Valid until 30 Apr 2028 Residential/Group Housing project

Rajeshwari Pride

By RAJESHWARI BUILDERS

RG-GJ-80237 · RERA PR/GJ/MEHSANA/KADI/Kadi Municipality/RAA13225/010424/311227 · Last updated on GujRERA portal: 14 Jul 2026

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Apr 2028Possession promisedno revision filed
57 of 63Construction stages doneacross 7 buildings; furthest along: Installation of lifts, 67%
2 of 19Units unsoldnot recorded sold or booked
Jump to the 43 documents Report an error

Rajeshwari Pride is a Residential/Group Housing project by RAJESHWARI BUILDERS in Mehsana, Gujarat, registered with GujRERA as PR/GJ/MEHSANA/KADI/Kadi Municipality/RAA13225/010424/311227 on 1 Apr 2024. Possession is promised by 30 Apr 2028. 17 of the 19 units on this registration are recorded sold or booked, and 57 of 63 construction stages are filed complete.

At a glance

Project

  • NameRajeshwari Pride
  • TypeResidential/Group Housing
  • Location
    • Beside Rajeshwary Icon
    • Opp. Seva Sadan
    • Kadi Karannagar Road
    • Kadi.
    • KADI - KASBA
    • Kadi
    • Mehsana
    • 382715
  • Pincode382715
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/MEHSANA/KADI/Kadi Municipality/RAA13225/010424/311227
  • ReraGenie IDRG-GJ-80237

Builder

  • NameRAJESHWARI BUILDERS
  • Entity typePARTNERSHIP FIRM
  • Other registrations1 more →

Key dates

this monthRegisteredApr 2024PromisedApr 2028

Key facts

Registration and timeline

  • StatusValid until 30 Apr 2028
  • Registered on1 Apr 2024
  • Promised completion30 Apr 2028
  • Revised completionNone
  • Buildings7 building records
  • Documents filed43 files

Current status

89%17 of 19 units booked
61.4%Of the estimated cost spent so far

Figures as on 14 Jul 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Type B---303
Type A---303
Type D---303
Type C---101
Type F---303
Type E---303
Type G---303

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building7

As on 14 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

57 of 63 construction stages are filed complete across 7 buildings. The stage furthest along is Installation of lifts, at 67%.

Type B96%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing67%
Type A96%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing67%
Type D96%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing67%
Type C100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Type F96%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing67%
Type E96%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing67%
Type G96%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing67%

Progress on shared amenities19

As on 14 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes100%
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Fire fightingNoNot applicable
Drinking water facilitiesYes100%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes100%
Letter boxYes100%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,766 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 4.78 cr
Cost incurredRs 2.93 cr
Spent of the estimate61.38%
BuildingWingEstimatedIncurred
Type BNARs 87.77 lakhRs 56.09 lakh
Type FNARs 73.97 lakhRs 43.97 lakh
Type GNARs 73.97 lakhRs 43.97 lakh
Type ENARs 72.79 lakhRs 42.28 lakh
Type DNARs 72.78 lakhRs 46.54 lakh
Type ANARs 67.31 lakhRs 43.06 lakh
Type CNARs 29.19 lakhRs 17.35 lakh

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectHarsh Sureshbhai Patel
EngineerKALPESHBHAI BACHUBHAI PATEL

Documents filed43

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/MEHSANA/KADI/Kadi Municipality/RAA13225/010424/311227 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)14 Jul 2026
Engineer's certificate (Form 2)14 Jul 2026
Engineer's certificate annexure14 Jul 2026
Accountant's certificate (Form 3)14 Jul 2026
Site photograph, Type B14 Jul 2026
Site photograph, Type A14 Jul 2026
Site photograph, Type D14 Jul 2026
Site photograph, Type C14 Jul 2026
Site photograph, Type F14 Jul 2026
Site photograph, Type E14 Jul 2026
Site photograph, Type G14 Jul 2026
RERA registration certificate1 Apr 2024
Proforma agreement for sale-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Drainage affidavit-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Approved sanctioned plan-
Approved layout plan-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Declaration in Form B-
Approved building or plotting plan-
NOCs from authorities-
Title clearance certificate-
Title report-
Property card-
Statutory document-
Project photograph-
Proforma sale deed-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Mehsana

89%of this project is bookeddistrict median 54%
11%of Mehsana projects moved their completion datethis one has not

Computed across the 200+ Mehsana projects on ReraGenie, from their own filings.

Keep Rajeshwari Pride on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near KADI - KASBA200+ in Mehsana

2 kmRajeshwari PrideOther 68Dot size: filed unitsN

Filed coordinates, straight-line distance. 68 registered projects within 2 km.

Builder: RAJESHWARI BUILDERS

RAJESHWARI BUILDERS has 2 registrations on GujRERA, including Rajeshwari Icon and Rajeshwari Pride. Read the full track record. See more projects on the Mehsana district page.

Frequently asked questions

What are my rights if Rajeshwari Pride is delayed beyond 30 Apr 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of Rajeshwari Pride?

The registered promoter entity is RAJESHWARI BUILDERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in Rajeshwari Pride?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Rajeshwari Pride?

The professionals named in the filing: Architect: Harsh Sureshbhai Patel; Engineer: KALPESHBHAI BACHUBHAI PATEL. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Rajeshwari Pride?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Rajeshwari Pride. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Rajeshwari Pride to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.