Home / Browse projects / Dahod, Gujarat / Radhe Govind Park

Valid until 20 Oct 2026 Mixed Development project

Radhe Govind Park

By Kamlesh S Pathak

RG-GJ-54330 · RERA PR/GJ/DAHOD/DEVGADBARIA/Others/MAA04721/EX1/191224/250625 · Last updated on GujRERA portal: 25 Jun 2024

Source: official GujRERA filing

Red flags

  • Completion date moved by 28 months
  • 2 extensions taken

Clear

  • Nothing verified clear yet
Oct 2026Possession promisedmoved 28 months from the original
16 of 18Construction stages doneacross 2 buildings; furthest along: Plinth, 0%
23 of 112Units unsoldnot recorded sold or booked
Jump to the 38 documents Report an error

Radhe Govind Park is a Mixed Development project by Kamlesh S Pathak in Dahod, Gujarat, registered with GujRERA as PR/GJ/DAHOD/DEVGADBARIA/Others/MAA04721/EX1/191224/250625 on 22 Jan 2019. Possession is promised by 20 Oct 2026. The completion date has moved by 28 months from the original filing. 89 of the 112 units on this registration are recorded sold or booked, and 16 of 18 construction stages are filed complete.

At a glance

Project

  • NameRadhe Govind Park
  • TypeMixed Development
  • Location
    • RAdhe Govind Park
    • RAdhe Govind Mandir Road
    • Devgadh Bariya
    • Dahod
    • Devgahdbariya
    • Devgadbaria
    • Dahod
    • 389380
  • Pincode389380
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/DAHOD/DEVGADBARIA/Others/MAA04721/EX1/191224/250625
  • ReraGenie IDRG-GJ-54330

Builder

  • NameKamlesh S Pathak
  • Entity typeIndividual/Propritorship

Key dates

this monthRegisteredJan 2019First promiseJun 2024Revised toOct 2026

Key facts

Registration and timeline

  • StatusValid until 20 Oct 2026
  • Registered on22 Jan 2019
  • Promised completion20 Oct 2026
  • Revised completionRevised to 20 Oct 2026 (originally 30 Jun 2024)
  • Buildings2 building records
  • Documents filed38 files

Current status

79%89 of 112 units booked
99.5%Of the estimated cost spent so far

Figures as on 25 Jun 2024, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A+B---442064
C+D---48048

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building2

As on 25 Jun 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

16 of 18 construction stages are filed complete across 2 buildings. The stage furthest along is Plinth, at 0%.

A+B89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
C+D89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities23

As on 25 Jun 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes10%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable
Compound wallYes0%
Plinth protectionYes10%
Water tankYes10%
Other requirementsNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,015 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 6.50 cr
Cost incurredRs 6.47 cr
Spent of the estimate99.54%
BuildingWingEstimatedIncurred
A+BNARs 4.15 crRs 4.13 cr
C+DNARs 2.35 crRs 2.34 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKamlesh S Pathak
EngineerKamlesh S Pathak

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/DAHOD/DEVGADBARIA/Others/MAA04721/EX1/191224/250625Applied Jun 2024; approved Dec 2024
ExtensionApplied Jun 2025; no approval date filed

Documents filed38

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/DAHOD/DEVGADBARIA/Others/MAA04721/EX1/191224/250625 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineer's certificate (Form 2)25 Jun 2024
Engineer's certificate annexure25 Jun 2024
RERA registration certificate22 Jan 2019
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

Keep Radhe Govind Park on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Builder: Kamlesh S Pathak

Kamlesh S Pathak has 1 registration on GujRERA, including Radhe Govind Park. Read the full track record. See more projects on the Dahod district page.

Frequently asked questions

What are my rights if Radhe Govind Park is delayed beyond 20 Oct 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of Radhe Govind Park?

The registered promoter entity is Kamlesh S Pathak, an individual/propritorship as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in Radhe Govind Park?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Radhe Govind Park?

The professionals named in the filing: Architect: Kamlesh S Pathak; Engineer: Kamlesh S Pathak. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Radhe Govind Park?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Radhe Govind Park. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Radhe Govind Park to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.