ReraGenieLog inGet a buyer report

Home / Browse projects / Surat, Gujarat / PIONEER DREAMS

Valid until 7 Aug 2022 Residential/Group Housing project

PIONEER DREAMS

By PIONEER DREAMS CORPORATION

RG-GJ-48144 · RERA PR/GJ/SURAT/SURAT CITY/SUDA/RAA00338/EX1/240621 · Last updated on GujRERA portal: 5 Aug 2022

Source: official GujRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • Separate project account declared
Aug 2022Possession promisedmoved 12 months from the original
48 of 48Construction stages doneacross 6 buildings; every applicable stage filed complete
27 of 312Units unsoldnot recorded sold or booked
Jump to the 43 documents Report an error

PIONEER DREAMS is a Residential/Group Housing project by PIONEER DREAMS CORPORATION in Surat, Gujarat, registered with GujRERA as PR/GJ/SURAT/SURAT CITY/SUDA/RAA00338/EX1/240621 on 5 Oct 2017. Possession is promised by 7 Aug 2022. The completion date has moved by 12 months from the original filing. 285 of the 312 units on this registration are recorded sold or booked, and 48 of 48 construction stages are filed complete.

At a glance

Project

  • NamePIONEER DREAMS
  • TypeResidential/Group Housing
  • Location
    • FP 47
    • TP 71
    • BLOCK 83
    • 150 FT BAMROLI MAIN ROAD
    • VADOD
    • Vadod
    • Surat City
    • Surat
    • 395023
  • Pincode395023
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/SURAT/SURAT CITY/SUDA/RAA00338/EX1/240621
  • ReraGenie IDRG-GJ-48144

Builder

  • NamePIONEER DREAMS CORPORATION
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredOct 2017First promiseAug 2021Revised toAug 2022

Key facts

Registration and timeline

  • StatusValid until 7 Aug 2022
  • Registered on5 Oct 2017
  • Promised completion7 Aug 2022
  • Revised completionRevised to 7 Aug 2022 (originally 8 Aug 2021)
  • Buildings6 building records
  • Documents filed43 files

Current status

91%285 of 312 units booked
83.2%Of the estimated cost spent so far

Figures as on 5 Aug 2022, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---52052
B---52052
C---52052
D---52052
E---52052
F---52052

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building6

As on 5 Aug 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

48 of 48 construction stages are filed complete across 6 buildings.

A100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
B100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
C100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
D100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
E100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
F100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 5 Aug 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsYes100%
Treatment and disposal of sewage and sullage waterYes100%
Solid waste management and disposalYes100%
Water conservation, rain water harvestingYes100%
Energy managementYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingYes100%
Drinking water facilitiesYes100%
Emergency evacuationYes100%
Use of renewable energyYes100%
SecurityYes100%
Letter boxYes100%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area9,382 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 41.29 cr
Cost incurredRs 34.35 cr
Spent of the estimate83.2%
BuildingWingEstimatedIncurred
ANARs 6.88 crRs 5.72 cr
BNARs 6.88 crRs 5.72 cr
CNARs 6.88 crRs 5.72 cr
DNARs 6.88 crRs 5.72 cr
ENARs 6.88 crRs 5.72 cr
FNARs 6.88 crRs 5.72 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVISTAR ARCHITECHTS
EngineerHEMANT A SHUKLA (TECHNOCRAT CONSULTANT)

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/SURAT/SURAT CITY/SUDA/RAA00338/EX1/240621Applied May 2021; approved Jun 2021

Documents filed43

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/SURAT/SURAT CITY/SUDA/RAA00338/EX1/240621 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)5 Aug 2022
Architect's certificate (Form 1)4 Aug 2022
Engineer's certificate (Form 2)4 Aug 2022
Engineer's certificate annexure4 Aug 2022
Site photograph, A4 Aug 2022
Site photograph, B4 Aug 2022
Site photograph, C4 Aug 2022
Site photograph, D4 Aug 2022
Site photograph, E4 Aug 2022
Site photograph, F4 Aug 2022
RERA registration certificate5 Oct 2017
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Surat

91%of this project is bookeddistrict median 39%
15%of Surat projects moved their completion datethis one moved by 12 months

Computed across the 2,600+ Surat projects on ReraGenie, from their own filings.

Keep PIONEER DREAMS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Vadod2,600+ in Surat

2 kmPIONEER DREAMSOther 69Dot size: filed unitsN

Filed coordinates, straight-line distance. 69 registered projects within 2 km.

Builder: PIONEER DREAMS CORPORATION

PIONEER DREAMS CORPORATION has 1 registration on GujRERA, including PIONEER DREAMS. Read the full track record. See more projects on the Surat district page.

Frequently asked questions

What are my rights if PIONEER DREAMS is delayed beyond 7 Aug 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of PIONEER DREAMS?

The registered promoter entity is PIONEER DREAMS CORPORATION, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in PIONEER DREAMS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at PIONEER DREAMS?

The professionals named in the filing: Architect: VISTAR ARCHITECHTS; Engineer: HEMANT A SHUKLA (TECHNOCRAT CONSULTANT). Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PIONEER DREAMS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PIONEER DREAMS. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PIONEER DREAMS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.