Home / Browse projects / Kutch, Gujarat / RAJVI PARK

Valid until 30 Jun 2024 Residential/Group Housing project

RAJVI PARK

By RAJVI ESTATE LLP

RG-GJ-39215 · RERA PR/GJ/KUTCH/GANDHIDHAM/Others/RAA02493/250418 · Last updated on GujRERA portal: 15 Apr 2024

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
  • Separate project account declared
Jun 2024Possession promisedno revision filed
136 of 153Construction stages doneacross 17 buildings; furthest along: Stilt Floor, 0%
77 of 158Units unsoldnot recorded sold or booked
Jump to the 54 documents Report an error

RAJVI PARK is a Residential/Group Housing project by RAJVI ESTATE LLP in Kutch, Gujarat, registered with GujRERA as PR/GJ/KUTCH/GANDHIDHAM/Others/RAA02493/250418 on 25 Apr 2018. Possession is promised by 30 Jun 2024. 81 of the 158 units on this registration are recorded sold or booked, and 136 of 153 construction stages are filed complete.

At a glance

Project

  • NameRAJVI PARK
  • TypeResidential/Group Housing
  • Location
    • SURVEY NO. 33
    • KIDANA
    • Kidana
    • Gandhidham
    • Kutch
    • 370230
  • Pincode370230
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/KUTCH/GANDHIDHAM/Others/RAA02493/250418
  • ReraGenie IDRG-GJ-39215

Builder

  • NameRAJVI ESTATE LLP
  • Entity typeLIMITED LIABILITY PARTNERSHIP FIRM
  • Other registrations5 more →

Key dates

this monthRegisteredApr 2018PromisedJun 2024

Key facts

Registration and timeline

  • StatusValid until 30 Jun 2024
  • Registered on25 Apr 2018
  • Promised completion30 Jun 2024
  • Revised completionNone
  • Buildings17 building records
  • Documents filed54 files

Current status

51%81 of 158 units booked
100.0%Of the estimated cost spent so far

Figures as on 15 Apr 2024, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
5 to 10---606
44 to 54---11011
55 to 65---11011
101 to 110---10010
111 to 117---707
170 to 179---10010
180 to 189---10010
261 to 267---707
268 to 270---303
158 to 169---12012
190 to 201---12012
249 to 260---12012
271 to 282---12012
343 to 346---404
331 to 342---12012
347 to 358---12012
407 to 413---707

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building17

As on 15 Apr 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

136 of 153 construction stages are filed complete across 17 buildings. The stage furthest along is Stilt Floor, at 0%.

5 to 1089%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
44 to 5489%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
55 to 6589%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
101 to 11089%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
111 to 11789%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
170 to 17989%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
180 to 18989%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
261 to 26789%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
268 to 27089%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
158 to 16989%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
190 to 20189%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
249 to 26089%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
271 to 28289%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
343 to 34689%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
331 to 34289%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
347 to 35889%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
407 to 41389%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 15 Apr 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsNoNot applicable
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsYes100%
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingNoNot applicable
Drinking water facilitiesYes100%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area10,063 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 9.24 cr
Cost incurredRs 9.24 cr
Spent of the estimate100.0%
BuildingWingEstimatedIncurred
101 to 110NARs 54.35 lakhRs 54.35 lakh
111 to 117NARs 54.35 lakhRs 54.35 lakh
158 to 169NARs 54.35 lakhRs 54.35 lakh
170 to 179NARs 54.35 lakhRs 54.35 lakh
180 to 189NARs 54.35 lakhRs 54.35 lakh
190 to 201NARs 54.35 lakhRs 54.35 lakh
249 to 260NARs 54.35 lakhRs 54.35 lakh
261 to 267NARs 54.35 lakhRs 54.35 lakh
268 to 270NARs 54.35 lakhRs 54.35 lakh
271 to 282NARs 54.35 lakhRs 54.35 lakh
331 to 342NARs 54.35 lakhRs 54.35 lakh
343 to 346NARs 54.35 lakhRs 54.35 lakh

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDIVYESH DESAI & ASSOCIATES
EngineerKALPEN D SOMPURA

Documents filed54

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/KUTCH/GANDHIDHAM/Others/RAA02493/250418 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineer's certificate (Form 2)15 Apr 2024
Engineer's certificate annexure15 Apr 2024
Accountant's certificate (Form 3)15 Apr 2024
Architect's certificate (Form 1)12 Apr 2024
Site photograph, 5 to 1029 Mar 2024
Site photograph, 44 to 5429 Mar 2024
Site photograph, 55 to 6529 Mar 2024
Site photograph, 101 to 11029 Mar 2024
Site photograph, 111 to 11729 Mar 2024
Site photograph, 170 to 17929 Mar 2024
Site photograph, 180 to 18929 Mar 2024
Site photograph, 261 to 26729 Mar 2024
Site photograph, 268 to 27029 Mar 2024
Site photograph, 158 to 16929 Mar 2024
Site photograph, 190 to 20129 Mar 2024
Site photograph, 249 to 26029 Mar 2024
Site photograph, 271 to 28229 Mar 2024
Site photograph, 343 to 34629 Mar 2024
Site photograph, 331 to 34229 Mar 2024
Site photograph, 347 to 35829 Mar 2024
Site photograph, 407 to 41329 Mar 2024
RERA registration certificate25 Apr 2018
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Kutch

51%of this project is bookeddistrict median 42%
6%of Kutch projects moved their completion datethis one has not

Computed across the 80 Kutch projects on ReraGenie, from their own filings.

Keep RAJVI PARK on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Kidana80 in Kutch

Builder: RAJVI ESTATE LLP

RAJVI ESTATE LLP has 6 registrations on GujRERA, including Riviera Elegance II and Riviera Elegance II Bungalows. Read the full track record. See more projects on the Kutch district page.

Frequently asked questions

What are my rights if RAJVI PARK is delayed beyond 30 Jun 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of RAJVI PARK?

The registered promoter entity is RAJVI ESTATE LLP, a limited liability partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in RAJVI PARK?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at RAJVI PARK?

The professionals named in the filing: Architect: DIVYESH DESAI & ASSOCIATES; Engineer: KALPEN D SOMPURA. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in RAJVI PARK?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About RAJVI PARK. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save RAJVI PARK to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.