Home / Browse projects / Surat, Gujarat / FLOWER VALLEY

Valid until 30 Apr 2029 Residential/Group Housing project

FLOWER VALLEY

By SHIV DEVELOPERS

RG-GJ-23395 · RERA PR/GJ/SURAT/CHORYASI/Surat Municipal Corporation/RAA14468/021224/311228 · Last updated on GujRERA portal: 8 Apr 2026

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Apr 2029Possession promisedno revision filed
8 of 9Construction stages donefurthest along: Stilt Floor, 0%
42 of 56Units unsoldnot recorded sold or booked
Jump to the 37 documents Report an error

FLOWER VALLEY is a Residential/Group Housing project by SHIV DEVELOPERS in Surat, Gujarat, registered with GujRERA as PR/GJ/SURAT/CHORYASI/Surat Municipal Corporation/RAA14468/021224/311228 on 2 Dec 2024. Possession is promised by 30 Apr 2029. 14 of the 56 units on this registration are recorded sold or booked, and 8 of 9 construction stages are filed complete.

At a glance

Project

  • NameFLOWER VALLEY
  • TypeResidential/Group Housing
  • Location
    • BLOCK NO.:- 585
    • O.P.NO.:- 193
    • F.P. NO.:- 193
    • SUB PLOT NUMBER: - 3/2
    • T.P.S. NO. 84 (KOSAD - BHARTHANA KOSAD - MOTA VARACHHA - ABRAMA)
    • MOJE: MOTA...
  • Pincode394101
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/SURAT/CHORYASI/Surat Municipal Corporation/RAA14468/021224/311228
  • ReraGenie IDRG-GJ-23395

Builder

  • NameSHIV DEVELOPERS
  • Entity typePARTNERSHIP FIRM
  • Other registrations48 more →

Key dates

this monthRegisteredDec 2024PromisedApr 2029

Key facts

Registration and timeline

  • StatusValid until 30 Apr 2029
  • Registered on2 Dec 2024
  • Promised completion30 Apr 2029
  • Revised completionNone
  • Buildings1 building record
  • Documents filed37 files

Current status

25%14 of 56 units booked
100.0%Of the estimated cost spent so far

Figures as on 8 Apr 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A+B---56056

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 8 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 9 construction stages are filed complete. The stage furthest along is Stilt Floor, at 0%.

A+B: 89% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 8 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsYes100%
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes100%
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingYes100%
Drinking water facilitiesYes100%
Emergency evacuationYes100%
Use of renewable energyNoNot applicable
SecurityYes100%
Letter boxYes100%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,986 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 13.00 cr
Cost incurredRs 13.00 cr
Spent of the estimate100.0%
BuildingWingEstimatedIncurred
A+BNARs 13.00 crRs 13.00 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectHiralben Anilbhai Thummer
EngineerJIGNESHKUMAR BABUBHAI MORADIYA

Documents filed37

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/SURAT/CHORYASI/Surat Municipal Corporation/RAA14468/021224/311228 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)8 Apr 2026
Engineer's certificate (Form 2)8 Apr 2026
Engineer's certificate annexure8 Apr 2026
Accountant's certificate (Form 3)8 Apr 2026
Site photograph, A+B8 Apr 2026
RERA registration certificate2 Dec 2024
Proforma agreement for sale-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Drainage affidavit-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Approved sanctioned plan-
Approved layout plan-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Declaration in Form B-
Approved building or plotting plan-
NOCs from authorities-
Title clearance certificate-
Title report-
Property card-
Statutory document-
Project photograph-
Proforma sale deed-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Surat

25%of this project is bookeddistrict median 39%
15%of Surat projects moved their completion datethis one has not

Computed across the 2,600+ Surat projects on ReraGenie, from their own filings.

Keep FLOWER VALLEY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near MOTA VARACHHA2,600+ in Surat

2 kmFLOWER VALLEYOther 190Dot size: filed unitsN

Filed coordinates, straight-line distance. 190 registered projects within 2 km.

Builder: SHIV DEVELOPERS

SHIV DEVELOPERS has 49 registrations on GujRERA, including PRATHAM LUXURIA and SHIV HABITAT. Read the full track record. See more projects on the Surat district page.

Frequently asked questions

What are my rights if FLOWER VALLEY is delayed beyond 30 Apr 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of FLOWER VALLEY?

The registered promoter entity is SHIV DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in FLOWER VALLEY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at FLOWER VALLEY?

The professionals named in the filing: Architect: Hiralben Anilbhai Thummer; Engineer: JIGNESHKUMAR BABUBHAI MORADIYA. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in FLOWER VALLEY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About FLOWER VALLEY. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save FLOWER VALLEY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.