Home / Browse projects / Surat, Gujarat / MANTRA IT CENTER

Valid until 31 Dec 2028 Commercial project

MANTRA IT CENTER

By MAHAMATI REALTY LLP

RG-GJ-39637 · RERA PR/GJ/SURAT/CHORYASI/Surat Municipal Corporation/CAA13217/300324/311228 · Last updated on GujRERA portal: 23 Dec 2025

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Dec 2028Possession promisedno revision filed
4 of 9Construction stages donefurthest along: Internal walls, 90%
111 of 209Units unsoldnot recorded sold or booked
Jump to the 31 documents Report an error

MANTRA IT CENTER is a Commercial project by MAHAMATI REALTY LLP in Surat, Gujarat, registered with GujRERA as PR/GJ/SURAT/CHORYASI/Surat Municipal Corporation/CAA13217/300324/311228 on 30 Mar 2024. Possession is promised by 31 Dec 2028. 98 of the 209 units on this registration are recorded sold or booked, and 4 of 9 construction stages are filed complete.

At a glance

Project

  • NameMANTRA IT CENTER
  • TypeCommercial
  • Location
    • T.P.S. NO: - 18 (MOTA VARACHHA)
    • BLOCK NO: 684/P/1
    • O.P. NO. : - 92
    • F.P. NO:- 93 (AS PER DRAFT)
    • 92 (AS PER AWARD)
    • MOJE: MOTA VARACHHA
    • TAL: ADAJAN
    • DIST:...
  • Pincode394101
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/SURAT/CHORYASI/Surat Municipal Corporation/CAA13217/300324/311228
  • ReraGenie IDRG-GJ-39637

Builder

  • NameMAHAMATI REALTY LLP
  • Entity typeLIMITED LIABILITY PARTNERSHIP FIRM

Key dates

this monthRegisteredMar 2024PromisedDec 2028

Key facts

Registration and timeline

  • StatusValid until 31 Dec 2028
  • Registered on30 Mar 2024
  • Promised completion31 Dec 2028
  • Revised completionNone
  • Buildings1 building record
  • Documents filed31 files

Current status

47%98 of 209 units booked
92.6%Of the estimated cost spent so far

Figures as on 23 Dec 2025, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---0209209

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 23 Dec 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 9 construction stages are filed complete. The stage furthest along is Internal walls, at 90%.

A: 93% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats90%
Sanitary fittings within the flats90%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing90%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing80%

Progress on shared amenities19

As on 23 Dec 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes50%
Water supplyYes50%
Sewerage (chamber, lines, septic tank, STP)Yes50%
Storm water drainsYes50%
Landscaping and tree plantingYes50%
Street lightingYes50%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterYes50%
Solid waste management and disposalYes50%
Water conservation, rain water harvestingYes50%
Energy managementYes50%
Fire protection and fire safety requirementsYes50%
Electrical meter room, sub-station, receiving stationYes50%
Fire fightingYes50%
Drinking water facilitiesYes50%
Emergency evacuationYes50%
Use of renewable energyYes50%
SecurityYes50%
Letter boxYes50%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,988 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 27.00 cr
Cost incurredRs 25.00 cr
Spent of the estimate92.59%
BuildingWingEstimatedIncurred
ANARs 27.00 crRs 25.00 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDimple Padmshibhai Mordiya
EngineerJIGAR HIMMATBHAI NAKRANI

Documents filed31

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/SURAT/CHORYASI/Surat Municipal Corporation/CAA13217/300324/311228 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)23 Dec 2025
Engineer's certificate (Form 2)23 Dec 2025
Engineer's certificate annexure23 Dec 2025
Accountant's certificate (Form 3)23 Dec 2025
Site photograph, A22 Dec 2025
RERA registration certificate30 Mar 2024
Proforma agreement for sale-
Auditor's report (3 of 3)-
Income tax return (3 of 3)-
Project specific document-
Drainage affidavit-
Directors' report (3 of 3)-
Approved sanctioned plan-
Approved layout plan-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Declaration in Form B-
Approved building or plotting plan-
NOCs from authorities-
Title clearance certificate-
Title report-
Property card-
Statutory document-
Project photograph-
Proforma sale deed-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (3 of 3)-

How this compares with Surat

47%of this project is bookeddistrict median 39%
15%of Surat projects moved their completion datethis one has not

Computed across the 2,600+ Surat projects on ReraGenie, from their own filings.

Keep MANTRA IT CENTER on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near MOTA VARACHHA2,600+ in Surat

2 kmMANTRA IT CENTEROther 235Dot size: filed unitsN

Filed coordinates, straight-line distance. 235 registered projects within 2 km.

Builder: MAHAMATI REALTY LLP

MAHAMATI REALTY LLP has 1 registration on GujRERA, including MANTRA IT CENTER. Read the full track record. See more projects on the Surat district page.

Frequently asked questions

What are my rights if MANTRA IT CENTER is delayed beyond 31 Dec 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of MANTRA IT CENTER?

The registered promoter entity is MAHAMATI REALTY LLP, a limited liability partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in MANTRA IT CENTER?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at MANTRA IT CENTER?

The professionals named in the filing: Architect: Dimple Padmshibhai Mordiya; Engineer: JIGAR HIMMATBHAI NAKRANI. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MANTRA IT CENTER?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MANTRA IT CENTER. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MANTRA IT CENTER to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.