Home / Browse projects / Rajkot, Gujarat / NANDAN

Valid until 30 Apr 2028 Mixed Development project

NANDAN

By SIDDHI VINAYAK ENTERPRISE

RG-GJ-39707 · RERA PR/GJ/RAJKOT/RAJKOT/Others/MAA12353/041023 · Last updated on GujRERA portal: 18 Nov 2024

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Apr 2028Possession promisedno revision filed
27 of 45Construction stages doneacross 5 buildings; furthest along: Sanitary fittings within the flats, 96%
184 of 351Units unsoldnot recorded sold or booked
Jump to the 38 documents Report an error

NANDAN is a Mixed Development project by SIDDHI VINAYAK ENTERPRISE in Rajkot, Gujarat, registered with GujRERA as PR/GJ/RAJKOT/RAJKOT/Others/MAA12353/041023 on 4 Oct 2023. Possession is promised by 30 Apr 2028. 167 of the 351 units on this registration are recorded sold or booked, and 27 of 45 construction stages are filed complete.

At a glance

Project

  • NameNANDAN
  • TypeMixed Development
  • Location
    • 'Nandan'
    • R.S. No.65p1 & 65p2
    • Opp. Matuki Restaurant
    • Nr. Satyam Hills
    • 80 Feet Road
    • Mavdi
    • Rajkot
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/RAJKOT/RAJKOT/Others/MAA12353/041023
  • ReraGenie IDRG-GJ-39707

Builder

  • NameSIDDHI VINAYAK ENTERPRISE
  • Entity typePARTNERSHIP FIRM
  • Other registrations6 more →

Key dates

this monthRegisteredOct 2023PromisedApr 2028

Key facts

Registration and timeline

  • StatusValid until 30 Apr 2028
  • Registered on4 Oct 2023
  • Promised completion30 Apr 2028
  • Revised completionNone
  • Buildings5 building records
  • Documents filed38 files

Current status

48%167 of 351 units booked
49.5%Of the estimated cost spent so far

Figures as on 18 Nov 2024, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Wing-B2---56056
Wing-A3---54054
Wing-B3---56056
Wing-A2---55055
Wing-A1 + B1 + Shop---9634130

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building5

As on 18 Nov 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

27 of 45 construction stages are filed complete across 5 buildings. The stage furthest along is Sanitary fittings within the flats, at 96%.

Wing-B273%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor12%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats93%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing29%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing27%
Wing-A375%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor15%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing30%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing33%
Wing-B372%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor21%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats96%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing30%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
Wing-A275%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor15%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing27%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing36%
Wing-A1 + B1 + Shop72%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor3%
Slabs of Super Structure93%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing23%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing32%

Progress on shared amenities23

As on 18 Nov 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes20%
Water supplyYes25%
Sewerage (chamber, lines, septic tank, STP)Yes10%
Storm water drainsYes5%
Landscaping and tree plantingYes1%
Street lightingYes10%
Community buildingsYes0%
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes0%
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingYes2%
Drinking water facilitiesYes63%
Emergency evacuationYes0%
Use of renewable energyNoNot applicable
SecurityYes34%
Letter boxYes25%
Compound wallYes60%
Plinth protectionYes13%
Water tankYes63%
Other requirementsNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area8,681 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 42.50 cr
Cost incurredRs 21.06 cr
Spent of the estimate49.55%
BuildingWingEstimatedIncurred
Wing-A1 + B1 + ShopNARs 14.40 crRs 7.49 cr
Wing-A2NARs 8.10 crRs 3.97 cr
Wing-A3NARs 8.00 crRs 3.84 cr
Wing-B2NARs 6.00 crRs 2.82 cr
Wing-B3NARs 6.00 crRs 2.94 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectParth Patel
EngineerSanjay Unjia

Documents filed38

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/RAJKOT/RAJKOT/Others/MAA12353/041023 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineer's certificate (Form 2)18 Nov 2024
Engineer's certificate annexure18 Nov 2024
RERA registration certificate4 Oct 2023
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Rajkot

48%of this project is bookeddistrict median 56%
13%of Rajkot projects moved their completion datethis one has not

Computed across the 1,800+ Rajkot projects on ReraGenie, from their own filings.

Keep NANDAN on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Rajkot1,800+ in Rajkot

2 kmNANDANOther 218Dot size: filed unitsN

Filed coordinates, straight-line distance. 218 registered projects within 2 km.

Builder: SIDDHI VINAYAK ENTERPRISE

siddhi vinayak enterprise has 7 registrations on GujRERA, including THE ATMOSPHERE and SHARNAM RESIDENCY. Read the full track record. See more projects on the Rajkot district page.

Frequently asked questions

What are my rights if NANDAN is delayed beyond 30 Apr 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of NANDAN?

The registered promoter entity is SIDDHI VINAYAK ENTERPRISE, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in NANDAN?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at NANDAN?

The professionals named in the filing: Architect: Parth Patel; Engineer: Sanjay Unjia. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in NANDAN?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About NANDAN. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save NANDAN to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.