ReraGenieLog inGet a buyer report

Home / Browse projects / Rajkot, Gujarat / GOKUL HARIDWAR HILLS

Valid until 30 Apr 2031 Residential/Group Housing project

GOKUL HARIDWAR HILLS

By OM REALTY

RG-GJ-99168 · RERA PR/GJ/RAJKOT/UPLETA/Upleta Municipality/RAA16017/181025/311230 · Last updated on GujRERA portal: 18 Oct 2025

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Apr 2031Possession promisedno revision filed
3 of 45Construction stages doneacross 5 buildings; furthest along: Stilt Floor, 45%
198 of 198Units unsoldnot recorded sold or booked
Jump to the 35 documents Report an error

GOKUL HARIDWAR HILLS is a Residential/Group Housing project by OM REALTY in Rajkot, Gujarat, registered with GujRERA as PR/GJ/RAJKOT/UPLETA/Upleta Municipality/RAA16017/181025/311230 on 18 Oct 2025. Possession is promised by 30 Apr 2031. 0 of the 198 units on this registration are recorded sold or booked, and 3 of 45 construction stages are filed complete.

At a glance

Project

  • NameGOKUL HARIDWAR HILLS
  • TypeResidential/Group Housing
  • Location
    • NEAR BAPS SWAMINARAYAN MANDIR
    • OPP. V.P. GHETIA HIGH SCHOOL
    • UPLETA
    • UPLETA
    • Rajkot
    • 360490
  • Pincode360490
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/RAJKOT/UPLETA/Upleta Municipality/RAA16017/181025/311230
  • ReraGenie IDRG-GJ-99168

Builder

  • NameOM REALTY
  • Entity typePARTNERSHIP FIRM
  • Other registrations2 more →

Key dates

this monthRegisteredOct 2025PromisedApr 2031

Key facts

Registration and timeline

  • StatusValid until 30 Apr 2031
  • Registered on18 Oct 2025
  • Promised completion30 Apr 2031
  • Revised completionNone
  • Buildings5 building records
  • Documents filed35 files

Current status

0%0 of 198 units booked
5.6%Of the estimated cost spent so far

Figures as on 18 Oct 2025, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---44044
C---44044
B---44044
E---22022
D---44044

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building5

As on 18 Oct 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 45 construction stages are filed complete across 5 buildings. The stage furthest along is Stilt Floor, at 45%.

A0%
ActivityProgress
Excavation0%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
C16%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor23%
Slabs of Super Structure20%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks5%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
B23%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor45%
Slabs of Super Structure40%
Internal walls, internal plaster, floorings, doors and windows within flats5%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks15%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
E12%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor5%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
D0%
ActivityProgress
Excavation0%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%

Progress on shared amenities19

As on 18 Oct 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes0%
Water supplyYes0%
Sewerage (chamber, lines, septic tank, STP)Yes0%
Storm water drainsYes0%
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterYes0%
Solid waste management and disposalYes0%
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingYes0%
Drinking water facilitiesYes0%
Emergency evacuationYes0%
Use of renewable energyYes0%
SecurityYes0%
Letter boxYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area8,897 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 32.25 cr
Cost incurredRs 1.81 cr
Spent of the estimate5.62%
BuildingWingEstimatedIncurred
BNARs 7.70 crRs 1.08 cr
ANARs 7.60 cr-
ENARs 5.85 crRs 23.40 lakh
CNARs 5.55 crRs 49.95 lakh
DNARs 5.55 cr-

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectParth Jayantilal Patel
EngineerSANJAYKUMAR GOPALBHAI UNJIA

Documents filed35

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/RAJKOT/UPLETA/Upleta Municipality/RAA16017/181025/311230 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
RERA registration certificate18 Oct 2025
Accountant's certificate (Form 3)15 Oct 2025
Architect's certificate (Form 1)9 Jul 2025
Engineer's certificate (Form 2)9 Jul 2025
Engineer's certificate annexure9 Jul 2025
Site photograph, A9 Jul 2025
Site photograph, C9 Jul 2025
Site photograph, B9 Jul 2025
Site photograph, E9 Jul 2025
Site photograph, D9 Jul 2025
Proforma agreement for sale-
Auditor's report (3 of 3)-
Income tax return (3 of 3)-
Project specific document-
Drainage affidavit-
Directors' report (3 of 3)-
Approved sanctioned plan-
Approved layout plan-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Declaration in Form B-
Approved building or plotting plan-
NOCs from authorities-
Title clearance certificate-
Title report-
Property card-
Statutory document-
Project photograph-
Proforma sale deed-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (3 of 3)-

How this compares with Rajkot

0%of this project is bookeddistrict median 56%
13%of Rajkot projects moved their completion datethis one has not

Computed across the 1,800+ Rajkot projects on ReraGenie, from their own filings.

Keep GOKUL HARIDWAR HILLS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near UPLETA1,800+ in Rajkot

2 kmGOKUL HARIDWAR HILLSOther 9Dot size: filed unitsN

Filed coordinates, straight-line distance. 9 registered projects within 2 km.

Builder: OM REALTY

OM REALTY has 3 registrations on GujRERA, including PELICAN PARADISE and The Signature. Read the full track record. See more projects on the Rajkot district page.

Frequently asked questions

What are my rights if GOKUL HARIDWAR HILLS is delayed beyond 30 Apr 2031?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of GOKUL HARIDWAR HILLS?

The registered promoter entity is OM REALTY, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in GOKUL HARIDWAR HILLS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at GOKUL HARIDWAR HILLS?

The professionals named in the filing: Architect: Parth Jayantilal Patel; Engineer: SANJAYKUMAR GOPALBHAI UNJIA. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in GOKUL HARIDWAR HILLS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About GOKUL HARIDWAR HILLS. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save GOKUL HARIDWAR HILLS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.