Valid until 31 Mar 2020 Mixed Development project

Prerna RajVijay Tirth

By Prerna Infrabuild Limited

RG-GJ-87785 · RERA PR/GJ/AHMEDABAD/SANAND/AUDA/MAA00260/EX1/190918 · Last updated on GujRERA portal: 5 Jun 2019

Source: official GujRERA filing

Red flags

  • Completion date moved by 24 months
  • 2 extensions taken

Clear

  • Separate project account declared
Mar 2020Possession promisedmoved 24 months from the original
45 of 45Construction stages doneacross 5 buildings; every applicable stage filed complete
Jump to the 39 documents Report an error

Prerna RajVijay Tirth is a Mixed Development project by Prerna Infrabuild Limited in Ahmedabad, Gujarat, registered with GujRERA as PR/GJ/AHMEDABAD/SANAND/AUDA/MAA00260/EX1/190918 on 26 Sep 2017. Possession is promised by 31 Mar 2020. The completion date has moved by 24 months from the original filing.

At a glance

Project

  • NamePrerna RajVijay Tirth
  • TypeMixed Development
  • Location
    • "Prerna RajVijay Tirth"
    • Opp. Sukirti Bunglows
    • Ahmedabad-Sanand-Viramgam Highway
    • Sanand
    • Ahmedabad
    • 382170
  • Pincode382170
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/AHMEDABAD/SANAND/AUDA/MAA00260/EX1/190918
  • ReraGenie IDRG-GJ-87785

Builder

  • NamePrerna Infrabuild Limited
  • Entity typeCOMPANY
  • Other registrations2 more →

Key dates

this monthRegisteredSep 2017First promiseMar 2018Revised toMar 2020

Key facts

Registration and timeline

  • StatusValid until 31 Mar 2020
  • Registered on26 Sep 2017
  • Promised completion31 Mar 2020
  • Revised completionRevised to 31 Mar 2020 (originally 31 Mar 2018)
  • Buildings5 building records
  • Documents filed39 files

Current status

100.0%Of the estimated cost spent so far

Figures as on 5 Jun 2019, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A-----8
B-----43
C-----28
D-----28
E-----36

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building5

As on 5 Jun 2019, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

45 of 45 construction stages are filed complete across 5 buildings.

A100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
B100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
C100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
D100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
E100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 5 Jun 2019, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterYes100%
Solid waste management and disposalYes100%
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,613 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 12.26 cr
Cost incurredRs 12.26 cr
Spent of the estimate100.0%
BuildingWingEstimatedIncurred
ANARs 2.45 crRs 2.45 cr
BNARs 2.45 crRs 2.45 cr
CNARs 2.45 crRs 2.45 cr
DNARs 2.45 crRs 2.45 cr
ENARs 2.45 crRs 2.45 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNarendra K. Modi
EngineerRajendrakumar Desai

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/AHMEDABAD/SANAND/AUDA/MAA00260/EX1/190918Applied Apr 2018; approved Sep 2018
ExtensionApplied Mar 2019; no approval date filed

Documents filed39

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/AHMEDABAD/SANAND/AUDA/MAA00260/EX1/190918 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)5 Jun 2019
Engineer's certificate (Form 2)5 Jun 2019
Site photograph, A5 Jun 2019
Site photograph, B5 Jun 2019
Site photograph, C5 Jun 2019
Site photograph, D5 Jun 2019
Site photograph, E5 Jun 2019
RERA registration certificate26 Sep 2017
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Ahmedabad

14%of Ahmedabad projects moved their completion datethis one moved by 24 months

Computed across the 5,400+ Ahmedabad projects on ReraGenie, from their own filings.

Keep Prerna RajVijay Tirth on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Sanand5,400+ in Ahmedabad

2 kmPrerna RajVijay TirthOther 57Dot size: filed unitsN

Filed coordinates, straight-line distance. 57 registered projects within 2 km.

Builder: Prerna Infrabuild Limited

Prerna Infrabuild Limited has 3 registrations on GujRERA, including Prerna Aartika and Prerna RajVijay Tirth. Read the full track record. See more projects on the Ahmedabad district page.

Frequently asked questions

What are my rights if Prerna RajVijay Tirth is delayed beyond 31 Mar 2020?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of Prerna RajVijay Tirth?

The registered promoter entity is Prerna Infrabuild Limited, a company as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in Prerna RajVijay Tirth?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Prerna RajVijay Tirth?

The professionals named in the filing: Architect: Narendra K. Modi; Engineer: Rajendrakumar Desai. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Prerna RajVijay Tirth?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Prerna RajVijay Tirth. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Prerna RajVijay Tirth to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.