Home / Browse projects / Valsad, Gujarat / PINNACLE

Valid until 30 Apr 2027 Mixed Development project

PINNACLE

By N & F DEVELOPERS

RG-GJ-34887 · RERA PR/GJ/VALSAD/PARDI/Vapi Municipality/MAA10113/A1M/060325/311226 · Last updated on GujRERA portal: 1 Feb 2025

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Apr 2027Possession promisedno revision filed
2 of 9Construction stages donefurthest along: Slabs of Super Structure, 46%
134 of 250Units unsoldnot recorded sold or booked
Jump to the 41 documents Report an error

PINNACLE is a Mixed Development project by N & F DEVELOPERS in Valsad, Gujarat, registered with GujRERA as PR/GJ/VALSAD/PARDI/Vapi Municipality/MAA10113/A1M/060325/311226 on 29 Apr 2022. Possession is promised by 30 Apr 2027. 116 of the 250 units on this registration are recorded sold or booked, and 2 of 9 construction stages are filed complete.

At a glance

Project

  • NamePINNACLE
  • TypeMixed Development
  • Location
    • Survey No. 999/2
    • Silvassa Vapi Road
    • Dungra
    • Vapi.
    • Dungra
    • Pardi
    • Valsad
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VALSAD/PARDI/Vapi Municipality/MAA10113/A1M/060325/311226
  • ReraGenie IDRG-GJ-34887

Builder

  • NameN & F DEVELOPERS
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredApr 2022PromisedApr 2027

Key facts

Registration and timeline

  • StatusValid until 30 Apr 2027
  • Registered on29 Apr 2022
  • Promised completion30 Apr 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed41 files

Current status

46%116 of 250 units booked
43.0%Of the estimated cost spent so far

Figures as on 1 Feb 2025, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A + B---19258250

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 1 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

2 of 9 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 46%.

A + B: 35% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure46%
Internal walls, internal plaster, floorings, doors and windows within flats15%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks46%
External plumbing and external plaster, elevation, completion of terraces with waterproofing10%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%

Progress on shared amenities23

As on 1 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes0%
Water supplyYes0%
Sewerage (chamber, lines, septic tank, STP)Yes0%
Storm water drainsYes0%
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes0%
Water conservation, rain water harvestingYes0%
Energy managementYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingYes0%
Drinking water facilitiesYes0%
Emergency evacuationYes0%
Use of renewable energyNoNot applicable
SecurityYes0%
Letter boxYes0%
Compound wallYes0%
Plinth protectionYes0%
Water tankYes0%
Other requirementsYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area6,095 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 40.00 cr
Cost incurredRs 17.20 cr
Spent of the estimate43.0%
BuildingWingEstimatedIncurred
A + BNARs 40.00 crRs 17.20 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMANISH DOSHI
EngineerPRIYANK RAJESHKUMAR SHAH

Documents filed41

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VALSAD/PARDI/Vapi Municipality/MAA10113/A1M/060325/311226 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineer's certificate (Form 2)1 Feb 2025
Engineer's certificate annexure1 Feb 2025
RERA registration certificate29 Apr 2022
Alteration certificate-
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Drainage affidavit-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Approved building or plotting plan-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Proforma sale deed-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Valsad

46%of this project is bookeddistrict median 45%
23%of Valsad projects moved their completion datethis one has not

Computed across the 390+ Valsad projects on ReraGenie, from their own filings.

Keep PINNACLE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Dungra390+ in Valsad

2 kmPINNACLEOther 78Dot size: filed unitsN

Filed coordinates, straight-line distance. 78 registered projects within 2 km.

Builder: N & F DEVELOPERS

N & F DEVELOPERS has 1 registration on GujRERA, including PINNACLE. Read the full track record. See more projects on the Valsad district page.

Frequently asked questions

What are my rights if PINNACLE is delayed beyond 30 Apr 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of PINNACLE?

The registered promoter entity is N & F DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in PINNACLE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at PINNACLE?

The professionals named in the filing: Architect: MANISH DOSHI; Engineer: PRIYANK RAJESHKUMAR SHAH. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PINNACLE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PINNACLE. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PINNACLE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.