Red flags

  • Completion date moved by 47 months
  • 4 extensions taken

Clear

  • Nothing verified clear yet
Nov 2022Possession promisedmoved 47 months from the original
4 of 8Construction stages donefurthest along: Staircases, 80%
68 of 71Units unsoldnot recorded sold or booked
Jump to the 38 documents Report an error

INDIA COLONY (BLOCK A) GERATPUR is a Mixed Development project by B NANJI ENTERPRISES LIMITED in Ahmedabad, Gujarat, registered with GujRERA as PR/GJ/AHMEDABAD/DASKROI/AUDA/MAA01761/EX4/151022 on 26 Feb 2018. Possession is promised by 30 Nov 2022. The completion date has moved by 47 months from the original filing. 3 of the 71 units on this registration are recorded sold or booked, and 4 of 8 construction stages are filed complete.

At a glance

Project

  • NameINDIA COLONY (BLOCK A) GERATPUR
  • TypeMixed Development
  • Location
    • INDIA COLONY
    • OPP. GERATPUR RAILWAY STATION
    • SEEMA COLONY BUS STAND
    • GERATPUR
    • TA. DASCROI
    • Geratpur
    • Daskroi
    • Ahmedabad
    • 382445
  • Pincode382445
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/AHMEDABAD/DASKROI/AUDA/MAA01761/EX4/151022
  • ReraGenie IDRG-GJ-45543

Builder

  • NameB NANJI ENTERPRISES LIMITED
  • Entity typeCOMPANY

Key dates

this monthRegisteredFeb 2018First promiseDec 2018Revised toNov 2022

Key facts

Registration and timeline

  • StatusValid until 30 Nov 2022
  • Registered on26 Feb 2018
  • Promised completion30 Nov 2022
  • Revised completionRevised to 30 Nov 2022 (originally 31 Dec 2018)
  • Buildings1 building record
  • Documents filed38 files

Current status

4%3 of 71 units booked
64.2%Of the estimated cost spent so far

Figures as on 13 Oct 2022, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---561571

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 13 Oct 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 8 construction stages are filed complete. The stage furthest along is Staircases, at 80%.

A: 82% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats50%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing80%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing50%

Progress on shared amenities19

As on 13 Oct 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes0%
Water supplyYes0%
Sewerage (chamber, lines, septic tank, STP)Yes0%
Storm water drainsNoNot applicable
Landscaping and tree plantingYes80%
Street lightingYes0%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area6,070 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Estimated costRs 7.12 cr
Cost incurredRs 4.58 cr
Spent of the estimate64.21%
BuildingWingEstimatedIncurred
ANARs 7.12 crRs 4.58 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectHASMUKH R. PAREKH
EngineerJayesh D desai

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/AHMEDABAD/DASKROI/AUDA/MAA01761/EX1/160722Applied Jun 2022; approved Jul 2022
PR/GJ/AHMEDABAD/DASKROI/AUDA/MAA01761/EX2/041022Applied Sep 2022; approved Oct 2022
PR/GJ/AHMEDABAD/DASKROI/AUDA/MAA01761/EX3/121022Applied Oct 2022; approved Oct 2022
PR/GJ/AHMEDABAD/DASKROI/AUDA/MAA01761/EX4/151022Applied Oct 2022; approved Oct 2022

Documents filed38

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/AHMEDABAD/DASKROI/AUDA/MAA01761/EX4/151022 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)13 Oct 2022
Architect's certificate (Form 1)12 Oct 2022
Site photograph, A12 Oct 2022
RERA registration certificate26 Feb 2018
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-
Engineer's certificate (Form 2)-
Engineer's certificate annexure-

How this compares with Ahmedabad

4%of this project is bookeddistrict median 53%
14%of Ahmedabad projects moved their completion datethis one moved by 47 months

Computed across the 5,400+ Ahmedabad projects on ReraGenie, from their own filings.

Keep INDIA COLONY (BLOCK A) GERATPUR on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Geratpur5,400+ in Ahmedabad

2 kmINDIA COLONY (BLOCK A) GOther 21Dot size: filed unitsN

Filed coordinates, straight-line distance. 21 registered projects within 2 km.

Builder: B NANJI ENTERPRISES LIMITED

B NANJI ENTERPRISES LIMITED has 1 registration on GujRERA, including INDIA COLONY (BLOCK A) GERATPUR. Read the full track record. See more projects on the Ahmedabad district page.

Frequently asked questions

What are my rights if INDIA COLONY (BLOCK A) GERATPUR is delayed beyond 30 Nov 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of INDIA COLONY (BLOCK A) GERATPUR?

The registered promoter entity is B NANJI ENTERPRISES LIMITED, a company as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in INDIA COLONY (BLOCK A) GERATPUR?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at INDIA COLONY (BLOCK A) GERATPUR?

The professionals named in the filing: Architect: HASMUKH R. PAREKH; Engineer: Jayesh D desai. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in INDIA COLONY (BLOCK A) GERATPUR?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About INDIA COLONY (BLOCK A) GERATPUR. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save INDIA COLONY (BLOCK A) GERATPUR to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.