Home / Browse projects / Bhavnagar, Gujarat / LOTUS CORPORATE

Valid until 1 Aug 2020 Commercial project

LOTUS CORPORATE

By Lotus Real Estate

RG-GJ-88129 · RERA PR/GJ/BHAVNAGAR/BHAVNAGAR/Others/CAA04745/EX1/161219 · Last updated on GujRERA portal: 6 Dec 2019

Source: official GujRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • Separate project account declared
Aug 2020Possession promisedmoved 12 months from the original
3 of 8Construction stages donefurthest along: Internal walls, 85%
16 of 16Units unsoldnot recorded sold or booked
Jump to the 38 documents Report an error

LOTUS CORPORATE is a Commercial project by Lotus Real Estate in Bhavnagar, Gujarat, registered with GujRERA as PR/GJ/BHAVNAGAR/BHAVNAGAR/Others/CAA04745/EX1/161219 on 24 Jan 2019. Possession is promised by 1 Aug 2020. The completion date has moved by 12 months from the original filing. 0 of the 16 units on this registration are recorded sold or booked, and 3 of 8 construction stages are filed complete.

At a glance

Project

  • NameLOTUS CORPORATE
  • TypeCommercial
  • Location
    • PLOT NO. 734/734A
    • VIJAYRAJNAGAR
    • Bhavnagar
    • 364003
  • Pincode364003
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/BHAVNAGAR/BHAVNAGAR/Others/CAA04745/EX1/161219
  • ReraGenie IDRG-GJ-88129

Builder

  • NameLotus Real Estate
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredJan 2019First promiseAug 2019Revised toAug 2020

Key facts

Registration and timeline

  • StatusValid until 1 Aug 2020
  • Registered on24 Jan 2019
  • Promised completion1 Aug 2020
  • Revised completionRevised to 1 Aug 2020 (originally 5 Aug 2019)
  • Buildings1 building record
  • Documents filed38 files

Current status

0%0 of 16 units booked
85.0%Of the estimated cost spent so far

Figures as on 6 Dec 2019, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---01616

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 6 Dec 2019, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 8 construction stages are filed complete. The stage furthest along is Internal walls, at 85%.

A: 82% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats85%
Sanitary fittings within the flats20%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks85%
External plumbing and external plaster, elevation, completion of terraces with waterproofing85%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing85%

Progress on shared amenities19

As on 6 Dec 2019, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsNoNot applicable
Water supplyYes20%
Sewerage (chamber, lines, septic tank, STP)NoNot applicable
Storm water drainsNoNot applicable
Landscaping and tree plantingNoNot applicable
Street lightingNoNot applicable
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes30%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes30%
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area401 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 90.00 lakh
Cost incurredRs 76.50 lakh
Spent of the estimate85.0%
BuildingWingEstimatedIncurred
ANARs 90.00 lakhRs 76.50 lakh

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectALOK H. BHATT
EngineerBHAVESH VYAS

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/BHAVNAGAR/BHAVNAGAR/Others/CAA04745/EX1/161219Applied Dec 2019; approved Dec 2019

Documents filed38

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/BHAVNAGAR/BHAVNAGAR/Others/CAA04745/EX1/161219 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)6 Dec 2019
Architect's certificate (Form 1)6 Nov 2019
Site photograph, A6 Nov 2019
RERA registration certificate24 Jan 2019
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-
Engineer's certificate (Form 2)-
Engineer's certificate annexure-

How this compares with Bhavnagar

0%of this project is bookeddistrict median 50%
16%of Bhavnagar projects moved their completion datethis one moved by 12 months

Computed across the 730+ Bhavnagar projects on ReraGenie, from their own filings.

Keep LOTUS CORPORATE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bhavnagar730+ in Bhavnagar

2 kmLOTUS CORPORATEOther 75Dot size: filed unitsN

Filed coordinates, straight-line distance. 75 registered projects within 2 km.

Builder: Lotus Real Estate

Lotus Real Estate has 1 registration on GujRERA, including LOTUS CORPORATE. Read the full track record. See more projects on the Bhavnagar district page.

Frequently asked questions

What are my rights if LOTUS CORPORATE is delayed beyond 1 Aug 2020?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of LOTUS CORPORATE?

The registered promoter entity is Lotus Real Estate, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in LOTUS CORPORATE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at LOTUS CORPORATE?

The professionals named in the filing: Architect: ALOK H. BHATT; Engineer: BHAVESH VYAS. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in LOTUS CORPORATE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About LOTUS CORPORATE. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save LOTUS CORPORATE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.