Home / Browse projects / Junagadh, Gujarat / DWARIKA PLATINUM 15

Valid until 30 Apr 2029 Residential/Group Housing project

DWARIKA PLATINUM 15

By DASARAM BUILDERS

RG-GJ-86348 · RERA PR/GJ/JUNAGADH/JUNAGADH/Junagadh Municipal Corporation/RAA14242/071024/311228 · Last updated on GujRERA portal: 7 May 2026

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Apr 2029Possession promisedno revision filed
7 of 9Construction stages donefurthest along: External plumbing and external plaster, 85%
12 of 40Units unsoldnot recorded sold or booked
Jump to the 43 documents Report an error

DWARIKA PLATINUM 15 is a Residential/Group Housing project by DASARAM BUILDERS in Junagadh, Gujarat, registered with GujRERA as PR/GJ/JUNAGADH/JUNAGADH/Junagadh Municipal Corporation/RAA14242/071024/311228 on 7 Oct 2024. Possession is promised by 30 Apr 2029. 28 of the 40 units on this registration are recorded sold or booked, and 7 of 9 construction stages are filed complete.

At a glance

Project

  • NameDWARIKA PLATINUM 15
  • TypeResidential/Group Housing
  • Location
    • Near BAPS Swaminarayan Temple
    • Gopalnagar - Opp. Shree Ram Nagar
    • Joshipara
    • Joshipara
    • Junagadh
    • Junagadh
    • 362002
  • Pincode362002
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/JUNAGADH/JUNAGADH/Junagadh Municipal Corporation/RAA14242/071024/311228
  • ReraGenie IDRG-GJ-86348

Builder

  • NameDASARAM BUILDERS
  • Entity typePARTNERSHIP FIRM
  • Other registrations3 more →

Key dates

this monthRegisteredOct 2024PromisedApr 2029

Key facts

Registration and timeline

  • StatusValid until 30 Apr 2029
  • Registered on7 Oct 2024
  • Promised completion30 Apr 2029
  • Revised completionNone
  • Buildings1 building record
  • Documents filed43 files

Current status

70%28 of 40 units booked
100.0%Of the estimated cost spent so far

Figures as on 7 May 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---40040

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 7 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 9 construction stages are filed complete. The stage furthest along is External plumbing and external plaster, at 85%.

A: 94% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing85%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing60%

Progress on shared amenities19

As on 7 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes70%
Water supplyYes70%
Sewerage (chamber, lines, septic tank, STP)Yes70%
Storm water drainsYes70%
Landscaping and tree plantingYes70%
Street lightingYes70%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes70%
Water conservation, rain water harvestingYes70%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes70%
Electrical meter room, sub-station, receiving stationYes70%
Fire fightingYes70%
Drinking water facilitiesYes70%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes70%
Letter boxYes70%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area879 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 2.06 cr
Cost incurredRs 2.06 cr
Spent of the estimate100.0%
BuildingWingEstimatedIncurred
ANARs 2.06 crRs 2.06 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMAITRI UPENDRA MODI
EngineerVIREN DILIPBHAI PAREKH

Documents filed43

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/JUNAGADH/JUNAGADH/Junagadh Municipal Corporation/RAA14242/071024/311228 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)7 May 2026
Engineer's certificate (Form 2)7 May 2026
Engineer's certificate annexure7 May 2026
Accountant's certificate (Form 3)7 May 2026
Site photograph, A7 May 2026
RERA registration certificate7 Oct 2024
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Drainage affidavit-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Approved sanctioned plan-
Approved layout plan-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Declaration in Form B-
Approved building or plotting plan-
NOCs from authorities-
Title clearance certificate-
Title report-
Property card-
Statutory document-
Project photograph-
Proforma sale deed-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Junagadh

70%of this project is bookeddistrict median 32%
7%of Junagadh projects moved their completion datethis one has not

Computed across the 240+ Junagadh projects on ReraGenie, from their own filings.

Keep DWARIKA PLATINUM 15 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Joshipara , Junagadh240+ in Junagadh

2 kmDWARIKA PLATINUM 15Other 103Dot size: filed unitsN

Filed coordinates, straight-line distance. 103 registered projects within 2 km.

Builder: DASARAM BUILDERS

DASARAM BUILDERS has 4 registrations on GujRERA, including DWARIKA PLATINUM 2 and DASARAM PRIME 2. Read the full track record. See more projects on the Junagadh district page.

Frequently asked questions

What are my rights if DWARIKA PLATINUM 15 is delayed beyond 30 Apr 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of DWARIKA PLATINUM 15?

The registered promoter entity is DASARAM BUILDERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in DWARIKA PLATINUM 15?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at DWARIKA PLATINUM 15?

The professionals named in the filing: Architect: MAITRI UPENDRA MODI; Engineer: VIREN DILIPBHAI PAREKH. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in DWARIKA PLATINUM 15?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About DWARIKA PLATINUM 15. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save DWARIKA PLATINUM 15 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.