last updated on GujRERA portal: 7 Oct 2023

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
  • Separate project account declared
Dec 2023Possession promisedno revision filed
38 of 64Units unsoldnot recorded sold or booked
Jump to the 41 documents Report an error

Ramdev Park 1 is a Plotted Development project by BHARTIBENPARBATBHAIODEDRA AND OTHERS in Junagadh, Gujarat, registered with GujRERA as PR/GJ/JUNAGADH/KESHOD/Others/PAA07799/181220 on 18 Dec 2020. Possession is promised by 31 Dec 2023. 26 of the 64 units on this registration are recorded sold or booked.

At a glance

Project

  • NameRamdev Park 1
  • TypePlotted Development
  • Location
    • T.B. Hospital road
    • near Ganganath Para or Meghana society
    • Keshod
    • Keshod
    • Junagadh
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/JUNAGADH/KESHOD/Others/PAA07799/181220
  • ReraGenie IDRG-GJ-50380

Builder

  • NameBHARTIBENPARBATBHAIODEDRA AND OTHERS
  • Entity typeOther
  • Other registrations1 more →

Key dates

this monthRegisteredDec 2020PromisedDec 2023

Key facts

Registration and timeline

  • StatusValid until 31 Dec 2023
  • Registered on18 Dec 2020
  • Promised completion31 Dec 2023
  • Revised completionNone
  • Buildings1 building record
  • Documents filed41 files

Current status

41%26 of 64 units booked
116.5%Of the estimated cost spent so far

Figures as on 7 Oct 2023, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Plotting Scheme---64064

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 7 Oct 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Plotting Scheme:

ActivityProgress
ExcavationNot applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flatsNot applicable
Sanitary fittings within the flatsNot applicable
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofingNot applicable
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable

Progress on shared amenities19

As on 7 Oct 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsNoNot applicable
Landscaping and tree plantingNoNot applicable
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area7,743 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 30.00 lakh
Cost incurredRs 34.94 lakh
Spent of the estimate116.45%
BuildingWingEstimatedIncurred
Plotting SchemeNARs 30.00 lakhRs 34.94 lakh

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKrishnkant A. Pandat
EngineerKIRITBHAI TRAMBADIYA

Documents filed41

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/JUNAGADH/KESHOD/Others/PAA07799/181220 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)7 Oct 2023
Engineer's certificate (Form 2)7 Oct 2023
Engineer's certificate annexure7 Oct 2023
Accountant's certificate (Form 3)7 Oct 2023
Site photograph, Plotting Scheme7 Oct 2023
RERA registration certificate18 Dec 2020
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Junagadh

41%of this project is bookeddistrict median 32%
7%of Junagadh projects moved their completion datethis one has not

Computed across the 240+ Junagadh projects on ReraGenie, from their own filings.

Keep Ramdev Park 1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Keshod240+ in Junagadh

2 kmRamdev Park 1Other 8Dot size: filed unitsN

Filed coordinates, straight-line distance. 8 registered projects within 2 km.

Builder: BHARTIBENPARBATBHAIODEDRA AND OTHERS

BHARTIBENPARBATBHAIODEDRA AND OTHERS has 2 registrations on GujRERA, including Ramdev Park 2 and Ramdev Park 1. Read the full track record. See more projects on the Junagadh district page.

Frequently asked questions

What are my rights if Ramdev Park 1 is delayed beyond 31 Dec 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of Ramdev Park 1?

The registered promoter entity is BHARTIBENPARBATBHAIODEDRA AND OTHERS. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in Ramdev Park 1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Ramdev Park 1?

The professionals named in the filing: Architect: Krishnkant A. Pandat; Engineer: KIRITBHAI TRAMBADIYA. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Ramdev Park 1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Ramdev Park 1. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Ramdev Park 1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.