Home / Browse projects / Mehsana, Gujarat / Matru Shakti

Valid until 30 Oct 2028 Residential/Group Housing project

Matru Shakti

By YASHVI CORPORATION

RG-GJ-54691 · RERA PR/GJ/MEHSANA/KADI/Kadi Municipality/RAA13226/010424/300628 · Last updated on GujRERA portal: 13 Jul 2026

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Oct 2028Possession promisedno revision filed
24 of 36Construction stages doneacross 4 buildings; furthest along: Sanitary fittings within the flats, 78%
10 of 34Units unsoldnot recorded sold or booked
Jump to the 41 documents Report an error

Matru Shakti is a Residential/Group Housing project by YASHVI CORPORATION in Mehsana, Gujarat, registered with GujRERA as PR/GJ/MEHSANA/KADI/Kadi Municipality/RAA13226/010424/300628 on 1 Apr 2024. Possession is promised by 30 Oct 2028. 24 of the 34 units on this registration are recorded sold or booked, and 24 of 36 construction stages are filed complete.

At a glance

Project

  • NameMatru Shakti
  • TypeResidential/Group Housing
  • Location
    • R.S.NO. 1290 AT&TA-KADI
    • DT-MEHSANA.
    • Kadi
    • Mehsana
    • 382715
  • Pincode382715
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/MEHSANA/KADI/Kadi Municipality/RAA13226/010424/300628
  • ReraGenie IDRG-GJ-54691

Builder

  • NameYASHVI CORPORATION
  • Entity typePARTNERSHIP FIRM
  • Other registrations1 more →

Key dates

this monthRegisteredApr 2024PromisedOct 2028

Key facts

Registration and timeline

  • StatusValid until 30 Oct 2028
  • Registered on1 Apr 2024
  • Promised completion30 Oct 2028
  • Revised completionNone
  • Buildings4 building records
  • Documents filed41 files

Current status

71%24 of 34 units booked
86.2%Of the estimated cost spent so far

Figures as on 13 Jul 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Type A2---16016
Type A1---16016
Type A4---101
Type A3---101

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building4

As on 13 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

24 of 36 construction stages are filed complete across 4 buildings. The stage furthest along is Sanitary fittings within the flats, at 78%.

Type A275%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats78%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
Type A173%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats53%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
Type A470%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats30%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
Type A374%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats70%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%

Progress on shared amenities19

As on 13 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes42%
Water supplyYes52%
Sewerage (chamber, lines, septic tank, STP)Yes85%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes0%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes0%
Water conservation, rain water harvestingNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Fire fightingNoNot applicable
Drinking water facilitiesYes0%
Emergency evacuationNoNot applicable
Use of renewable energyYes0%
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area6,378 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 4.65 cr
Cost incurredRs 4.01 cr
Spent of the estimate86.24%
BuildingWingEstimatedIncurred
Type A1NARs 2.24 crRs 1.91 cr
Type A2NARs 2.21 crRs 1.93 cr
Type A3NARs 14.24 lakhRs 11.83 lakh
Type A4NARs 5.58 lakhRs 4.54 lakh

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectHarsh Sureshbhai Patel
EngineerDHRUV VITTHALBHAI PATEL

Documents filed41

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/MEHSANA/KADI/Kadi Municipality/RAA13226/010424/300628 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)13 Jul 2026
Engineer's certificate (Form 2)13 Jul 2026
Engineer's certificate annexure13 Jul 2026
Accountant's certificate (Form 3)13 Jul 2026
Site photograph, Type A29 Jul 2026
Site photograph, Type A19 Jul 2026
Site photograph, Type A19 Jul 2026
Site photograph, Type A49 Jul 2026
Site photograph, Type A39 Jul 2026
RERA registration certificate1 Apr 2024
Proforma agreement for sale-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Drainage affidavit-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Approved sanctioned plan-
Approved layout plan-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Declaration in Form B-
Approved building or plotting plan-
NOCs from authorities-
Title clearance certificate-
Title report-
Property card-
Statutory document-
Project photograph-
Proforma sale deed-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Mehsana

71%of this project is bookeddistrict median 54%
11%of Mehsana projects moved their completion datethis one has not

Computed across the 200+ Mehsana projects on ReraGenie, from their own filings.

Keep Matru Shakti on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Kadi200+ in Mehsana

2 kmMatru ShaktiOther 25Dot size: filed unitsN

Filed coordinates, straight-line distance. 25 registered projects within 2 km.

Builder: YASHVI CORPORATION

YASHVI CORPORATION has 2 registrations on GujRERA, including Matru Shakti and MATRUBHAV. Read the full track record. See more projects on the Mehsana district page.

Frequently asked questions

What are my rights if Matru Shakti is delayed beyond 30 Oct 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of Matru Shakti?

The registered promoter entity is YASHVI CORPORATION, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in Matru Shakti?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Matru Shakti?

The professionals named in the filing: Architect: Harsh Sureshbhai Patel; Engineer: DHRUV VITTHALBHAI PATEL. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Matru Shakti?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Matru Shakti. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Matru Shakti to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.