Home / Browse projects / Surat, Gujarat / DMD PARK

Valid until 31 Dec 2026 Residential/Group Housing project

DMD PARK

By Propritorship of Dharmeshbhai Patel Proprietor of DMD PARK

RG-GJ-01120 · RERA PR/GJ/SURAT/SURAT CITY/Surat Municipal Corporation/RN107AA10007/A1R/EX1/160326/311226 · Last updated on GujRERA portal: 19 Jan 2026

Source: official GujRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • Nothing verified clear yet
Dec 2026Possession promisedmoved 12 months from the original
43 of 54Construction stages doneacross 6 buildings; furthest along: Installation of lifts, 85%
81 of 132Units unsoldnot recorded sold or booked
Jump to the 49 documents Report an error

DMD PARK is a Residential/Group Housing project by Propritorship of Dharmeshbhai Patel Proprietor of DMD PARK in Surat, Gujarat, registered with GujRERA as PR/GJ/SURAT/SURAT CITY/Surat Municipal Corporation/RN107AA10007/A1R/EX1/160326/311226 on 11 Jul 2022. Possession is promised by 31 Dec 2026. The completion date has moved by 12 months from the original filing. 51 of the 132 units on this registration are recorded sold or booked, and 43 of 54 construction stages are filed complete.

At a glance

Project

  • NameDMD PARK
  • TypeResidential/Group Housing
  • Location
    • DMD Park
    • RS No: 333
    • FP : 31
    • TP 29(Rundh-Vesu)
    • Vesu
    • Surat
    • Rundh-Vesu
    • Surat City
    • Surat
    • 395009
  • Pincode395009
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/SURAT/SURAT CITY/Surat Municipal Corporation/RN107AA10007/A1R/EX1/160326/311226
  • ReraGenie IDRG-GJ-01120

Builder

  • NamePropritorship of Dharmeshbhai Patel Proprietor of DMD PARK
  • Entity typeIndividual/Propritorship

Key dates

this monthRegisteredJul 2022First promiseDec 2025Revised toDec 2026

Key facts

Registration and timeline

  • StatusValid until 31 Dec 2026
  • Registered on11 Jul 2022
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 31 Dec 2025)
  • Buildings6 building records
  • Documents filed49 files

Current status

39%51 of 132 units booked
88.7%Of the estimated cost spent so far

Figures as on 19 Jan 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
E---22022
F---22022
D---22022
A---22022
B---22022
C---22022

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building6

As on 19 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

43 of 54 construction stages are filed complete across 6 buildings. The stage furthest along is Installation of lifts, at 85%.

E87%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing85%
F82%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing50%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing85%
D83%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing60%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing85%
A89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
B89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
C89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 19 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes80%
Sewerage (chamber, lines, septic tank, STP)Yes85%
Storm water drainsYes85%
Landscaping and tree plantingYes50%
Street lightingYes70%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterYes0%
Solid waste management and disposalYes100%
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes60%
Fire fightingYes100%
Drinking water facilitiesYes100%
Emergency evacuationYes100%
Use of renewable energyYes0%
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area10,985 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 99.17 cr
Cost incurredRs 87.91 cr
Spent of the estimate88.65%
BuildingWingEstimatedIncurred
ANARs 19.91 crRs 19.91 cr
DNARs 19.91 crRs 14.94 cr
BNARs 15.08 crRs 15.08 cr
CNARs 15.08 crRs 15.08 cr
ENARs 14.59 crRs 12.40 cr
FNARs 14.59 crRs 10.51 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSANJAY RIDDHISHANKAR JOSHI
EngineerLALITCHANDRA DURGARAM ASMAR

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/SURAT/SURAT CITY/Surat Municipal Corporation/RN107AA10007/A1R/EX1/160326/311226Applied Dec 2025; approved Mar 2026

Documents filed49

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/SURAT/SURAT CITY/Surat Municipal Corporation/RN107AA10007/A1R/EX1/160326/311226 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)19 Jan 2026
Architect's certificate (Form 1)16 Jan 2026
Engineer's certificate (Form 2)16 Jan 2026
Engineer's certificate annexure16 Jan 2026
Site photograph, E16 Jan 2026
Site photograph, F16 Jan 2026
Site photograph, D16 Jan 2026
Site photograph, A16 Jan 2026
Site photograph, B16 Jan 2026
Site photograph, C16 Jan 2026
RERA registration certificate11 Jul 2022
Extension certificate-
Alteration certificate-
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Drainage affidavit-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Declaration in Form B-
Approved building or plotting plan-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Proforma sale deed-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Surat

39%of this project is bookeddistrict median 39%
15%of Surat projects moved their completion datethis one moved by 12 months

Computed across the 2,600+ Surat projects on ReraGenie, from their own filings.

Keep DMD PARK on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Rundh-Vesu2,600+ in Surat

2 kmDMD PARKOther 172Dot size: filed unitsN

Filed coordinates, straight-line distance. 172 registered projects within 2 km.

Builder: Propritorship of Dharmeshbhai Patel Proprietor of DMD PARK

Propritorship of Dharmeshbhai Patel Proprietor of DMD PARK has 1 registration on GujRERA, including DMD PARK. Read the full track record. See more projects on the Surat district page.

Frequently asked questions

What are my rights if DMD PARK is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of DMD PARK?

The registered promoter entity is Propritorship of Dharmeshbhai Patel Proprietor of DMD PARK, an individual/propritorship as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in DMD PARK?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at DMD PARK?

The professionals named in the filing: Architect: SANJAY RIDDHISHANKAR JOSHI; Engineer: LALITCHANDRA DURGARAM ASMAR. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in DMD PARK?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About DMD PARK. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save DMD PARK to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.