ReraGenieLog inGet a buyer report

Home / Browse projects / Surat, Gujarat / Rajhans Stadium Plaza & residency

Valid until 31 May 2020 Mixed Development project

Rajhans Stadium Plaza & residency

By RAJHANS INFRABUILD LLP

RG-GJ-30012 · RERA PR/GJ/SURAT/SURAT CITY/SUDA/MAA00087/070917 · Last updated on GujRERA portal: 12 Feb 2020

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
  • Separate project account declared
May 2020Possession promisedno revision filed
38 of 41Construction stages doneacross 5 buildings; furthest along: Sanitary fittings within the flats, 0%
207 of 322Units unsoldnot recorded sold or booked
Jump to the 44 documents Report an error

Rajhans Stadium Plaza & residency is a Mixed Development project by RAJHANS INFRABUILD LLP in Surat, Gujarat, registered with GujRERA as PR/GJ/SURAT/SURAT CITY/SUDA/MAA00087/070917 on 7 Sep 2017. Possession is promised by 31 May 2020. 115 of the 322 units on this registration are recorded sold or booked, and 38 of 41 construction stages are filed complete.

At a glance

Project

  • NameRajhans Stadium Plaza & residency
  • TypeMixed Development
  • Location
    • T.P.S. (Palanpor-Bhesan)
    • Final Plot No 26
    • Palanpor
    • Surat City
    • Surat
    • 395009
  • Pincode395009
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/SURAT/SURAT CITY/SUDA/MAA00087/070917
  • ReraGenie IDRG-GJ-30012

Builder

  • NameRAJHANS INFRABUILD LLP
  • Entity typeLIMITED LIABILITY PARTNERSHIP FIRM
  • Other registrations2 more →

Key dates

this monthRegisteredSep 2017PromisedMay 2020

Key facts

Registration and timeline

  • StatusValid until 31 May 2020
  • Registered on7 Sep 2017
  • Promised completion31 May 2020
  • Revised completionNone
  • Buildings5 building records
  • Documents filed44 files

Current status

36%115 of 322 units booked
100.0%Of the estimated cost spent so far

Figures as on 12 Feb 2020, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Commercial---0202202
A+B---40040
C---20020
D+E---40040
F---20020

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building5

As on 12 Feb 2020, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

38 of 41 construction stages are filed complete across 5 buildings. The stage furthest along is Sanitary fittings within the flats, at 0%.

Commercial88%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
A+B89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
C100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
D+E88%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
F100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 12 Feb 2020, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsNoNot applicable
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingYes0%
Drinking water facilitiesYes0%
Emergency evacuationYes0%
Use of renewable energyNoNot applicable
SecurityYes100%
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area9,262 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 22.50 cr
Cost incurredRs 22.50 cr
Spent of the estimate100.0%
BuildingWingEstimatedIncurred
CommercialNARs 4.50 crRs 4.50 cr
A+BNARs 4.50 crRs 4.50 cr
CNARs 4.50 crRs 4.50 cr
D+ENARs 4.50 crRs 4.50 cr
FNARs 4.50 crRs 4.50 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAr. Haresh J. Mahadevwala
EngineerJalil Abdulbahi Sheikh

Documents filed44

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/SURAT/SURAT CITY/SUDA/MAA00087/070917 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)12 Feb 2020
Architect's certificate (Form 1)1 Feb 2020
Engineer's certificate (Form 2)1 Feb 2020
Engineer's certificate annexure1 Feb 2020
Site photograph, Commercial1 Feb 2020
Site photograph, A+B1 Feb 2020
Site photograph, A+B1 Feb 2020
Site photograph, C1 Feb 2020
Site photograph, D+E1 Feb 2020
Site photograph, D+E1 Feb 2020
Site photograph, F1 Feb 2020
RERA registration certificate7 Sep 2017
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Surat

36%of this project is bookeddistrict median 39%
15%of Surat projects moved their completion datethis one has not

Computed across the 2,600+ Surat projects on ReraGenie, from their own filings.

Keep Rajhans Stadium Plaza & residency on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Palanpor2,600+ in Surat

2 kmRajhans Stadium Plaza & Other 178Dot size: filed unitsN

Filed coordinates, straight-line distance. 178 registered projects within 2 km.

Builder: RAJHANS INFRABUILD LLP

RAJHANS INFRABUILD LLP has 3 registrations on GujRERA, including Rajhans Stadium Plaza & residency and RAJHANS PLATINUM RESIDENCY. Read the full track record. See more projects on the Surat district page.

Frequently asked questions

What are my rights if Rajhans Stadium Plaza & residency is delayed beyond 31 May 2020?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of Rajhans Stadium Plaza & residency?

The registered promoter entity is RAJHANS INFRABUILD LLP, a limited liability partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in Rajhans Stadium Plaza & residency?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Rajhans Stadium Plaza & residency?

The professionals named in the filing: Architect: Ar. Haresh J. Mahadevwala; Engineer: Jalil Abdulbahi Sheikh. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Rajhans Stadium Plaza & residency?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Rajhans Stadium Plaza & residency. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Rajhans Stadium Plaza & residency to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.