Home / Browse projects / Yadgir, Karnataka / M K R BHAGYA TOWERS
M K R BHAGYA TOWERS
RG-KA-05979 · RERA PRM/KA/RERA/1276/421/PR/300124/006582 · Last updated on RERA Karnataka portal: 10 Jan 2026
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
M K R BHAGYA TOWERS is a Residential/Group Housing project by M K R ASSOCIATES in Yadgir, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1276/421/PR/300124/006582 on 30 Jan 2024. Possession is promised by 31 Dec 2025. 0 of the 21 units on this registration are recorded sold or booked, and 16 of 16 construction stages are filed complete.
At a glance
Project
- NameM K R BHAGYA TOWERS
- TypeResidential/Group Housing
- Location
- Yadgir
- 585202
- Pincode585202
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1276/421/PR/300124/006582
- ReraGenie IDRG-KA-05979
Builder
- NameM K R ASSOCIATES
- Entity typePartnership Firm
- GSTIN29ABJFM7354B1Z4
- Authorized SignatoryM KOTESHWAR RAO S/O M NAGESHWAR RAO
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on30 Jan 2024
- Promised completion31 Dec 2025
- Revised completionNone
- Buildings1 building record
- Documents filed123 files
Current status
Figures as on 10 Jan 2026, this project's latest RERA Karnataka filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| M K R BHAGYA TOWERS | - | - | - | 21 | 0 | 21 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 10 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
16 of 16 construction stages are filed complete.
Building: 100% average across the applicable activities
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | 100% |
| Foundation footing work | 100% |
| Upto Plinth Level | 100% |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | 100% |
| Retaining wall (All types) | 100% |
| RCC or MS Framed structure | 100% |
| Masonry Construction | 100% |
| Plastering inside , outside & Ceiling | 100% |
| Joinery: Doors, Windows, Ventilators etc | 100% |
| Basic work of Water supply, Sanitary and Electrification | 100% |
| Dadoing, Skirting, Flooring, Tiles work (All types) | 100% |
| Railing and Grill fixing | 100% |
| Electrification, Water supply and Sanitary Finishing | 100% |
| Painting | 100% |
| Fire prevention and fire fighting fitting and fixture with network | Not applicable |
| Weather Proof work(tile,concrete) | Not applicable |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | 100% |
| Elevation work | 100% |
| Internal and External work including landscapes as per sanctioned drawings | Not applicable |
Progress on shared amenities41
As on 10 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | 100% |
| Sewage and Drainage System | No | Not applicable |
| Water conservation/rain water harvesting/recharge of ground water | No | Not applicable |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Solid waste management and disposal | No | Not applicable |
| Emergency Evacuation services | No | Not applicable |
| Internal Roads & Footpaths | No | Not applicable |
| Electricity supply transformer and substation | No | Not applicable |
| Storm water drains | No | Not applicable |
| Use of renewable energy | No | Not applicable |
| Sewage Treatment Plant (STP) | No | Not applicable |
| Parks & Tree planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Electricity | Yes | 100% |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | No | Not applicable |
| Club House | No | Not applicable |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | No | Not applicable |
| Gym | No | Not applicable |
| Parks | No | Not applicable |
| Power Backup | No | Not applicable |
| Piped Gas | No | Not applicable |
| Water and Sanitation | No | Not applicable |
| Air Conditioning | No | Not applicable |
| Staircases | Yes | 100% |
| Lifts | Yes | 100% |
| Corridor/Lobbies | Yes | 100% |
| Fire escapes | No | Not applicable |
| Common entrance and exit for the building/common portico/foyer/verandah | Yes | 100% |
| Basement | Yes | 100% |
| Terrace | Yes | 100% |
| Outer Wall | Yes | 100% |
| Open parking areas | No | Not applicable |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | No | Not applicable |
| Common storage spaces | No | Not applicable |
| STAIRCASE, LIFT, LOBBY & CORRIDOR INCLUDING DUCTS IN ALL FLOOR | Yes | 100% |
Land and ownership2
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| M KOTESHWAR RAO S/O M NAGESHWAR RAO | - | - |
| M BHAGYA JYOTI W/O M KOTESHWAR RAO | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 5.00 cr | Rs 5.00 cr |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | FIRDOUS KHANAM |
| Engineer | MOHAMMED WAJEED ALI |
| Chartered Accountant | MOHAMMED KHAJA MOINUDDIN |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed123
As listed on the registration, under the names the promoter filed them with; the newest 80 of 123 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1276/421/PR/300124/006582 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Certificate issued by Chartered Accountant.pdf | 10 Jan 2026 |
| Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Certificate issued by Architect.pdf | 10 Jan 2026 |
| Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Certificate issued by Engineer.pdf | 10 Jan 2026 |
| Uploaded in Portal and Built up area relevant documentFile: Uploaded in Portal and Built up area relevant documents.pdf | 18 Jan 2024 |
| Uploaded Declaration letter for Height of the buildingFile: Declaration letter for Height of Building as per sanction plan.pdf | 18 Jan 2024 |
| Uploaded Single plot layout OrderFile: Uploaded Single plot layout Order.pdf | 18 Jan 2024 |
| Uploaded village map showing the proposed siteFile: Uploaded village map showing the proposed site.pdf | 18 Jan 2024 |
| Uploaded project specificationFile: Uploaded Project Specification.pdf | 18 Jan 2024 |
| Uploaded in Portal and Plinth up area relevant documentFile: Uploaded in Portal and Built up area relevant documents.pdf | 18 Jan 2024 |
| Uploaded Brief estimated cost of construction certified by the registered Civil EngineerFile: Brief estimated cost of construction certified by the registered CivilEngineer.pdf | 18 Jan 2024 |
| Uploaded the proforma of Agreement for Sale notified by GOKFile: Upload the proforma of Agreement for Sale notified by GOK.pdf | 18 Jan 2024 |
| Uploaded Declaration regarding Water board NOC and Gescom NOCFile: Declaration regarding Water board NOC and Gescom NOC.pdf | 18 Jan 2024 |
| Uploaded Land cost calculation sheet as per the guidance value with self-attestedFile: Land cost calculation sheet as per the guidance value with self-attested.pdf | 18 Jan 2024 |
| Uploaded Notarized JD AFFIDAVIT CUM DECLARATIONFile: Notarized Joint Affidavit cum declaration.pdf | 8 Jan 2024 |
| Uploaded Built up area relevant documentFile: Built up area relevant document.pdf | 8 Jan 2024 |
| Uploaded Height of the building relevant documentFile: Height of the building relevant document.pdf | 8 Jan 2024 |
| Uploaded Single plot layout OrderFile: Single Plot Layout Order.pdf | 8 Jan 2024 |
| Uploaded Village map showing the proposed siteFile: Village map showing the proposed site.pdf | 8 Jan 2024 |
| Uploaded Declaration regarding Project Status New project launchFile: Declaration regarding Project Status New project launch.pdf | 8 Jan 2024 |
| Uploaded Brief estimated cost of construction certified by the registered Civil EngineerFile: Brief estimated cost of construction certified by the registered Civil Engineer.pdf | 8 Jan 2024 |
| Uploaded Proforma of Agreement for SaleFile: Proforma of Agreement for Sale.pdf | 8 Jan 2024 |
| Uploaded Declaration self-attested copy of the Power supply NOC and Water supply NOCFile: Declaration regarding Water board NOC and Gescom NOC.pdf | 8 Jan 2024 |
| Uploaded STP design drawing certified by the EngineerFile: STP design drawing certified by the Engineer.pdf | 8 Jan 2024 |
| Uploaded Land cost calculation sheet as per the guidance value with self-attestedFile: Land cost calculation sheet as per the guidance value with self-attested.pdf | 8 Jan 2024 |
| Uploaded Section 3 of 1 Notarized AffidavitFile: Section 3 of 1 Notarized Affidavit.pdf | 8 Jan 2024 |
| Uploaded CA certificate form-01 in the prescribed formatFile: CA certificate form-01 in the prescribed format.pdf | 23 Dec 2023 |
| Uploaded Financial statements with promoter signature Balance sheet P&L 2020-21File: Financial statements with promoter signature Balance sheet P&L 2020-21.pdf | 23 Dec 2023 |
| Uploaded Financial statements with promoter signature Balance sheet P&L 2021-22File: Financial statements with promoter signature Balance sheet P&L 2021-22.pdf | 23 Dec 2023 |
| Uploaded Financial statements with promoter signature Balance sheet P&L 2022-23File: Financial statements with promoter signature Balance sheet P&L 2022-23.pdf | 23 Dec 2023 |
| Uploaded RTCFile: RTC.pdf | 23 Dec 2023 |
| Uploaded ECFile: EC.pdf | 23 Dec 2023 |
| Uploaded Tittle deed of a land owner at sub registrar officeFile: Tittle deed of a land owner at sub registrar.pdf | 23 Dec 2023 |
| Uploaded Declaration regarding FAR As per the sanction PlanFile: Declaration regarding FAR As per the sanction Plan.pdf | 23 Dec 2023 |
| Uploaded Built up area Mentioned in the project details page relevant documentsFile: As per paln Built up area Mentioned in the project details page and attached relevant docu | 23 Dec 2023 |
| Uploaded Single plot layout OrderFile: Single Plot Layout Order.pdf | 23 Dec 2023 |
| Uploaded Certified Carpet area calculationFile: Certified Carpet area calculation.pdf | 23 Dec 2023 |
| Uploaded Village map showing the proposed siteFile: Village map showing the proposed site.pdf | 23 Dec 2023 |
| Uploaded Approved drawing along with the area calculation sheet certified by the EngineerFile: Approved drawing along with the area calculation sheet certified by the Engineer.pdf | 23 Dec 2023 |
| Uploaded Declaration regarding Project Status New project launchFile: Declaration regarding Project Status New project launch.pdf | 23 Dec 2023 |
| Uploaded Amenities and Common area details calculation sheet certified by the EngineerFile: Amenities and Common area details calculation sheet certified by the Engineer.pdf | 23 Dec 2023 |
| Uploaded the Engineer certificate in the prescribed formatFile: Engineer certificate in the prescribed format.pdf | 23 Dec 2023 |
| Uploaded project specification certified by the Engineer pertains to this projectFile: Project specification certified by the Engineer.pdf | 23 Dec 2023 |
| Brief estimated cost of construction certified by the registered Civil EngineerFile: Brief estimated cost of construction certified by the registered Civil Engineer.pdf | 23 Dec 2023 |
| Uploaded the proforma of the Agreement for SaleFile: Proforma of the Agreement for Sale.pdf | 23 Dec 2023 |
| Uploaded Declaration regarding Water board NOC and Gescom NOCFile: Declaration regarding Water board NOC and Gescom NOC.pdf | 23 Dec 2023 |
| STP design drawing certified by the EngineerFile: STP design drawing certified by the Engineer.pdf | 23 Dec 2023 |
| Uploaded Declaration Reason for the delay in RERA registration along with the sold and unsold detailFile: Reason for the delay in RERA registration along with the sold and unsold details.pdf | 23 Dec 2023 |
| Uploaded Land cost calculation sheet as per the guidance value with self-attestedFile: Land cost calculation sheet as per the guidance value with self-attested.pdf | 23 Dec 2023 |
| Uploaded Section 3 of 1 Notarized AffidavitFile: Section 3 of 1 Notarized Affidavit.pdf | 23 Dec 2023 |
| Uploaded the area calculation sheet certified by the Engineer WITH APPROVED DRAWINGFile: Area calculation sheet certified by the Engineer WITH APPROVED DRAWING.pdf | 23 Dec 2023 |
| RTC, survey 326/6 | - |
| Mutation, survey 326/6 | - |
| Encumbrance Certificate, survey 326/6 | - |
| Conversion/Alienation Order, survey 326/6 | - |
| Sale/Title/Gift Deed, survey 326/6 | - |
| Khatha, survey 326/6 | - |
| Registration CertificateFile: Firm Registration certificate.pdf | - |
| Partnership DeedFile: Partnership Deed.pdf | - |
| Partner Details | - |
| Partner Details | - |
| Certificate issued by CA Form 1File: Certificate issued by CA Form 1.pdf | - |
| Certificate issued by Architect Form 2File: Certificate issued by Architect Form 2.pdf | - |
| Certificate issued by Engineer Form 3File: Certificate issued by Engineer Form 3.pdf | - |
| Project Chartered Accountant | - |
| Project Engineer | - |
| Project Architect | - |
| AffidavitFile: Non Litigation Affidavit.pdf | - |
| Certificate from Chartered AccountFile: Certificate from CA.pdf | - |
| Balance Sheet 2022 - 2023File: Balance sheet 2023-24.pdf | - |
| Balance Sheet 2021 - 2022File: Balance sheet 2022-23.pdf | - |
| Balance Sheet 2020 - 2021File: Balance sheet 2021-22.pdf | - |
| Audited Profit and Loss Statement 2022 - 2023File: Profit & Loss 2023-24.pdf | - |
| Audited Profit and Loss Statement 2021 - 2022File: Profit & Loss 2022-23.pdf | - |
| Audited Profit and Loss Statement 2020 - 2021File: Profit & Loss 2021-22.pdf | - |
| Income Tax Return Acknowledgement 2022 - 2023File: ACK 2023-24.pdf | - |
| Income Tax Return Acknowledgement 2021 - 2022File: ACK 2022- 23.pdf | - |
| Income Tax Return Acknowledgement 2020 - 2021File: ACK 2021-22.pdf | - |
| Muncipal Council | - |
| Approved Building Plan | - |
| Approved Building Plan | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
Keep M K R BHAGYA TOWERS on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Yadgir15 in Yadgir
CONSTRUCTION OF 200 HOUSED IN SHORAPUR TOWN
KARNATAKA SLUM DEVELOPMENT BOARD
CONSTRUCTION OF 200 HOUSES IN GURUMITKAL TOWN
KARNATAKA SLUM DEVELOPMENT BOARD
Construction of 250 houses at yadgiri city.
KARNATAKA SLUM DEVELOPMENT BOARD
DEESHA I
Satish Kandkur
Deesha II
Satish Kandkur
K R PANCHAMGIRI TOWNSHIP
RAGHAVENDRA PANCHAMGIRI
See every Yadgir project, with the district possession charts
Builder: M K R ASSOCIATES
M K R ASSOCIATES has 1 registration on RERA Karnataka, including M K R BHAGYA TOWERS. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Yadgir district page.
Frequently asked questions
What are my rights if M K R BHAGYA TOWERS is delayed beyond 31 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of M K R BHAGYA TOWERS?
The registered promoter entity is M K R ASSOCIATES, a partnership firm as per the filing. Its GSTIN 29ABJFM7354B1Z4 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in M K R BHAGYA TOWERS?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at M K R BHAGYA TOWERS?
The professionals named in the filing: Architect: FIRDOUS KHANAM; Engineer: MOHAMMED WAJEED ALI; Chartered Accountant: MOHAMMED KHAJA MOINUDDIN. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in M K R BHAGYA TOWERS?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback