Valid until 31 Mar 2024 Mixed Development project

PUSHP MAHADEV

By SANSKRUT INFRA

RG-GJ-90894 · RERA PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/MAA05456/EX1/240220 · Last updated on GujRERA portal: 18 Sep 2024

Source: official GujRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • Nothing verified clear yet
Mar 2024Possession promisedmoved 12 months from the original
48 of 54Construction stages doneacross 6 buildings; furthest along: Stilt Floor, 0%
187 of 455Units unsoldnot recorded sold or booked
Jump to the 51 documents Report an error

PUSHP MAHADEV is a Mixed Development project by SANSKRUT INFRA in Ahmedabad, Gujarat, registered with GujRERA as PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/MAA05456/EX1/240220 on 17 May 2019. Possession is promised by 31 Mar 2024. The completion date has moved by 12 months from the original filing. 268 of the 455 units on this registration are recorded sold or booked, and 48 of 54 construction stages are filed complete.

At a glance

Project

  • NamePUSHP MAHADEV
  • TypeMixed Development
  • Location
    • PUSHPMAHADE
    • NEAR DOON SCHOOL
    • OPP SHRINAND VILLA 9
    • PARALLEL TO BARODA EXPRESS WAY
    • NEW MANINAGAR
    • RAMOL
    • RAMOL
    • Ahmedabad City
    • Ahmedabad
    • 382449
  • Pincode382449
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/MAA05456/EX1/240220
  • ReraGenie IDRG-GJ-90894

Builder

  • NameSANSKRUT INFRA
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredMay 2019First promiseMar 2023Revised toMar 2024

Key facts

Registration and timeline

  • StatusValid until 31 Mar 2024
  • Registered on17 May 2019
  • Promised completion31 Mar 2024
  • Revised completionRevised to 31 Mar 2024 (originally 31 Mar 2023)
  • Buildings6 building records
  • Documents filed51 files

Current status

59%268 of 455 units booked
100.0%Of the estimated cost spent so far

Figures as on 18 Sep 2024, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BLOCK A---38947
BLOCK B+C---80080
BLOCK D+E---80080
BLOCK F---38038
BLOCK G+H+I---1100110
BLOCK J+K---7624100

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building6

As on 18 Sep 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

48 of 54 construction stages are filed complete across 6 buildings. The stage furthest along is Stilt Floor, at 0%.

BLOCK A89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
BLOCK B+C89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
BLOCK D+E89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
BLOCK F89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
BLOCK G+H+I89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
BLOCK J+K89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 18 Sep 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsNoNot applicable
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsYes100%
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingYes100%
Drinking water facilitiesYes100%
Emergency evacuationYes100%
Use of renewable energyYes100%
SecurityYes100%
Letter boxYes100%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area12,262 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 67.40 cr
Cost incurredRs 67.40 cr
Spent of the estimate100.0%
BuildingWingEstimatedIncurred
BLOCK J+KNARs 16.50 crRs 16.50 cr
BLOCK G+H+INARs 15.00 crRs 15.00 cr
BLOCK B+CNARs 10.80 crRs 10.80 cr
BLOCK D+ENARs 10.80 crRs 10.80 cr
BLOCK ANARs 7.50 crRs 7.50 cr
BLOCK FNARs 6.80 crRs 6.80 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectHM ARCHITECHTS
EngineerKETAV P JOSHI

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/MAA05456/EX1/240220Applied Jan 2020; approved Feb 2020

Documents filed51

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/MAA05456/EX1/240220 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)18 Sep 2024
Engineer's certificate (Form 2)5 Sep 2024
Engineer's certificate annexure5 Sep 2024
Architect's certificate (Form 1)3 Sep 2024
Site photograph, BLOCK A22 Jul 2024
Site photograph, BLOCK B+C22 Jul 2024
Site photograph, BLOCK B+C22 Jul 2024
Site photograph, BLOCK D+E22 Jul 2024
Site photograph, BLOCK D+E22 Jul 2024
Site photograph, BLOCK F22 Jul 2024
Site photograph, BLOCK G+H+I22 Jul 2024
Site photograph, BLOCK G+H+I22 Jul 2024
Site photograph, BLOCK G+H+I22 Jul 2024
Site photograph, BLOCK J+K22 Jul 2024
Site photograph, BLOCK J+K22 Jul 2024
RERA registration certificate17 May 2019
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Ahmedabad

59%of this project is bookeddistrict median 53%
14%of Ahmedabad projects moved their completion datethis one moved by 12 months

Computed across the 5,400+ Ahmedabad projects on ReraGenie, from their own filings.

Keep PUSHP MAHADEV on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near RAMOL5,400+ in Ahmedabad

2 kmPUSHP MAHADEVOther 118Dot size: filed unitsN

Filed coordinates, straight-line distance. 118 registered projects within 2 km.

Builder: SANSKRUT INFRA

SANSKRUT INFRA has 1 registration on GujRERA, including PUSHP MAHADEV. Read the full track record. See more projects on the Ahmedabad district page.

Frequently asked questions

What are my rights if PUSHP MAHADEV is delayed beyond 31 Mar 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of PUSHP MAHADEV?

The registered promoter entity is SANSKRUT INFRA, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in PUSHP MAHADEV?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at PUSHP MAHADEV?

The professionals named in the filing: Architect: HM ARCHITECHTS; Engineer: KETAV P JOSHI. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PUSHP MAHADEV?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PUSHP MAHADEV. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PUSHP MAHADEV to a free account