ReraGenieLog inGet a buyer report

Home / Browse projects / Valsad, Gujarat / DREAM ICON

Valid until 31 Dec 2026 Residential/Group Housing project

DREAM ICON

By AL-MAYOOF LIFE STYLES

RG-GJ-00991 · RERA PR/GJ/VALSAD/PARDI/AUDA/RAA08529/EX1/EX2/260526/311226 · Last updated on GujRERA portal: 9 May 2026

Source: official GujRERA filing

Red flags

  • Completion date moved by 24 months
  • 2 extensions taken

Clear

  • Nothing verified clear yet
Dec 2026Possession promisedmoved 24 months from the original
22 of 27Construction stages doneacross 3 buildings; furthest along: Installation of lifts, 85%
29 of 170Units unsoldnot recorded sold or booked
Jump to the 43 documents Report an error

DREAM ICON is a Residential/Group Housing project by AL-MAYOOF LIFE STYLES in Valsad, Gujarat, registered with GujRERA as PR/GJ/VALSAD/PARDI/AUDA/RAA08529/EX1/EX2/260526/311226 on 1 Jun 2021. Possession is promised by 31 Dec 2026. The completion date has moved by 24 months from the original filing. 141 of the 170 units on this registration are recorded sold or booked, and 22 of 27 construction stages are filed complete.

At a glance

Project

  • NameDREAM ICON
  • TypeResidential/Group Housing
  • Location
    • DUNGRA
    • VAPI
    • Pardi
    • Valsad
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VALSAD/PARDI/AUDA/RAA08529/EX1/EX2/260526/311226
  • ReraGenie IDRG-GJ-00991

Builder

  • NameAL-MAYOOF LIFE STYLES
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredJun 2021First promiseDec 2024Revised toDec 2026

Key facts

Registration and timeline

  • StatusValid until 31 Dec 2026
  • Registered on1 Jun 2021
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 31 Dec 2024)
  • Buildings3 building records
  • Documents filed43 files

Current status

83%141 of 170 units booked
100.0%Of the estimated cost spent so far

Figures as on 9 May 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
F1---60060
F2---70070
F3---40040

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building3

As on 9 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

22 of 27 construction stages are filed complete across 3 buildings. The stage furthest along is Installation of lifts, at 85%.

F189%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
F289%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
F383%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing60%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing85%

Progress on shared amenities19

As on 9 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes80%
Water supplyYes80%
Sewerage (chamber, lines, septic tank, STP)Yes80%
Storm water drainsNoNot applicable
Landscaping and tree plantingYes80%
Street lightingYes80%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes80%
Electrical meter room, sub-station, receiving stationNoNot applicable
Fire fightingYes80%
Drinking water facilitiesYes80%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes80%
Letter boxYes80%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,114 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 7.12 cr
Cost incurredRs 7.12 cr
Spent of the estimate100.0%
BuildingWingEstimatedIncurred
F1NARs 2.38 crRs 2.38 cr
F2NARs 2.38 crRs 2.38 cr
F3NARs 2.38 crRs 2.38 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKUSHKUVAR Y SHAH
EngineerDIPALI M DESAI

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/VALSAD/PARDI/AUDA/RAA08529/EX1/070425/311225Applied Mar 2025; approved Apr 2025
PR/GJ/VALSAD/PARDI/AUDA/RAA08529/EX1/EX2/260526/311226Applied Dec 2025; approved May 2026

Documents filed43

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VALSAD/PARDI/AUDA/RAA08529/EX1/EX2/260526/311226 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)9 May 2026
Architect's certificate (Form 1)8 May 2026
Engineer's certificate (Form 2)8 May 2026
Engineer's certificate annexure8 May 2026
Site photograph, F17 May 2026
Site photograph, F27 May 2026
Site photograph, F37 May 2026
RERA registration certificate1 Jun 2021
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Valsad

83%of this project is bookeddistrict median 45%
23%of Valsad projects moved their completion datethis one moved by 24 months

Computed across the 390+ Valsad projects on ReraGenie, from their own filings.

Keep DREAM ICON on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Valsad390+ in Valsad

2 kmDREAM ICONOther 77Dot size: filed unitsN

Filed coordinates, straight-line distance. 77 registered projects within 2 km.

Builder: AL-MAYOOF LIFE STYLES

AL-MAYOOF LIFE STYLES has 1 registration on GujRERA, including DREAM ICON. Read the full track record. See more projects on the Valsad district page.

Frequently asked questions

What are my rights if DREAM ICON is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of DREAM ICON?

The registered promoter entity is AL-MAYOOF LIFE STYLES, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in DREAM ICON?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at DREAM ICON?

The professionals named in the filing: Architect: KUSHKUVAR Y SHAH; Engineer: DIPALI M DESAI. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in DREAM ICON?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About DREAM ICON. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save DREAM ICON to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.