Home / Browse projects / Ahmedabad, Gujarat / EMINENCE 14

Valid until 30 Jan 2027 Mixed Development project

EMINENCE 14

By OM INFRASTRUCTURE

RG-GJ-98575 · RERA PR/GJ/AHMEDABAD/AHMEDABAD CITY/Ahmedabad Municipal Corporation/MAA16004/171025/300926 · Last updated on GujRERA portal: 21 Nov 2025

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Jan 2027Possession promisedno revision filed
3 of 9Construction stages donefurthest along: Internal walls, 70%
7 of 16Units unsoldnot recorded sold or booked
Jump to the 44 documents Report an error

EMINENCE 14 is a Mixed Development project by OM INFRASTRUCTURE in Ahmedabad, Gujarat, registered with GujRERA as PR/GJ/AHMEDABAD/AHMEDABAD CITY/Ahmedabad Municipal Corporation/MAA16004/171025/300926 on 17 Oct 2025. Possession is promised by 30 Jan 2027. 9 of the 16 units on this registration are recorded sold or booked, and 3 of 9 construction stages are filed complete.

At a glance

Project

  • NameEMINENCE 14
  • TypeMixed Development
  • Location
    • Eminence-14
    • Dalal Colony
    • Opp. Nilkanth Hospital
    • Ramannagar Cross Roads
    • Maninagar
    • Ahmedabad
    • KHOKHRA
    • Ahmedabad City
    • Ahmedabad
    • 380008
  • Pincode380008
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/AHMEDABAD/AHMEDABAD CITY/Ahmedabad Municipal Corporation/MAA16004/171025/300926
  • ReraGenie IDRG-GJ-98575

Builder

  • NameOM INFRASTRUCTURE
  • Entity typePARTNERSHIP FIRM
  • Other registrations8 more →

Key dates

this monthRegisteredOct 2025PromisedJan 2027

Key facts

Registration and timeline

  • StatusValid until 30 Jan 2027
  • Registered on17 Oct 2025
  • Promised completion30 Jan 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed44 files

Current status

56%9 of 16 units booked
54.3%Of the estimated cost spent so far

Figures as on 21 Nov 2025, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---14216

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 21 Nov 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 9 construction stages are filed complete. The stage furthest along is Internal walls, at 70%.

A: 41% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats70%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%

Progress on shared amenities19

As on 21 Nov 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsNoNot applicable
Water supplyYes0%
Sewerage (chamber, lines, septic tank, STP)Yes0%
Storm water drainsYes0%
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterYes0%
Solid waste management and disposalYes0%
Water conservation, rain water harvestingYes0%
Energy managementYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingYes0%
Drinking water facilitiesYes0%
Emergency evacuationYes0%
Use of renewable energyYes0%
SecurityNoNot applicable
Letter boxYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area393 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 1.90 cr
Cost incurredRs 1.03 cr
Spent of the estimate54.34%
BuildingWingEstimatedIncurred
ANARs 1.90 crRs 1.03 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRamesh Dolatbhai Khatri
EngineerMILAP BIPINCHANDRA CHOKSHI

Documents filed44

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/AHMEDABAD/AHMEDABAD CITY/Ahmedabad Municipal Corporation/MAA16004/171025/300926 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)21 Nov 2025
Engineer's certificate (Form 2)21 Nov 2025
Engineer's certificate annexure21 Nov 2025
Accountant's certificate (Form 3)21 Nov 2025
Site photograph, A15 Nov 2025
RERA registration certificate17 Oct 2025
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Approved sanctioned plan-
Approved layout plan-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Declaration in Form B-
Declaration in Form B1-
Declaration in Form B2-
Approved building or plotting plan-
NOCs from authorities-
Title clearance certificate-
Title report-
Property card-
Statutory document-
Project photograph-
Proforma sale deed-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Ahmedabad

56%of this project is bookeddistrict median 53%
14%of Ahmedabad projects moved their completion datethis one has not

Computed across the 5,400+ Ahmedabad projects on ReraGenie, from their own filings.

Keep EMINENCE 14 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near KHOKHRA5,400+ in Ahmedabad

2 kmEMINENCE 14Other 131Dot size: filed unitsN

Filed coordinates, straight-line distance. 131 registered projects within 2 km.

Builder: OM INFRASTRUCTURE

OM INFRASTRUCTURE has 9 registrations on GujRERA, including SHLOK PARISAR and TANISHQ-21. Read the full track record. See more projects on the Ahmedabad district page.

Frequently asked questions

What are my rights if EMINENCE 14 is delayed beyond 30 Jan 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of EMINENCE 14?

The registered promoter entity is OM INFRASTRUCTURE, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in EMINENCE 14?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at EMINENCE 14?

The professionals named in the filing: Architect: Ramesh Dolatbhai Khatri; Engineer: MILAP BIPINCHANDRA CHOKSHI. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in EMINENCE 14?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About EMINENCE 14. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save EMINENCE 14 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.