Home / Browse projects / Valsad, Gujarat / LAXMI VILAS

Valid until 29 Sep 2024 Mixed Development project

LAXMI VILAS

By PUSHYANT PRAVINCHANDRA SHAH

RG-GJ-75144 · RERA PR/GJ/VALSAD/PARDI/Vapi Municipality/MAA03630/A1M/EX2/191124/300324 · Last updated on GujRERA portal: 5 Sep 2025

Source: official GujRERA filing

Red flags

  • Completion date moved by 18 months
  • 3 extensions taken

Clear

  • Nothing verified clear yet
Sep 2024Possession promisedmoved 18 months from the original
8 of 9Construction stages donefurthest along: Stilt Floor, 0%
39 of 66Units unsoldnot recorded sold or booked
Jump to the 46 documents Report an error

LAXMI VILAS is a Mixed Development project by PUSHYANT PRAVINCHANDRA SHAH in Valsad, Gujarat, registered with GujRERA as PR/GJ/VALSAD/PARDI/Vapi Municipality/MAA03630/A1M/EX2/191124/300324 on 8 Oct 2018. Possession is promised by 29 Sep 2024. The completion date has moved by 18 months from the original filing. 27 of the 66 units on this registration are recorded sold or booked, and 8 of 9 construction stages are filed complete.

At a glance

Project

  • NameLAXMI VILAS
  • TypeMixed Development
  • Location
    • SR.NO. 9
    • 11/2
    • 11/3
    • 11/3P1
    • 1063
    • C SR.3214 PLOT10 NEAR RAILWAY UNDER BRIDGE
    • NALA FALIYA
    • JAIN STREET
    • VAPI
    • VAPI
    • Pardi
    • Valsad
    • 396191
  • Pincode396191
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VALSAD/PARDI/Vapi Municipality/MAA03630/A1M/EX2/191124/300324
  • ReraGenie IDRG-GJ-75144

Builder

  • NamePUSHYANT PRAVINCHANDRA SHAH
  • Entity typeIndividual/Propritorship

Key dates

this monthRegisteredOct 2018First promiseMar 2023Revised toSep 2024

Key facts

Registration and timeline

  • StatusValid until 29 Sep 2024
  • Registered on8 Oct 2018
  • Promised completion29 Sep 2024
  • Revised completionRevised to 29 Sep 2024 (originally 30 Mar 2023)
  • Buildings1 building record
  • Documents filed46 files

Current status

41%27 of 66 units booked
85.5%Of the estimated cost spent so far

Figures as on 5 Sep 2025, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
LAXMI VILAS---481866

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 5 Sep 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 9 construction stages are filed complete. The stage furthest along is Stilt Floor, at 0%.

LAXMI VILAS: 89% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 5 Sep 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingNoNot applicable
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingYes100%
Drinking water facilitiesYes100%
Emergency evacuationYes100%
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,856 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 10.87 cr
Cost incurredRs 9.29 cr
Spent of the estimate85.53%
BuildingWingEstimatedIncurred
LAXMI VILASNARs 10.87 crRs 9.29 cr

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionApplied Dec 2020; no approval date filed
PR/GJ/VALSAD/PARDI/Others/MAA03630/EX1/150623Applied Mar 2023; approved Jun 2023
PR/GJ/VALSAD/PARDI/Others/MAA03630/EX2/310824/290924Applied Jun 2024; approved Aug 2024

Documents filed46

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VALSAD/PARDI/Vapi Municipality/MAA03630/A1M/EX2/191124/300324 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)5 Sep 2025
Architect's certificate (Form 1)3 Sep 2025
Site photograph, LAXMI VILAS2 Sep 2025
Engineer's certificate (Form 2)21 Mar 2024
Engineer's certificate annexure21 Mar 2024
RERA registration certificate8 Oct 2018
Extension certificate-
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Drainage affidavit-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Approved building or plotting plan-
NOCs from authorities-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Proforma sale deed-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Valsad

41%of this project is bookeddistrict median 45%
23%of Valsad projects moved their completion datethis one moved by 18 months

Computed across the 390+ Valsad projects on ReraGenie, from their own filings.

Keep LAXMI VILAS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near VAPI390+ in Valsad

2 kmLAXMI VILASOther 94Dot size: filed unitsN

Filed coordinates, straight-line distance. 94 registered projects within 2 km.

Builder: PUSHYANT PRAVINCHANDRA SHAH

PUSHYANT PRAVINCHANDRA SHAH has 1 registration on GujRERA, including LAXMI VILAS. Read the full track record. See more projects on the Valsad district page.

Frequently asked questions

What are my rights if LAXMI VILAS is delayed beyond 29 Sep 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of LAXMI VILAS?

The registered promoter entity is PUSHYANT PRAVINCHANDRA SHAH, an individual/propritorship as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in LAXMI VILAS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

What should I check before booking in LAXMI VILAS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About LAXMI VILAS. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save LAXMI VILAS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.