Home / Browse projects / Mehsana, Gujarat / JANNAT CITY PART-D

Valid until 30 Jun 2024 Mixed Development project

JANNAT CITY PART-D

By Amrishbhai chandulal patel (PROPRITOR OF SHREE RAMYA BUILDERS)

RG-GJ-68473 · RERA PR/GJ/MEHSANA/KADI/Others/MAA05686/100719 · Last updated on GujRERA portal: 20 Apr 2021

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
  • Separate project account declared
Jun 2024Possession promisedno revision filed
40 of 41Construction stages doneacross 5 buildings; furthest along: Stilt Floor, 0%
30 of 59Units unsoldnot recorded sold or booked
Jump to the 45 documents Report an error

JANNAT CITY PART-D is a Mixed Development project by Amrishbhai chandulal patel (PROPRITOR OF SHREE RAMYA BUILDERS) in Mehsana, Gujarat, registered with GujRERA as PR/GJ/MEHSANA/KADI/Others/MAA05686/100719 on 10 Jul 2019. Possession is promised by 30 Jun 2024. 29 of the 59 units on this registration are recorded sold or booked, and 40 of 41 construction stages are filed complete.

At a glance

Project

  • NameJANNAT CITY PART-D
  • TypeMixed Development
  • Location
    • Jannat City Part-D
    • Mota talav Road
    • Nr. Ambika jin
    • Nandasan Road-Kadi
    • North Gujarat
    • India
    • Kadi
    • Mehsana
    • 382715
  • Pincode382715
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/MEHSANA/KADI/Others/MAA05686/100719
  • ReraGenie IDRG-GJ-68473

Builder

  • NameAmrishbhai chandulal patel (PROPRITOR OF SHREE RAMYA BUILDERS)
  • Entity typeIndividual/Propritorship

Key dates

this monthRegisteredJul 2019PromisedJun 2024

Key facts

Registration and timeline

  • StatusValid until 30 Jun 2024
  • Registered on10 Jul 2019
  • Promised completion30 Jun 2024
  • Revised completionNone
  • Buildings5 building records
  • Documents filed45 files

Current status

49%29 of 59 units booked
83.2%Of the estimated cost spent so far

Figures as on 20 Apr 2021, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Duplex Type B---12012
Duplex Type C---31031
Duplex Type D---101
Tower A---10414
Duplex Type A---101

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building5

As on 20 Apr 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

40 of 41 construction stages are filed complete across 5 buildings. The stage furthest along is Stilt Floor, at 0%.

Duplex Type B100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Duplex Type C100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Duplex Type D100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Tower A89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Duplex Type A100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 20 Apr 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsNoNot applicable
Landscaping and tree plantingNoNot applicable
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Fire fightingNoNot applicable
Drinking water facilitiesYes100%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,180 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 3.65 cr
Cost incurredRs 3.04 cr
Spent of the estimate83.16%
BuildingWingEstimatedIncurred
Duplex Type ANARs 73.10 lakhRs 60.79 lakh
Duplex Type BNARs 73.10 lakhRs 60.79 lakh
Duplex Type CNARs 73.10 lakhRs 60.79 lakh
Duplex Type DNARs 73.10 lakhRs 60.79 lakh
Tower ANARs 73.10 lakhRs 60.79 lakh

Certifying professionals and partners1

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectLAXMAN C SUTHAR

Documents filed45

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/MEHSANA/KADI/Others/MAA05686/100719 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)20 Apr 2021
Engineer's certificate (Form 2)20 Apr 2021
Engineer's certificate annexure20 Apr 2021
Accountant's certificate (Form 3)20 Apr 2021
Site photograph, Duplex Type B20 Apr 2021
Site photograph, Duplex Type C20 Apr 2021
Site photograph, Duplex Type D20 Apr 2021
Site photograph, Tower A20 Apr 2021
Site photograph, Duplex Type A20 Apr 2021
RERA registration certificate10 Jul 2019
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Mehsana

49%of this project is bookeddistrict median 54%
11%of Mehsana projects moved their completion datethis one has not

Computed across the 200+ Mehsana projects on ReraGenie, from their own filings.

Keep JANNAT CITY PART-D on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Kadi200+ in Mehsana

2 kmJANNAT CITY PART-DOther 25Dot size: filed unitsN

Filed coordinates, straight-line distance. 25 registered projects within 2 km.

Builder: Amrishbhai chandulal patel (PROPRITOR OF SHREE RAMYA BUILDERS)

Amrishbhai chandulal patel (PROPRITOR OF SHREE RAMYA BUILDERS) has 1 registration on GujRERA, including JANNAT CITY PART-D. Read the full track record. See more projects on the Mehsana district page.

Frequently asked questions

What are my rights if JANNAT CITY PART-D is delayed beyond 30 Jun 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of JANNAT CITY PART-D?

The registered promoter entity is Amrishbhai chandulal patel (PROPRITOR OF SHREE RAMYA BUILDERS), an individual/propritorship as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in JANNAT CITY PART-D?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at JANNAT CITY PART-D?

The professionals named in the filing: Architect: LAXMAN C SUTHAR. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in JANNAT CITY PART-D?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About JANNAT CITY PART-D. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save JANNAT CITY PART-D to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.