ReraGenieLog inGet a buyer report

Home / Browse projects / Sabar Kantha, Gujarat / ONE WORLD

Valid until 31 May 2025 Commercial project

ONE WORLD

By SHREE NEELKANTH DEVELOPERS

RG-GJ-78180 · RERA PR/GJ/SABAR KANTHA/HIMATNAGAR/Others/CAA09657/A1C/101022 · Last updated on GujRERA portal: 29 Mar 2025

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
May 2025Possession promisedno revision filed
18 of 18Construction stages doneacross 2 buildings; every applicable stage filed complete
101 of 224Units unsoldnot recorded sold or booked
Jump to the 41 documents Report an error

ONE WORLD is a Commercial project by SHREE NEELKANTH DEVELOPERS in Sabar Kantha, Gujarat, registered with GujRERA as PR/GJ/SABAR KANTHA/HIMATNAGAR/Others/CAA09657/A1C/101022 on 1 Jan 2022. Possession is promised by 31 May 2025. 123 of the 224 units on this registration are recorded sold or booked, and 18 of 18 construction stages are filed complete.

At a glance

Project

  • NameONE WORLD
  • TypeCommercial
  • Location
    • CITY SURVEY NO 2793
    • POLYTECHNIC CROSS ROAD
    • MOTIPURA
    • HIMMATNAGAR
    • Himatnagar
    • Sabar Kantha
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/SABAR KANTHA/HIMATNAGAR/Others/CAA09657/A1C/101022
  • ReraGenie IDRG-GJ-78180

Builder

  • NameSHREE NEELKANTH DEVELOPERS
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredJan 2022PromisedMay 2025

Key facts

Registration and timeline

  • StatusValid until 31 May 2025
  • Registered on1 Jan 2022
  • Promised completion31 May 2025
  • Revised completionNone
  • Buildings2 building records
  • Documents filed41 files

Current status

55%123 of 224 units booked
100.0%Of the estimated cost spent so far

Figures as on 29 Mar 2025, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING A---0194194
BUILDING B---03030

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building2

As on 29 Mar 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

18 of 18 construction stages are filed complete across 2 buildings.

BUILDING A100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
BUILDING B100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 29 Mar 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsNoNot applicable
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterYes100%
Solid waste management and disposalYes100%
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingYes100%
Drinking water facilitiesYes100%
Emergency evacuationNoNot applicable
Use of renewable energyYes100%
SecurityYes100%
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area7,573 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 13.97 cr
Cost incurredRs 13.97 cr
Spent of the estimate100.0%
BuildingWingEstimatedIncurred
BUILDING ANARs 6.99 crRs 6.99 cr
BUILDING BNARs 6.99 crRs 6.99 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectHAREESH PATEL
EngineerHarsh Rajeshbhai Sanghvi

Documents filed41

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/SABAR KANTHA/HIMATNAGAR/Others/CAA09657/A1C/101022 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)29 Mar 2025
Architect's certificate (Form 1)27 Mar 2025
Site photograph, BUILDING A27 Mar 2025
Site photograph, BUILDING B27 Mar 2025
Engineer's certificate (Form 2)4 Oct 2024
RERA registration certificate1 Jan 2022
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Sabar Kantha

55%of this project is bookeddistrict median 27%
0%of Sabar Kantha projects moved their completion datethis one has not

Computed across the 33 Sabar Kantha projects on ReraGenie, from their own filings.

Keep ONE WORLD on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Sabar Kantha33 in Sabar Kantha

2 kmONE WORLDOther 27Dot size: filed unitsN

Filed coordinates, straight-line distance. 27 registered projects within 2 km.

Builder: SHREE NEELKANTH DEVELOPERS

SHREE NEELKANTH DEVELOPERS has 1 registration on GujRERA, including ONE WORLD. Read the full track record. See more projects on the Sabar Kantha district page.

Frequently asked questions

What are my rights if ONE WORLD is delayed beyond 31 May 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of ONE WORLD?

The registered promoter entity is SHREE NEELKANTH DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in ONE WORLD?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at ONE WORLD?

The professionals named in the filing: Architect: HAREESH PATEL; Engineer: Harsh Rajeshbhai Sanghvi. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ONE WORLD?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ONE WORLD. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ONE WORLD to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.