Home / Browse projects / Surat, Gujarat / RAJ VICTORIA

Valid until 30 Jun 2022 Mixed Development project

RAJ VICTORIA

By RAJ DEVELOPERS

RG-GJ-59724 · RERA PR/GJ/SURAT/SURAT CITY/SUDA/MAA04016/EX1/141021 · Last updated on GujRERA portal: 3 May 2022

Source: official GujRERA filing

Red flags

  • Completion date moved by 9 months
  • 1 extension taken

Clear

  • Separate project account declared
Jun 2022Possession promisedmoved 9 months from the original
18 of 18Construction stages doneacross 2 buildings; every applicable stage filed complete
13 of 125Units unsoldnot recorded sold or booked
Jump to the 39 documents Report an error

RAJ VICTORIA is a Mixed Development project by RAJ DEVELOPERS in Surat, Gujarat, registered with GujRERA as PR/GJ/SURAT/SURAT CITY/SUDA/MAA04016/EX1/141021 on 14 Nov 2018. Possession is promised by 30 Jun 2022. The completion date has moved by 9 months from the original filing. 112 of the 125 units on this registration are recorded sold or booked, and 18 of 18 construction stages are filed complete.

At a glance

Project

  • NameRAJ VICTORIA
  • TypeMixed Development
  • Location
    • F.P. 52
    • T.P. 61 (PARVAT-GODADRA)
    • Surat
    • Surat City
    • 395012
  • Pincode395012
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/SURAT/SURAT CITY/SUDA/MAA04016/EX1/141021
  • ReraGenie IDRG-GJ-59724

Builder

  • NameRAJ DEVELOPERS
  • Entity typePARTNERSHIP FIRM
  • Other registrations9 more →

Key dates

this monthRegisteredNov 2018First promiseSep 2021Revised toJun 2022

Key facts

Registration and timeline

  • StatusValid until 30 Jun 2022
  • Registered on14 Nov 2018
  • Promised completion30 Jun 2022
  • Revised completionRevised to 30 Jun 2022 (originally 30 Sep 2021)
  • Buildings2 building records
  • Documents filed39 files

Current status

90%112 of 125 units booked
100.0%Of the estimated cost spent so far

Figures as on 3 May 2022, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---521769
B---56056

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building2

As on 3 May 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

18 of 18 construction stages are filed complete across 2 buildings.

A100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
B100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 3 May 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,904 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 7.32 cr
Cost incurredRs 7.32 cr
Spent of the estimate100.0%
BuildingWingEstimatedIncurred
ANARs 3.66 crRs 3.66 cr
BNARs 3.66 crRs 3.66 cr

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/SURAT/SURAT CITY/SUDA/MAA04016/EX1/141021Applied Sep 2021; approved Oct 2021

Documents filed39

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/SURAT/SURAT CITY/SUDA/MAA04016/EX1/141021 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)3 May 2022
Engineer's certificate (Form 2)3 May 2022
Engineer's certificate annexure3 May 2022
Accountant's certificate (Form 3)3 May 2022
Site photograph, A3 May 2022
Site photograph, A3 May 2022
Site photograph, B3 May 2022
RERA registration certificate14 Nov 2018
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Surat

90%of this project is bookeddistrict median 39%
15%of Surat projects moved their completion datethis one moved by 9 months

Computed across the 2,600+ Surat projects on ReraGenie, from their own filings.

Keep RAJ VICTORIA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Surat2,600+ in Surat

2 kmRAJ VICTORIAOther 131Dot size: filed unitsN

Filed coordinates, straight-line distance. 131 registered projects within 2 km.

Builder: RAJ DEVELOPERS

RAJ DEVELOPERS has 10 registrations on GujRERA, including GANESH VATIKA and Pramukh Oracle. Read the full track record. See more projects on the Surat district page.

Frequently asked questions

What are my rights if RAJ VICTORIA is delayed beyond 30 Jun 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of RAJ VICTORIA?

The registered promoter entity is RAJ DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in RAJ VICTORIA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

What should I check before booking in RAJ VICTORIA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About RAJ VICTORIA. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save RAJ VICTORIA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.