Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Jul 2030Possession promisedno revision filed
4 of 18Construction stages doneacross 2 buildings; furthest along: Slabs of Super Structure, 66%
191 of 219Units unsoldnot recorded sold or booked
Jump to the 26 documents Report an error

MAHADEV GLORY is a Mixed Development project by SHIV ESTATE DEVELOPERS in Ahmedabad, Gujarat, registered with GujRERA as PR/GJ/AHMEDABAD/AHMEDABAD CITY/Ahmedabad Municipal Corporation/MAA15369/230625/310330 on 23 Jun 2025. Possession is promised by 31 Jul 2030. 28 of the 219 units on this registration are recorded sold or booked, and 4 of 18 construction stages are filed complete.

At a glance

Project

  • NameMAHADEV GLORY
  • TypeMixed Development
  • Location
    • SAFAL PARISAR ROAD
    • NR. AASTHA AVIRAT
    • SOUTH-BOPAL
    • GHUMA
    • Ahmedabad City
    • Ahmedabad
    • 380058
  • Pincode380058
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/AHMEDABAD/AHMEDABAD CITY/Ahmedabad Municipal Corporation/MAA15369/230625/310330
  • ReraGenie IDRG-GJ-94696

Builder

  • NameSHIV ESTATE DEVELOPERS
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredJun 2025PromisedJul 2030

Key facts

Registration and timeline

  • StatusValid until 31 Jul 2030
  • Registered on23 Jun 2025
  • Promised completion31 Jul 2030
  • Revised completionNone
  • Buildings2 building records
  • Documents filed26 files

Current status

13%28 of 219 units booked
38.4%Of the estimated cost spent so far

Figures as on 13 May 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---521365
B+C+D---1540154

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building2

As on 13 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 18 construction stages are filed complete across 2 buildings. The stage furthest along is Slabs of Super Structure, at 66%.

A37%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor35%
Slabs of Super Structure60%
Internal walls, internal plaster, floorings, doors and windows within flats15%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks25%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
B+C+D40%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor40%
Slabs of Super Structure66%
Internal walls, internal plaster, floorings, doors and windows within flats20%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks30%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%

Progress on shared amenities19

As on 13 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes0%
Water supplyYes45%
Sewerage (chamber, lines, septic tank, STP)Yes20%
Storm water drainsYes10%
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterYes0%
Solid waste management and disposalYes0%
Water conservation, rain water harvestingYes0%
Energy managementYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingYes0%
Drinking water facilitiesYes0%
Emergency evacuationYes0%
Use of renewable energyYes0%
SecurityYes0%
Letter boxYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,996 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 43.00 cr
Cost incurredRs 16.50 cr
Spent of the estimate38.37%
BuildingWingEstimatedIncurred
B+C+DNARs 23.00 crRs 9.20 cr
ANARs 20.00 crRs 7.30 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectUrvashi Lalitkumar Tuli
EngineerJAYESH DINESHCHANDRA DESAI

Documents filed26

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/AHMEDABAD/AHMEDABAD CITY/Ahmedabad Municipal Corporation/MAA15369/230625/310330 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)13 May 2026
Engineer's certificate (Form 2)13 May 2026
Engineer's certificate annexure13 May 2026
Accountant's certificate (Form 3)13 May 2026
Site photograph, A13 May 2026
Site photograph, B+C+D13 May 2026
RERA registration certificate23 Jun 2025
Proforma agreement for sale-
Project specific document-
Approved sanctioned plan-
Approved layout plan-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Declaration in Form B-
Approved building or plotting plan-
NOCs from authorities-
Title clearance certificate-
Title report-
Property card-
Statutory document-
Other document-
Project photograph-
Proforma sale deed-

How this compares with Ahmedabad

13%of this project is bookeddistrict median 53%
14%of Ahmedabad projects moved their completion datethis one has not

Computed across the 5,400+ Ahmedabad projects on ReraGenie, from their own filings.

Keep MAHADEV GLORY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near GHUMA5,400+ in Ahmedabad

2 kmMAHADEV GLORYOther 212Dot size: filed unitsN

Filed coordinates, straight-line distance. 212 registered projects within 2 km.

Builder: SHIV ESTATE DEVELOPERS

SHIV ESTATE DEVELOPERS has 1 registration on GujRERA, including MAHADEV GLORY. Read the full track record. See more projects on the Ahmedabad district page.

Frequently asked questions

What are my rights if MAHADEV GLORY is delayed beyond 31 Jul 2030?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of MAHADEV GLORY?

The registered promoter entity is SHIV ESTATE DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in MAHADEV GLORY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at MAHADEV GLORY?

The professionals named in the filing: Architect: Urvashi Lalitkumar Tuli; Engineer: JAYESH DINESHCHANDRA DESAI. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MAHADEV GLORY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MAHADEV GLORY. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MAHADEV GLORY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.