Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • Separate project account declared
Aug 2019Possession promisedmoved 12 months from the original
27 of 27Construction stages doneacross 3 buildings; every applicable stage filed complete
Jump to the 38 documents Report an error

BHAGWAT ELEGANCE is a Mixed Development project by PUSHTI INFRACONE in Ahmedabad, Gujarat, registered with GujRERA as PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/MAA01018/EX1/071218 on 15 Dec 2017. Possession is promised by 13 Aug 2019. The completion date has moved by 12 months from the original filing.

At a glance

Project

  • NameBHAGWAT ELEGANCE
  • TypeMixed Development
  • Location
    • BHAGWAT ELEGANCE
    • OPP. SWAMINARAYAN PARK - 6
    • NR. OMSHANTINAGAR - 2
    • NAROL VATVA.
    • Vatva
    • Ahmedabad City
    • Ahmedabad
    • 382405
  • Pincode382405
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/MAA01018/EX1/071218
  • ReraGenie IDRG-GJ-17806

Builder

  • NamePUSHTI INFRACONE
  • Entity typePARTNERSHIP FIRM
  • Other registrations1 more →

Key dates

this monthRegisteredDec 2017First promiseAug 2018Revised toAug 2019

Key facts

Registration and timeline

  • StatusValid until 13 Aug 2019
  • Registered on15 Dec 2017
  • Promised completion13 Aug 2019
  • Revised completionRevised to 13 Aug 2019 (originally 15 Aug 2018)
  • Buildings3 building records
  • Documents filed38 files

Current status

100.0%Of the estimated cost spent so far

Figures as on 4 Apr 2019, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
C-----33
A-----85
B-----47

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building3

As on 4 Apr 2019, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

27 of 27 construction stages are filed complete across 3 buildings.

C100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
A100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
B100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 4 Apr 2019, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsNoNot applicable
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsYes100%
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingYes100%
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,521 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 8.79 cr
Cost incurredRs 8.79 cr
Spent of the estimate100.0%
BuildingWingEstimatedIncurred
ANARs 2.93 crRs 2.93 cr
BNARs 2.93 crRs 2.93 cr
CNARs 2.93 crRs 2.93 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSURESH G PRAJAPATI
EngineerMAHENDRA D KOSHTI

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/MAA01018/EX1/071218Applied Sep 2018; approved Dec 2018

Documents filed38

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/MAA01018/EX1/071218 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)4 Apr 2019
Engineer's certificate (Form 2)4 Apr 2019
Site photograph, C4 Apr 2019
Site photograph, A4 Apr 2019
Site photograph, B4 Apr 2019
RERA registration certificate15 Dec 2017
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Ahmedabad

14%of Ahmedabad projects moved their completion datethis one moved by 12 months

Computed across the 5,400+ Ahmedabad projects on ReraGenie, from their own filings.

Keep BHAGWAT ELEGANCE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Vatva5,400+ in Ahmedabad

2 kmBHAGWAT ELEGANCEOther 247Dot size: filed unitsN

Filed coordinates, straight-line distance. 247 registered projects within 2 km.

Builder: PUSHTI INFRACONE

PUSHTI INFRACONE has 2 registrations on GujRERA, including BHAGWAT ELEGANCE and BHAGWAT ALTIMUS. Read the full track record. See more projects on the Ahmedabad district page.

Frequently asked questions

What are my rights if BHAGWAT ELEGANCE is delayed beyond 13 Aug 2019?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of BHAGWAT ELEGANCE?

The registered promoter entity is PUSHTI INFRACONE, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in BHAGWAT ELEGANCE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at BHAGWAT ELEGANCE?

The professionals named in the filing: Architect: SURESH G PRAJAPATI; Engineer: MAHENDRA D KOSHTI. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in BHAGWAT ELEGANCE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About BHAGWAT ELEGANCE. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save BHAGWAT ELEGANCE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.