Valid until 20 Mar 2026 Residential/Group Housing project

CASA RIVERA

By 134 INFRA LLP

RG-GJ-81493 · RERA PR/GJ/SURAT/SURAT CITY/SUDA/RAA00853/EX3/EX4/100625/200326 · Last updated on GujRERA portal: 31 May 2025

Source: official GujRERA filing

Red flags

  • Completion date moved by 48 months
  • 5 extensions taken

Clear

  • Nothing verified clear yet
Mar 2026Possession promisedmoved 48 months from the original
27 of 30Construction stages doneacross 3 buildings; furthest along: External plumbing and external plaster, 98%
36 of 141Units unsoldnot recorded sold or booked
Jump to the 34 documents Report an error

CASA RIVERA is a Residential/Group Housing project by 134 INFRA LLP in Surat, Gujarat, registered with GujRERA as PR/GJ/SURAT/SURAT CITY/SUDA/RAA00853/EX3/EX4/100625/200326 on 29 Nov 2017. Possession is promised by 20 Mar 2026. The completion date has moved by 48 months from the original filing. 105 of the 141 units on this registration are recorded sold or booked, and 27 of 30 construction stages are filed complete.

At a glance

Project

  • NameCASA RIVERA
  • TypeResidential/Group Housing
  • Location
    • 134 INFRA
    • Casa Rivera
    • T.P.14
    • F.P. 134/B
    • Beside Rajhans Elita
    • Pal-Hazira Road
    • Surat City
    • Surat
    • 395009
  • Pincode395009
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/SURAT/SURAT CITY/SUDA/RAA00853/EX3/EX4/100625/200326
  • ReraGenie IDRG-GJ-81493

Builder

  • Name134 INFRA LLP
  • Entity typeLIMITED LIABILITY PARTNERSHIP FIRM

Key dates

this monthRegisteredNov 2017First promiseMar 2022Revised toMar 2026

Key facts

Registration and timeline

  • StatusValid until 20 Mar 2026
  • Registered on29 Nov 2017
  • Promised completion20 Mar 2026
  • Revised completionRevised to 20 Mar 2026 (originally 30 Mar 2022)
  • Buildings3 building records
  • Documents filed34 files

Current status

74%105 of 141 units booked
75.5%Of the estimated cost spent so far

Figures as on 31 May 2025, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
B---41041
A---60060
C---40040

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building3

As on 31 May 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

27 of 30 construction stages are filed complete across 3 buildings. The stage furthest along is External plumbing and external plaster, at 98%.

B100%
ActivityProgress
Excavation100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing98%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
A100%
ActivityProgress
Excavation100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing97%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
C100%
ActivityProgress
Excavation100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing98%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities23

As on 31 May 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes98%
Water supplyYes98%
Sewerage (chamber, lines, septic tank, STP)Yes95%
Storm water drainsYes98%
Landscaping and tree plantingYes97%
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes96%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes93%
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable
Compound wallYes100%
Plinth protectionYes100%
Water tankNoNot applicable
Other requirementsNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area11,883 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 188.13 cr
Cost incurredRs 142.08 cr
Spent of the estimate75.52%
BuildingWingEstimatedIncurred
ANARs 79.16 crRs 67.03 cr
CNARs 56.86 crRs 38.03 cr
BNARs 52.11 crRs 37.03 cr

Extensions applied for5

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionApplied Mar 2021; no approval date filed
PR/GJ/SURAT/SURAT CITY/SUDA/RAA00853/A1R/EX2/300422Applied Feb 2022; approved Apr 2022
PR/GJ/SURAT/SURAT CITY/SUDA/RAA00853/EX3/EX2/130623Applied Apr 2023; approved Jun 2023
PR/GJ/SURAT/SURAT CITY/SUDA/RAA00853/EX3/EX3/280824/200325Applied May 2024; approved Aug 2024
PR/GJ/SURAT/SURAT CITY/SUDA/RAA00853/EX3/EX4/100625/200326Applied Mar 2025; approved Jun 2025

Documents filed34

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/SURAT/SURAT CITY/SUDA/RAA00853/EX3/EX4/100625/200326 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineer's certificate (Form 2)31 May 2025
Engineer's certificate annexure31 May 2025
RERA registration certificate29 Nov 2017
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Brochure-
Project related document-
Approved building or plotting plan-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Surat

74%of this project is bookeddistrict median 39%
15%of Surat projects moved their completion datethis one moved by 48 months

Computed across the 2,600+ Surat projects on ReraGenie, from their own filings.

Keep CASA RIVERA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Surat2,600+ in Surat

2 kmCASA RIVERAOther 146Dot size: filed unitsN

Filed coordinates, straight-line distance. 146 registered projects within 2 km.

Builder: 134 INFRA LLP

134 INFRA LLP has 1 registration on GujRERA, including CASA RIVERA. Read the full track record. See more projects on the Surat district page.

Frequently asked questions

What are my rights if CASA RIVERA is delayed beyond 20 Mar 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of CASA RIVERA?

The registered promoter entity is 134 INFRA LLP, a limited liability partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in CASA RIVERA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

What should I check before booking in CASA RIVERA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About CASA RIVERA. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save CASA RIVERA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.