Home / Browse projects / Rajkot, Gujarat / COPPER GREEN

Valid until 31 Dec 2026 Residential/Group Housing project

COPPER GREEN

By TIMELINE INFRACON LLP

RG-GJ-66549 · RERA PR/GJ/RAJKOT/RAJKOT/Rajkot Municipal Corporation/MN46AA09946/A1R/200323 · Last updated on GujRERA portal: 7 Oct 2023

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
  • Separate project account declared
Dec 2026Possession promisedno revision filed
96 of 108Construction stages doneacross 12 buildings; furthest along: Plinth, 0%
18 of 77Units unsoldnot recorded sold or booked
Jump to the 36 documents Report an error

COPPER GREEN is a Residential/Group Housing project by TIMELINE INFRACON LLP in Rajkot, Gujarat, registered with GujRERA as PR/GJ/RAJKOT/RAJKOT/Rajkot Municipal Corporation/MN46AA09946/A1R/200323 on 31 May 2022. Possession is promised by 31 Dec 2026. 59 of the 77 units on this registration are recorded sold or booked, and 96 of 108 construction stages are filed complete.

At a glance

Project

  • NameCOPPER GREEN
  • TypeResidential/Group Housing
  • Location
    • BHAGWATIPARA MAIN ROAD
    • UNDER 150 FEET RING ROAD
    • COPPER AERA
    • RAJKOT
    • RAJKOT
    • 360003
  • Pincode360003
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/RAJKOT/RAJKOT/Rajkot Municipal Corporation/MN46AA09946/A1R/200323
  • ReraGenie IDRG-GJ-66549

Builder

  • NameTIMELINE INFRACON LLP
  • Entity typeLIMITED LIABILITY PARTNERSHIP FIRM
  • Other registrations2 more →

Key dates

this monthRegisteredMay 2022PromisedDec 2026

Key facts

Registration and timeline

  • StatusValid until 31 Dec 2026
  • Registered on31 May 2022
  • Promised completion31 Dec 2026
  • Revised completionNone
  • Buildings12 building records
  • Documents filed36 files

Current status

77%59 of 77 units booked
100.0%Of the estimated cost spent so far

Figures as on 7 Oct 2023, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
1---404
2---16016
3---23023
4---17017
5---404
6---606
7---202
8---101
9---101
10---101
11---101
12---101

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building12

As on 7 Oct 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

96 of 108 construction stages are filed complete across 12 buildings. The stage furthest along is Plinth, at 0%.

189%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
289%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
389%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
489%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
589%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
689%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
789%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
889%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
989%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
1089%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
1189%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
1289%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 7 Oct 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes0%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsNoNot applicable
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsYes100%
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes100%
Letter boxYes100%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,660 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 11.39 cr
Cost incurredRs 11.39 cr
Spent of the estimate100.0%
BuildingWingEstimatedIncurred
3NARs 3.45 crRs 3.45 cr
4NARs 2.50 crRs 2.50 cr
2NARs 2.40 crRs 2.40 cr
6NARs 88.00 lakhRs 88.00 lakh
1NARs 60.00 lakhRs 60.00 lakh
5NARs 60.00 lakhRs 60.00 lakh
7NARs 30.00 lakhRs 30.00 lakh
12NARs 15.00 lakhRs 15.00 lakh
10NARs 14.00 lakhRs 14.00 lakh
8NARs 13.00 lakhRs 13.00 lakh
9NARs 13.00 lakhRs 13.00 lakh
11NARs 11.25 lakhRs 11.25 lakh

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectBhargav Bhikhalal Gajera
EngineerHITESHBHAI SURESHBHAI TANK

Documents filed36

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/RAJKOT/RAJKOT/Rajkot Municipal Corporation/MN46AA09946/A1R/200323 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)7 Oct 2023
Engineer's certificate (Form 2)7 Oct 2023
Engineer's certificate annexure7 Oct 2023
Accountant's certificate (Form 3)7 Oct 2023
Site photograph, 11 Oct 2023
Site photograph, 21 Oct 2023
Site photograph, 31 Oct 2023
Site photograph, 41 Oct 2023
Site photograph, 51 Oct 2023
Site photograph, 61 Oct 2023
Site photograph, 71 Oct 2023
Site photograph, 81 Oct 2023
Site photograph, 91 Oct 2023
Site photograph, 101 Oct 2023
Site photograph, 111 Oct 2023
Site photograph, 121 Oct 2023
RERA registration certificate31 May 2022
Proforma agreement for sale-
Project specific document-
Drainage affidavit-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Approved building or plotting plan-
Title clearance certificate-
Title report-
Property card-
Proforma sale deed-
Project photograph-

How this compares with Rajkot

77%of this project is bookeddistrict median 56%
13%of Rajkot projects moved their completion datethis one has not

Computed across the 1,800+ Rajkot projects on ReraGenie, from their own filings.

Keep COPPER GREEN on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near RAJKOT1,800+ in Rajkot

2 kmCOPPER GREENOther 142Dot size: filed unitsN

Filed coordinates, straight-line distance. 142 registered projects within 2 km.

Builder: TIMELINE INFRACON LLP

TIMELINE INFRACON LLP has 3 registrations on GujRERA, including COPPER GREEN and COPPER CORNER. Read the full track record. See more projects on the Rajkot district page.

Frequently asked questions

What are my rights if COPPER GREEN is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of COPPER GREEN?

The registered promoter entity is TIMELINE INFRACON LLP, a limited liability partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in COPPER GREEN?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at COPPER GREEN?

The professionals named in the filing: Architect: Bhargav Bhikhalal Gajera; Engineer: HITESHBHAI SURESHBHAI TANK. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in COPPER GREEN?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About COPPER GREEN. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save COPPER GREEN to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.