Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • Nothing verified clear yet
Dec 2025Possession promisedmoved 12 months from the original
80 of 90Construction stages doneacross 10 buildings; furthest along: Stilt Floor, 0%
32 of 113Units unsoldnot recorded sold or booked
Jump to the 35 documents Report an error

OMKAR VILLA is a Residential/Group Housing project by VASUDEV DEVELOPERS in Mehsana, Gujarat, registered with GujRERA as PR/GJ/MEHSANA/KADI/Kadi Municipality/RN172AA10072/EX1/221225/311225 on 7 Sep 2022. Possession is promised by 31 Dec 2025. The completion date has moved by 12 months from the original filing. 81 of the 113 units on this registration are recorded sold or booked, and 80 of 90 construction stages are filed complete.

At a glance

Project

  • NameOMKAR VILLA
  • TypeResidential/Group Housing
  • Location
    • OMKAR VILLA
    • NEAR KADI-THOL RING ROAD
    • NR. PRASANG PARTY PLOTS
    • KADI
    • KADI
    • Mehsana
    • 382715
  • Pincode382715
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/MEHSANA/KADI/Kadi Municipality/RN172AA10072/EX1/221225/311225
  • ReraGenie IDRG-GJ-70497

Builder

  • NameVASUDEV DEVELOPERS
  • Entity typePARTNERSHIP FIRM
  • Other registrations2 more →

Key dates

this monthRegisteredSep 2022First promiseDec 2024Revised toDec 2025

Key facts

Registration and timeline

  • StatusValid until 31 Dec 2025
  • Registered on7 Sep 2022
  • Promised completion31 Dec 2025
  • Revised completionRevised to 31 Dec 2025 (originally 31 Dec 2024)
  • Buildings10 building records
  • Documents filed35 files

Current status

72%81 of 113 units booked
90.9%Of the estimated cost spent so far

Figures as on 11 Dec 2025, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
E TYPE---202
F TYPE---101
D TYPE---16016
A TYPE---808
B TYPE---606
D1 TYPE---16016
A1 TYPE---808
B1 TYPE---404
C TYPE---26026
C1 TYPE---26026

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building10

As on 11 Dec 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

80 of 90 construction stages are filed complete across 10 buildings. The stage furthest along is Stilt Floor, at 0%.

E TYPE89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
F TYPE89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
D TYPE89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
A TYPE89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
B TYPE89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
D1 TYPE89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
A1 TYPE89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
B1 TYPE89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
C TYPE89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
C1 TYPE89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 11 Dec 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingNoNot applicable
Drinking water facilitiesYes100%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes100%
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area13,870 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 18.50 cr
Cost incurredRs 16.82 cr
Spent of the estimate90.91%
BuildingWingEstimatedIncurred
C TYPENARs 4.35 crRs 4.00 cr
C1 TYPENARs 4.35 crRs 3.70 cr
D TYPENARs 2.49 crRs 2.20 cr
D1 TYPENARs 2.49 crRs 2.20 cr
A TYPENARs 1.41 crRs 1.40 cr
A1 TYPENARs 1.39 crRs 1.38 cr
B TYPENARs 97.24 lakhRs 97.24 lakh
B1 TYPENARs 64.83 lakhRs 62.00 lakh
E TYPENARs 27.64 lakhRs 25.00 lakh
F TYPENARs 13.64 lakhRs 10.00 lakh

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectBhavinkumar Bharatkumar Gajjar
EngineerSURESHKUMAR MAVJIBHAI PRAJAPATI

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/MEHSANA/KADI/Kadi Municipality/RN172AA10072/EX1/221225/311225Applied Mar 2025; approved Dec 2025

Documents filed35

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/MEHSANA/KADI/Kadi Municipality/RN172AA10072/EX1/221225/311225 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)11 Dec 2025
Engineer's certificate (Form 2)25 Nov 2025
Engineer's certificate annexure25 Nov 2025
Architect's certificate (Form 1)24 Nov 2025
Site photograph, E TYPE24 Nov 2025
Site photograph, F TYPE24 Nov 2025
Site photograph, D TYPE24 Nov 2025
Site photograph, A TYPE24 Nov 2025
Site photograph, B TYPE24 Nov 2025
Site photograph, D1 TYPE24 Nov 2025
Site photograph, A1 TYPE24 Nov 2025
Site photograph, B1 TYPE24 Nov 2025
Site photograph, C TYPE24 Nov 2025
Site photograph, C TYPE24 Nov 2025
Site photograph, C1 TYPE24 Nov 2025
RERA registration certificate7 Sep 2022
Proforma agreement for sale-
Project specific document-
Drainage affidavit-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Declaration in Form B-
Approved building or plotting plan-
NOCs from authorities-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Proforma sale deed-

How this compares with Mehsana

72%of this project is bookeddistrict median 54%
11%of Mehsana projects moved their completion datethis one moved by 12 months

Computed across the 200+ Mehsana projects on ReraGenie, from their own filings.

Keep OMKAR VILLA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near KADI200+ in Mehsana

2 kmOMKAR VILLAOther 78Dot size: filed unitsN

Filed coordinates, straight-line distance. 78 registered projects within 2 km.

Builder: VASUDEV DEVELOPERS

Vasudev Developers has 3 registrations on GujRERA, including Malhar Vadvala Residency and PUSHTI SKYLINE. Read the full track record. See more projects on the Mehsana district page.

Frequently asked questions

What are my rights if OMKAR VILLA is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of OMKAR VILLA?

The registered promoter entity is VASUDEV DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in OMKAR VILLA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at OMKAR VILLA?

The professionals named in the filing: Architect: Bhavinkumar Bharatkumar Gajjar; Engineer: SURESHKUMAR MAVJIBHAI PRAJAPATI. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in OMKAR VILLA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About OMKAR VILLA. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save OMKAR VILLA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.