Home / Browse projects / Surat, Gujarat / PRATISHTHA PALM
PRATISHTHA PALM
RG-GJ-99617 · RERA PR/GJ/SURAT/CHORYASI/Surat Municipal Corporation/RAA15636/040825/311230 · Last updated on GujRERA portal: 4 Aug 2025
Source: official GujRERA filing
Red flags
- No red flags in this filing
Clear
- Completion date never moved
Saved.
PRATISHTHA PALM is a Residential/Group Housing project by MND DEVELOPERS in Surat, Gujarat, registered with GujRERA as PR/GJ/SURAT/CHORYASI/Surat Municipal Corporation/RAA15636/040825/311230 on 4 Aug 2025. Possession is promised by 30 Apr 2031. 0 of the 208 units on this registration are recorded sold or booked, and 0 of 36 construction stages are filed complete.
At a glance
Project
- NamePRATISHTHA PALM
- TypeResidential/Group Housing
- Location
- BLOCK NO.74/1
- F.P NO. 256/A PAIKEE SUB PLOT - 06
- T.P.S NO. 84 (KOSAD-BHARTHANA KOSAD-MOTA VARACHHA-ABRAMA)
- OPP GOPIN GAM
- NR RING ROAD CIRCLE
- ABRAMA
- ...
- Pincode394101
- MapView location on Google Maps (as filed on RERA)
- RERA no.PR/GJ/SURAT/CHORYASI/Surat Municipal Corporation/RAA15636/040825/311230
- ReraGenie IDRG-GJ-99617
Builder
- NameMND DEVELOPERS
- Entity typePARTNERSHIP FIRM
- Other registrations1 more →
Key dates
Key facts
Registration and timeline
- StatusValid until 30 Apr 2031
- Registered on4 Aug 2025
- Promised completion30 Apr 2031
- Revised completionNone
- Buildings4 building records
- Documents filed34 files
Current status
Figures as on 4 Aug 2025, this project's latest GujRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| D | - | - | - | 52 | 0 | 52 |
| A | - | - | - | 52 | 0 | 52 |
| C | - | - | - | 52 | 0 | 52 |
| B | - | - | - | 52 | 0 | 52 |
The full filing
Everything below is from the project's own GujRERA filing, free to read.
Construction progress by building4
As on 4 Aug 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
0 of 36 construction stages are filed complete across 4 buildings. The stage furthest along is Excavation, at 0%.
D0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Podiums (if any) | Not applicable |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 0% |
| Sanitary fittings within the flats | 0% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 0% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 0% |
A0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Podiums (if any) | Not applicable |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 0% |
| Sanitary fittings within the flats | 0% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 0% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 0% |
C0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Podiums (if any) | Not applicable |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 0% |
| Sanitary fittings within the flats | 0% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 0% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 0% |
B0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Podiums (if any) | Not applicable |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 0% |
| Sanitary fittings within the flats | 0% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 0% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 0% |
Progress on shared amenities19
As on 4 Aug 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal roads and footpaths | Yes | 0% |
| Water supply | Yes | 0% |
| Sewerage (chamber, lines, septic tank, STP) | Yes | 0% |
| Storm water drains | Yes | 0% |
| Landscaping and tree planting | Yes | 0% |
| Street lighting | Yes | 0% |
| Community buildings | No | Not applicable |
| Treatment and disposal of sewage and sullage water | Yes | 0% |
| Solid waste management and disposal | Yes | 0% |
| Water conservation, rain water harvesting | Yes | 0% |
| Energy management | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Fire fighting | Yes | 0% |
| Drinking water facilities | Yes | 0% |
| Emergency evacuation | Yes | 0% |
| Use of renewable energy | No | Not applicable |
| Security | Yes | 0% |
| Letter box | Yes | 0% |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| A | NA | Rs 13.40 cr | - |
| B | NA | Rs 13.40 cr | - |
| C | NA | Rs 13.40 cr | - |
| D | NA | Rs 13.40 cr | - |
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | JIGNESHKUMAR GOVINDBHAI UCHADADIYA |
| Engineer | KEYUR RAJUBHAI TEJANI |
Documents filed34
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/SURAT/CHORYASI/Surat Municipal Corporation/RAA15636/040825/311230 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| RERA registration certificate | 4 Aug 2025 |
| Architect's certificate (Form 1) | 23 Jul 2025 |
| Engineer's certificate (Form 2) | 23 Jul 2025 |
| Engineer's certificate annexure | 23 Jul 2025 |
| Accountant's certificate (Form 3) | 23 Jul 2025 |
| Site photograph, D | 23 Jul 2025 |
| Site photograph, A | 23 Jul 2025 |
| Site photograph, C | 23 Jul 2025 |
| Site photograph, B | 23 Jul 2025 |
| Proforma agreement for sale | - |
| Auditor's report (3 of 3) | - |
| Income tax return (3 of 3) | - |
| Project specific document | - |
| Drainage affidavit | - |
| Directors' report (3 of 3) | - |
| Approved sanctioned plan | - |
| Approved layout plan | - |
| Land location | - |
| Encumbrance certificate | - |
| Area development document | - |
| Proforma allotment letter | - |
| Brochure | - |
| Declaration in Form B | - |
| Approved building or plotting plan | - |
| NOCs from authorities | - |
| Title clearance certificate | - |
| Title report | - |
| Property card | - |
| Statutory document | - |
| Project photograph | - |
| Proforma sale deed | - |
| Audited balance sheet (3 of 3) | - |
| Audited profit and loss statement (3 of 3) | - |
| Cash flow statement (3 of 3) | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Surat
Computed across the 2,600+ Surat projects on ReraGenie, from their own filings.
Keep PRATISHTHA PALM on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near ABRAMA2,600+ in Surat
Filed coordinates, straight-line distance. 185 registered projects within 2 km.
Construction Of 752 DUs Of EWS-II Type at T.P.
SURAT MUNICIPAL CORPORATION
SHIVDHARA RESIDENCY
SHIVDHARA BUILDERS
Construction Of 560 DUs Of EWS-I Type at T.P.
SURAT MUNICIPAL CORPORATION
KIRAN BUSINESS HUB
VARUNKUMAR BABUBHAI LAKHANI Proprietor of
SUMAN SURAJ EWS-26 TPS NO 24 (MOTA VARACHHA-UT
SURAT MUNICIPAL CORPORATION
SUMERU CITY MALL PHASE-2
DIVYAM DEVELOPERS
See every Surat project, with the district possession charts
Builder: MND DEVELOPERS
MND DEVELOPERS has 2 registrations on GujRERA, including EVERMARK 11 and PRATISHTHA PALM. Read the full track record. See more projects on the Surat district page.
Frequently asked questions
What are my rights if PRATISHTHA PALM is delayed beyond 30 Apr 2031?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.
How do I verify and contact the developer of PRATISHTHA PALM?
The registered promoter entity is MND DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.
Is my payment protected in PRATISHTHA PALM?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at PRATISHTHA PALM?
The professionals named in the filing: Architect: JIGNESHKUMAR GOVINDBHAI UCHADADIYA; Engineer: KEYUR RAJUBHAI TEJANI. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in PRATISHTHA PALM?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.
Report an error Share feedback