Helios Revanta
RG-GJ-08169 · RERA PR/GJ/SURAT/BARDOLI/Bardoli Municipality/RN205AA10105/A1R/110325/310327 · Last updated on GujRERA portal: 26 Feb 2025
Source: official GujRERA filing
Red flags
- No red flags in this filing
Clear
- Completion date never moved
Saved.
Helios Revanta is a Residential/Group Housing project by HELIOS REVANTA in Surat, Gujarat, registered with GujRERA as PR/GJ/SURAT/BARDOLI/Bardoli Municipality/RN205AA10105/A1R/110325/310327 on 28 Sep 2022. Possession is promised by 31 Mar 2027. 7 of the 46 units on this registration are recorded sold or booked, and 69 of 153 construction stages are filed complete.
At a glance
Project
- NameHelios Revanta
- TypeResidential/Group Housing
- Location
- SN No 337/1
- Paikee Subplot No 2
- OP No 76
- FP No 76/2
- Bardoli
- BARDOLI
- Surat
- 394601
- Pincode394601
- MapView location on Google Maps (as filed on RERA)
- RERA no.PR/GJ/SURAT/BARDOLI/Bardoli Municipality/RN205AA10105/A1R/110325/310327
- ReraGenie IDRG-GJ-08169
Builder
- NameHELIOS REVANTA
- Entity typePARTNERSHIP FIRM
Key dates
Key facts
Registration and timeline
- StatusValid until 31 Mar 2027
- Registered on28 Sep 2022
- Promised completion31 Mar 2027
- Revised completionNone
- Buildings17 building records
- Documents filed26 files
Current status
Figures as on 26 Feb 2025, this project's latest GujRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A | - | - | - | 1 | 0 | 1 |
| B | - | - | - | 1 | 0 | 1 |
| C | - | - | - | 1 | 0 | 1 |
| D | - | - | - | 1 | 0 | 1 |
| E | - | - | - | 2 | 0 | 2 |
| F | - | - | - | 2 | 0 | 2 |
| G | - | - | - | 6 | 0 | 6 |
| H | - | - | - | 6 | 0 | 6 |
| I | - | - | - | 1 | 0 | 1 |
| J | - | - | - | 1 | 0 | 1 |
| K | - | - | - | 5 | 0 | 5 |
| L | - | - | - | 4 | 0 | 4 |
| 33-35 | - | - | - | 3 | 0 | 3 |
| 36-38 | - | - | - | 3 | 0 | 3 |
| 39-41 | - | - | - | 3 | 0 | 3 |
| 42-44 | - | - | - | 3 | 0 | 3 |
| 45-47 | - | - | - | 3 | 0 | 3 |
The full filing
Everything below is from the project's own GujRERA filing, free to read.
Construction progress by building17
As on 26 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
69 of 153 construction stages are filed complete across 17 buildings. The stage furthest along is Slabs of Super Structure, at 67%.
A80%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 67% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 0% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
B80%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 67% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 0% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
C80%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 67% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 0% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
D80%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 67% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 0% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
E63%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 50% |
| Slabs of Super Structure | 67% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 50% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 0% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 50% |
F63%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 50% |
| Slabs of Super Structure | 67% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 50% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 0% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 50% |
G52%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 17% |
| Slabs of Super Structure | 67% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 17% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 0% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 17% |
H52%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 17% |
| Slabs of Super Structure | 67% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 17% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 0% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 17% |
I80%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 67% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 0% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
J80%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 67% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 0% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
K53%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 20% |
| Slabs of Super Structure | 67% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 20% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 0% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 20% |
L55%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 25% |
| Slabs of Super Structure | 67% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 25% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 0% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 25% |
33-3557%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 33% |
| Slabs of Super Structure | 67% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 33% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 0% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 33% |
36-3857%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 33% |
| Slabs of Super Structure | 67% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 33% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 0% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 33% |
39-4157%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 33% |
| Slabs of Super Structure | 67% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 33% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 0% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 33% |
42-4457%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 33% |
| Slabs of Super Structure | 67% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 33% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 0% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 33% |
45-4757%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 33% |
| Slabs of Super Structure | 67% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 33% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 0% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 33% |
Progress on shared amenities23
As on 26 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal roads and footpaths | Yes | 0% |
| Water supply | Yes | 0% |
| Sewerage (chamber, lines, septic tank, STP) | Yes | 0% |
| Storm water drains | Yes | 0% |
| Landscaping and tree planting | Yes | 0% |
| Street lighting | Yes | 0% |
| Community buildings | Yes | 0% |
| Treatment and disposal of sewage and sullage water | Yes | 0% |
| Solid waste management and disposal | Yes | 0% |
| Water conservation, rain water harvesting | Yes | 0% |
| Energy management | Yes | 0% |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Fire fighting | No | Not applicable |
| Drinking water facilities | Yes | 0% |
| Emergency evacuation | No | Not applicable |
| Use of renewable energy | No | Not applicable |
| Security | Yes | 0% |
| Letter box | No | Not applicable |
| Compound wall | Yes | 0% |
| Plinth protection | Yes | 0% |
| Water tank | Yes | 0% |
| Other requirements | Yes | 0% |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| G | NA | Rs 1.32 cr | Rs 1.15 cr |
| H | NA | Rs 1.32 cr | Rs 1.15 cr |
| K | NA | Rs 1.10 cr | Rs 75.00 lakh |
| L | NA | Rs 88.00 lakh | Rs 50.00 lakh |
| 33-35 | NA | Rs 66.00 lakh | Rs 50.00 lakh |
| 36-38 | NA | Rs 66.00 lakh | Rs 35.00 lakh |
| 39-41 | NA | Rs 66.00 lakh | Rs 35.00 lakh |
| 42-44 | NA | Rs 66.00 lakh | Rs 35.00 lakh |
| 45-47 | NA | Rs 66.00 lakh | Rs 35.00 lakh |
| E | NA | Rs 44.00 lakh | Rs 35.00 lakh |
| F | NA | Rs 44.00 lakh | Rs 35.00 lakh |
| A | NA | Rs 22.00 lakh | Rs 12.50 lakh |
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Devansh Vipul Kikani |
| Engineer | RIYAZHUSEN FAKIRMOHMAD SHAIKH |
Documents filed26
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/SURAT/BARDOLI/Bardoli Municipality/RN205AA10105/A1R/110325/310327 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Engineer's certificate (Form 2) | 26 Feb 2025 |
| Engineer's certificate annexure | 26 Feb 2025 |
| RERA registration certificate | 28 Sep 2022 |
| Proforma agreement for sale | - |
| Auditor's report (3 of 3) | - |
| Income tax return (3 of 3) | - |
| Project specific document | - |
| Drainage affidavit | - |
| Directors' report (3 of 3) | - |
| Approved sanctioned plan | - |
| Approved layout plan | - |
| Land location | - |
| Encumbrance certificate | - |
| Area development document | - |
| Proforma allotment letter | - |
| Brochure | - |
| Declaration in Form B | - |
| Approved building or plotting plan | - |
| Title clearance certificate | - |
| Title report | - |
| Property card | - |
| Project photograph | - |
| Proforma sale deed | - |
| Audited balance sheet (3 of 3) | - |
| Audited profit and loss statement (3 of 3) | - |
| Cash flow statement (3 of 3) | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Surat
Computed across the 2,600+ Surat projects on ReraGenie, from their own filings.
Keep Helios Revanta on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near BARDOLI2,600+ in Surat
Filed coordinates, straight-line distance. 9 registered projects within 2 km.
RUDRA IMPERIA
RUDRA BUILDCON
ORCHID HUB
OMKAR DEVELOPERS
ALPINE AROMA
RADHE CORPORATION
ALPINE SIERA SKY
ALPINE BUILDCON
THE ICONIC
THE ICONIC
BR SQUARE
DHARMRAJ CORPORATION
See every Surat project, with the district possession charts
Builder: HELIOS REVANTA
HELIOS REVANTA has 1 registration on GujRERA, including Helios Revanta. Read the full track record. See more projects on the Surat district page.
Frequently asked questions
What are my rights if Helios Revanta is delayed beyond 31 Mar 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.
How do I verify and contact the developer of Helios Revanta?
The registered promoter entity is HELIOS REVANTA, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.
Is my payment protected in Helios Revanta?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at Helios Revanta?
The professionals named in the filing: Architect: Devansh Vipul Kikani; Engineer: RIYAZHUSEN FAKIRMOHMAD SHAIKH. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Helios Revanta?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.