Home / Browse projects / Jamnagar, Gujarat / ORCHID GRAND
ORCHID GRAND
By NILESHKUMAR VANRAVAN DATTANI PROPRIETOR OF BHAVYA BUILDCON
RG-GJ-95966 · RERA PR/GJ/JAMNAGAR/JAMNAGAR/Jamnagar Municipal Corporation/MAA14908/050325/311227 · Last updated on GujRERA portal: 5 Mar 2025
Source: official GujRERA filing
Red flags
- No red flags in this filing
Clear
- Completion date never moved
Saved.
ORCHID GRAND is a Mixed Development project by NILESHKUMAR VANRAVAN DATTANI PROPRIETOR OF BHAVYA BUILDCON in Jamnagar, Gujarat, registered with GujRERA as PR/GJ/JAMNAGAR/JAMNAGAR/Jamnagar Municipal Corporation/MAA14908/050325/311227 on 5 Mar 2025. Possession is promised by 30 Apr 2028. 0 of the 61 units on this registration are recorded sold or booked, and 2 of 9 construction stages are filed complete.
At a glance
Project
- NameORCHID GRAND
- TypeMixed Development
- Location
- JAMNAGAR RAJKOT HIGHWAY FP NO 37 NR INCOME TAX OFFICE BESIDE TRI MANDIR
- LALWADI MAIN ROAD JAMNAGAR
- JAMNAGAR
- 361001
- Pincode361001
- MapView location on Google Maps (as filed on RERA)
- RERA no.PR/GJ/JAMNAGAR/JAMNAGAR/Jamnagar Municipal Corporation/MAA14908/050325/311227
- ReraGenie IDRG-GJ-95966
Builder
- NameNILESHKUMAR VANRAVAN DATTANI PROPRIETOR OF BHAVYA BUILDCON
- Entity typeIndividual/Propritorship
Key dates
Key facts
Registration and timeline
- StatusValid until 30 Apr 2028
- Registered on5 Mar 2025
- Promised completion30 Apr 2028
- Revised completionNone
- Buildings1 building record
- Documents filed39 files
Current status
Figures as on 5 Mar 2025, this project's latest GujRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A | - | - | - | 29 | 32 | 61 |
The full filing
Everything below is from the project's own GujRERA filing, free to read.
Construction progress by building1
As on 5 Mar 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
2 of 9 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 57%.
A: 33% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 57% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 43% |
| Sanitary fittings within the flats | 0% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 0% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 0% |
Progress on shared amenities23
As on 5 Mar 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal roads and footpaths | Yes | 0% |
| Water supply | Yes | 0% |
| Sewerage (chamber, lines, septic tank, STP) | Yes | 0% |
| Storm water drains | Yes | 0% |
| Landscaping and tree planting | Yes | 0% |
| Street lighting | Yes | 0% |
| Community buildings | No | Not applicable |
| Treatment and disposal of sewage and sullage water | No | Not applicable |
| Solid waste management and disposal | Yes | 0% |
| Water conservation, rain water harvesting | Yes | 0% |
| Energy management | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Fire fighting | Yes | 0% |
| Drinking water facilities | Yes | 0% |
| Emergency evacuation | Yes | 0% |
| Use of renewable energy | No | Not applicable |
| Security | Yes | 0% |
| Letter box | Yes | 0% |
| Compound wall | Yes | 0% |
| Plinth protection | Yes | 0% |
| Water tank | Yes | 0% |
| Other requirements | Yes | 0% |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| A | NA | Rs 5.60 cr | Rs 1.25 cr |
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Chetan Upendrabhai Pancholi |
| Engineer | RONAK KIRTIBHAI JHAVERI |
Documents filed39
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/JAMNAGAR/JAMNAGAR/Jamnagar Municipal Corporation/MAA14908/050325/311227 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| RERA registration certificate | 5 Mar 2025 |
| Engineer's certificate (Form 2) | 17 Feb 2025 |
| Engineer's certificate annexure | 17 Feb 2025 |
| Proforma agreement for sale | - |
| Auditor's report (1 of 3) | - |
| Auditor's report (2 of 3) | - |
| Auditor's report (3 of 3) | - |
| Income tax return (1 of 3) | - |
| Income tax return (2 of 3) | - |
| Income tax return (3 of 3) | - |
| Project specific document | - |
| Drainage affidavit | - |
| Directors' report (1 of 3) | - |
| Directors' report (2 of 3) | - |
| Directors' report (3 of 3) | - |
| Approved sanctioned plan | - |
| Approved layout plan | - |
| Agreement | - |
| Land location | - |
| Area development document | - |
| Proforma allotment letter | - |
| Brochure | - |
| Approved building or plotting plan | - |
| NOCs from authorities | - |
| Title clearance certificate | - |
| Title report | - |
| Property card | - |
| Statutory document | - |
| Project photograph | - |
| Proforma sale deed | - |
| Audited balance sheet (1 of 3) | - |
| Audited balance sheet (2 of 3) | - |
| Audited balance sheet (3 of 3) | - |
| Audited profit and loss statement (1 of 3) | - |
| Audited profit and loss statement (2 of 3) | - |
| Audited profit and loss statement (3 of 3) | - |
| Cash flow statement (1 of 3) | - |
| Cash flow statement (2 of 3) | - |
| Cash flow statement (3 of 3) | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Jamnagar
Computed across the 220+ Jamnagar projects on ReraGenie, from their own filings.
Keep ORCHID GRAND on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near JAMNAGAR220+ in Jamnagar
Filed coordinates, straight-line distance. 36 registered projects within 2 km.
SILVER SKY
SILVERDREAMZ DEVELOPERS PRIVATE LIMITED
JAY SHREE MARKET
BHAGWATI ENTERPRISE
NANDANVAN STYLES
MARUTI ENTERPRISE
JINKUSHAL RESIDENCY
JINDAT ENTERPRISE
SIMANDHAR SQUARE
PHOENIX DEVELOPERS
SIMANDHAR PRIDE
SIDDHARTH BUILDCON
See every Jamnagar project, with the district possession charts
Builder: NILESHKUMAR VANRAVAN DATTANI PROPRIETOR OF BHAVYA BUILDCON
NILESHKUMAR VANRAVAN DATTANI PROPRIETOR OF BHAVYA BUILDCON has 1 registration on GujRERA, including ORCHID GRAND. Read the full track record. See more projects on the Jamnagar district page.
Frequently asked questions
What are my rights if ORCHID GRAND is delayed beyond 30 Apr 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.
How do I verify and contact the developer of ORCHID GRAND?
The registered promoter entity is NILESHKUMAR VANRAVAN DATTANI PROPRIETOR OF BHAVYA BUILDCON, an individual/propritorship as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.
Is my payment protected in ORCHID GRAND?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at ORCHID GRAND?
The professionals named in the filing: Architect: Chetan Upendrabhai Pancholi; Engineer: RONAK KIRTIBHAI JHAVERI. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in ORCHID GRAND?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.
Report an error Share feedback