ReraGenieLog inGet a buyer report

Home / Browse projects / Ahmedabad, Gujarat / JALDHARA RESIDENCY

Valid until 31 Dec 2026 Mixed Development project

JALDHARA RESIDENCY

By EVERGREEN DEVELOPERS

RG-GJ-02381 · RERA PR/GJ/AHMEDABAD/DASKROI/Ahmedabad Municipal Corporation/MN271AA10171/121222 · Last updated on GujRERA portal: 26 Jun 2025

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Dec 2026Possession promisedno revision filed
36 of 36Construction stages doneacross 4 buildings; every applicable stage filed complete
15 of 211Units unsoldnot recorded sold or booked
Jump to the 33 documents Report an error

JALDHARA RESIDENCY is a Mixed Development project by EVERGREEN DEVELOPERS in Ahmedabad, Gujarat, registered with GujRERA as PR/GJ/AHMEDABAD/DASKROI/Ahmedabad Municipal Corporation/MN271AA10171/121222 on 12 Dec 2022. Possession is promised by 31 Dec 2026. 196 of the 211 units on this registration are recorded sold or booked, and 36 of 36 construction stages are filed complete.

At a glance

Project

  • NameJALDHARA RESIDENCY
  • TypeMixed Development
  • Location
    • JALDHARA RESIDENCY
    • OPP RIYASAT PARTY PLOT
    • B/H. GALAXY HOMES
    • UDAY AUTOLINK
    • KATHWADA ROAD
    • KATHWADA
    • AHMEDABAD- 382430.
    • KATHWADA
    • Daskroi
    • Ahmedabad
    • 382430
  • Pincode382430
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/AHMEDABAD/DASKROI/Ahmedabad Municipal Corporation/MN271AA10171/121222
  • ReraGenie IDRG-GJ-02381

Builder

  • NameEVERGREEN DEVELOPERS
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredDec 2022PromisedDec 2026

Key facts

Registration and timeline

  • StatusValid until 31 Dec 2026
  • Registered on12 Dec 2022
  • Promised completion31 Dec 2026
  • Revised completionNone
  • Buildings4 building records
  • Documents filed33 files

Current status

93%196 of 211 units booked
71.1%Of the estimated cost spent so far

Figures as on 26 Jun 2025, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BLOCK-A---40545
BLOCK-B---40646
BLOCK-C+D---80080
BLOCK-E---40040

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building4

As on 26 Jun 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

36 of 36 construction stages are filed complete across 4 buildings.

BLOCK-A100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
BLOCK-B100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
BLOCK-C+D100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
BLOCK-E100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 26 Jun 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes100%
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingNoNot applicable
Drinking water facilitiesYes100%
Emergency evacuationNoNot applicable
Use of renewable energyYes100%
SecurityYes100%
Letter boxYes100%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,941 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 32.83 cr
Cost incurredRs 23.34 cr
Spent of the estimate71.08%
BuildingWingEstimatedIncurred
BLOCK-C+DNARs 16.63 crRs 8.35 cr
BLOCK-ANARs 5.40 crRs 5.32 cr
BLOCK-BNARs 5.40 crRs 4.40 cr
BLOCK-ENARs 5.40 crRs 5.27 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectBHUMIKA JITENDRAKUMAR KAPADIYA
EngineerYAMINIBEN AKASHKUMAR PARMAR

Documents filed33

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/AHMEDABAD/DASKROI/Ahmedabad Municipal Corporation/MN271AA10171/121222 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)26 Jun 2025
Architect's certificate (Form 1)24 Jun 2025
Site photograph, BLOCK-A24 Jun 2025
Site photograph, BLOCK-B24 Jun 2025
Site photograph, BLOCK-C+D24 Jun 2025
Site photograph, BLOCK-E24 Jun 2025
Engineer's certificate (Form 2)27 Sep 2024
Engineer's certificate annexure27 Sep 2024
RERA registration certificate12 Dec 2022
Proforma agreement for sale-
Auditor's report (3 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (3 of 3)-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Declaration in Form B-
Approved building or plotting plan-
NOCs from authorities-
Title clearance certificate-
Title report-
Property card-
Proforma sale deed-
Project photograph-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (3 of 3)-

How this compares with Ahmedabad

93%of this project is bookeddistrict median 53%
14%of Ahmedabad projects moved their completion datethis one has not

Computed across the 5,400+ Ahmedabad projects on ReraGenie, from their own filings.

Keep JALDHARA RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near KATHWADA5,400+ in Ahmedabad

2 kmJALDHARA RESIDENCYOther 311Dot size: filed unitsN

Filed coordinates, straight-line distance. 311 registered projects within 2 km.

Builder: EVERGREEN DEVELOPERS

EVERGREEN DEVELOPERS has 1 registration on GujRERA, including JALDHARA RESIDENCY. Read the full track record. See more projects on the Ahmedabad district page.

Frequently asked questions

What are my rights if JALDHARA RESIDENCY is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of JALDHARA RESIDENCY?

The registered promoter entity is EVERGREEN DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in JALDHARA RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at JALDHARA RESIDENCY?

The professionals named in the filing: Architect: BHUMIKA JITENDRAKUMAR KAPADIYA; Engineer: YAMINIBEN AKASHKUMAR PARMAR. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in JALDHARA RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About JALDHARA RESIDENCY. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save JALDHARA RESIDENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.