Home / Browse projects / Surat, Gujarat / ORANGE SKY
ORANGE SKY
RG-GJ-76314 · RERA PR/GJ/SURAT/KAMREJ/Surat Urban Development Authority/RAA03562/A1R/EX1/050824/300625 · Last updated on GujRERA portal: 30 Jun 2025
Source: official GujRERA filing
Red flags
- Completion date moved by 12 months
- 1 extension taken
Clear
- Nothing verified clear yet
Saved.
ORANGE SKY is a Residential/Group Housing project by VISHWAS BUILDCON in Surat, Gujarat, registered with GujRERA as PR/GJ/SURAT/KAMREJ/Surat Urban Development Authority/RAA03562/A1R/EX1/050824/300625 on 3 Oct 2018. Possession is promised by 30 Jun 2025. The completion date has moved by 12 months from the original filing. 177 of the 183 units on this registration are recorded sold or booked, and 45 of 45 construction stages are filed complete.
At a glance
Project
- NameORANGE SKY
- TypeResidential/Group Housing
- Location
- BLOCK NO 3088 (NEW) 375(OLD)
- OP NO: - 155
- FP NO:-155
- T.P.S. NO:-48
- MOJE: - KHOLWAD
- TA: - KAMREJ
- DIST:-SURAT
- KHOLWAD
- Kamrej
- Surat
- 394185
- Pincode394185
- MapView location on Google Maps (as filed on RERA)
- RERA no.PR/GJ/SURAT/KAMREJ/Surat Urban Development Authority/RAA03562/A1R/EX1/050824/300625
- ReraGenie IDRG-GJ-76314
Builder
- NameVISHWAS BUILDCON
- Entity typePARTNERSHIP FIRM
- Other registrations2 more →
Key dates
Key facts
Registration and timeline
- StatusValid until 30 Jun 2025
- Registered on3 Oct 2018
- Promised completion30 Jun 2025
- Revised completionRevised to 30 Jun 2025 (originally 30 Jun 2024)
- Buildings5 building records
- Documents filed48 files
Current status
Figures as on 30 Jun 2025, this project's latest GujRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A | - | - | - | 32 | 0 | 32 |
| C1+C2 | - | - | - | 47 | 0 | 47 |
| B | - | - | - | 32 | 0 | 32 |
| E | - | - | - | 40 | 0 | 40 |
| D | - | - | - | 32 | 0 | 32 |
The full filing
Everything below is from the project's own GujRERA filing, free to read.
Construction progress by building5
As on 30 Jun 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
45 of 45 construction stages are filed complete across 5 buildings.
A100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
C1+C2100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
B100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
E100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
D100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
Progress on shared amenities19
As on 30 Jun 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal roads and footpaths | Yes | 100% |
| Water supply | Yes | 100% |
| Sewerage (chamber, lines, septic tank, STP) | Yes | 100% |
| Storm water drains | Yes | 100% |
| Landscaping and tree planting | Yes | 100% |
| Street lighting | Yes | 100% |
| Community buildings | No | Not applicable |
| Treatment and disposal of sewage and sullage water | No | Not applicable |
| Solid waste management and disposal | Yes | 100% |
| Water conservation, rain water harvesting | Yes | 100% |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Fire fighting | Yes | 100% |
| Drinking water facilities | No | Not applicable |
| Emergency evacuation | Yes | 100% |
| Use of renewable energy | Yes | 100% |
| Security | Yes | 100% |
| Letter box | Yes | 100% |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| A | NA | Rs 4.00 cr | Rs 3.25 cr |
| B | NA | Rs 2.20 cr | Rs 2.20 cr |
| C1+C2 | NA | Rs 2.20 cr | Rs 2.20 cr |
| D | NA | Rs 2.20 cr | Rs 2.20 cr |
| E | NA | Rs 2.20 cr | Rs 2.20 cr |
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Nirav Asit Khandwala |
| Engineer | MAYUR DIPAKBHAI VAGHASIYA |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Documents filed48
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/SURAT/KAMREJ/Surat Urban Development Authority/RAA03562/A1R/EX1/050824/300625 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Accountant's certificate (Form 3) | 30 Jun 2025 |
| Architect's certificate (Form 1) | 27 Jun 2025 |
| Site photograph, A | 27 Jun 2025 |
| Site photograph, C1+C2 | 27 Jun 2025 |
| Site photograph, B | 27 Jun 2025 |
| Site photograph, E | 27 Jun 2025 |
| Site photograph, D | 27 Jun 2025 |
| Engineer's certificate (Form 2) | 18 Oct 2024 |
| Engineer's certificate annexure | 18 Oct 2024 |
| RERA registration certificate | 3 Oct 2018 |
| Alteration certificate | - |
| Proforma agreement for sale | - |
| Auditor's report (1 of 3) | - |
| Auditor's report (2 of 3) | - |
| Auditor's report (3 of 3) | - |
| Income tax return (1 of 3) | - |
| Income tax return (2 of 3) | - |
| Income tax return (3 of 3) | - |
| Project specific document | - |
| Drainage affidavit | - |
| Directors' report (1 of 3) | - |
| Directors' report (2 of 3) | - |
| Directors' report (3 of 3) | - |
| Approved sanctioned plan | - |
| Approved layout plan | - |
| Agreement | - |
| Land location | - |
| Encumbrance certificate | - |
| Area development document | - |
| Proforma allotment letter | - |
| Brochure | - |
| Project related document | - |
| Declaration in Form B | - |
| Approved building or plotting plan | - |
| Title clearance certificate | - |
| Title report | - |
| Property card | - |
| Proforma sale deed | - |
| Project photograph | - |
| Audited balance sheet (1 of 3) | - |
| Audited balance sheet (2 of 3) | - |
| Audited balance sheet (3 of 3) | - |
| Audited profit and loss statement (1 of 3) | - |
| Audited profit and loss statement (2 of 3) | - |
| Audited profit and loss statement (3 of 3) | - |
| Cash flow statement (1 of 3) | - |
| Cash flow statement (2 of 3) | - |
| Cash flow statement (3 of 3) | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Surat
Computed across the 2,600+ Surat projects on ReraGenie, from their own filings.
Keep ORANGE SKY on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near KHOLWAD2,600+ in Surat
Filed coordinates, straight-line distance. 85 registered projects within 2 km.
OPERA PRINCE
VISHWAS HITECH INFRAPROJECTS PRIVATE LIMIT
OPERA ROYAL
VISHWAS BUILDCON
OM PALACE
M D CORPORATION
SAURASHTRA TOWNSHIP
VIMALKUMAR VAJUBHAI KATRODIYA PROP. OF SAU
OPERA PALM
VISHWAS HITECH INFRAPROJECTS PRIVATE LIMIT
AMBER PALACE
S V DEVELOPERS
See every Surat project, with the district possession charts
Builder: VISHWAS BUILDCON
VISHWAS BUILDCON has 3 registrations on GujRERA, including OPERA ROYAL and ORANGE SKY. Read the full track record. See more projects on the Surat district page.
Frequently asked questions
What are my rights if ORANGE SKY is delayed beyond 30 Jun 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.
How do I verify and contact the developer of ORANGE SKY?
The registered promoter entity is VISHWAS BUILDCON, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.
Is my payment protected in ORANGE SKY?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at ORANGE SKY?
The professionals named in the filing: Architect: Nirav Asit Khandwala; Engineer: MAYUR DIPAKBHAI VAGHASIYA. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in ORANGE SKY?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.
Report an error Share feedback