BEYOND VILLA

By SHREE HARI DEVELOPERS

RG-GJ-54110 · RERA PR/GJ/SURAT/SURAT CITY/SUDA/RAA02167/EX1/261021 · Last updated on GujRERA portal: 29 Jun 2022

Source: official GujRERA filing

Red flags

  • Completion date moved by 9 months
  • 1 extension taken

Clear

  • Separate project account declared
Jun 2022Possession promisedmoved 9 months from the original
357 of 357Construction stages doneacross 54 buildings; every applicable stage filed complete
12 of 54Units unsoldnot recorded sold or booked
Jump to the 91 documents Report an error

BEYOND VILLA is a Residential/Group Housing project by SHREE HARI DEVELOPERS in Surat, Gujarat, registered with GujRERA as PR/GJ/SURAT/SURAT CITY/SUDA/RAA02167/EX1/261021 on 26 Mar 2018. Possession is promised by 30 Jun 2022. The completion date has moved by 9 months from the original filing. 42 of the 54 units on this registration are recorded sold or booked, and 357 of 357 construction stages are filed complete.

At a glance

Project

  • NameBEYOND VILLA
  • TypeResidential/Group Housing
  • Location
    • BLOCK NO 20/1
    • FP NO:8/B
    • TP 43
    • JAHANGIRABAD
    • Jahangirabad
    • Surat City
    • Surat
    • 395005
  • Pincode395005
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/SURAT/SURAT CITY/SUDA/RAA02167/EX1/261021
  • ReraGenie IDRG-GJ-54110

Builder

  • NameSHREE HARI DEVELOPERS
  • Entity typePARTNERSHIP FIRM
  • Other registrations28 more →

Key dates

this monthRegisteredMar 2018First promiseSep 2021Revised toJun 2022

Key facts

Registration and timeline

  • StatusValid until 30 Jun 2022
  • Registered on26 Mar 2018
  • Promised completion30 Jun 2022
  • Revised completionRevised to 30 Jun 2022 (originally 30 Sep 2021)
  • Buildings54 building records
  • Documents filed91 files

Current status

78%42 of 54 units booked
100.0%Of the estimated cost spent so far

Figures as on 29 Jun 2022, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
1---101
2---101
3---101
4---101
5---101
6---101
7---101
8---101
9---101
10---101
11---101
12---101
13---101
14---101
15---101
16---101
17---101
18---101
19---101
20---101
21---101
22---101
23---101
24---101
25---101
26---101
27---101
28---101
29---101
30---101
31---101
32---101
33---101
34---101
35---101
36---101
37---101
38---101
39---101
40---101
41---101
42---101
43---101
44---101
45---101
46---101
47---101
48---101
49---101
50---101
51---101
52---101
53---101
54---101

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building20

As on 29 Jun 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 54 buildings; the table lists the first 20.

357 of 357 construction stages are filed complete across 54 buildings.

1100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
2100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
3100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
4100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
5100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
6100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
7100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
8100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
9100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
10100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
11100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
12100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
13100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
14100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
15100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
16100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
17100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
18100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
19100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
20100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 29 Jun 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingNoNot applicable
Drinking water facilitiesYes100%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes100%
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area10,708 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 15.04 cr
Cost incurredRs 15.04 cr
Spent of the estimate100.0%
BuildingWingEstimatedIncurred
1NARs 27.86 lakhRs 27.86 lakh
2NARs 27.86 lakhRs 27.86 lakh
3NARs 27.86 lakhRs 27.86 lakh
4NARs 27.86 lakhRs 27.86 lakh
5NARs 27.86 lakhRs 27.86 lakh
6NARs 27.86 lakhRs 27.86 lakh
7NARs 27.86 lakhRs 27.86 lakh
8NARs 27.86 lakhRs 27.86 lakh
9NARs 27.86 lakhRs 27.86 lakh
10NARs 27.86 lakhRs 27.86 lakh
11NARs 27.86 lakhRs 27.86 lakh
12NARs 27.86 lakhRs 27.86 lakh

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSANJAY JOSSHI
EngineerDharam Bhagat

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/SURAT/SURAT CITY/SUDA/RAA02167/EX1/261021Applied Sep 2021; approved Oct 2021

Documents filed91

As listed on the registration, under the names the promoter filed them with; the newest 80 of 91 are shown. The files themselves are available at source: search the registration number PR/GJ/SURAT/SURAT CITY/SUDA/RAA02167/EX1/261021 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)29 Jun 2022
Engineer's certificate (Form 2)29 Jun 2022
Engineer's certificate annexure29 Jun 2022
Accountant's certificate (Form 3)29 Jun 2022
Site photograph, 129 Jun 2022
Site photograph, 229 Jun 2022
Site photograph, 329 Jun 2022
Site photograph, 429 Jun 2022
Site photograph, 529 Jun 2022
Site photograph, 629 Jun 2022
Site photograph, 729 Jun 2022
Site photograph, 829 Jun 2022
Site photograph, 929 Jun 2022
Site photograph, 1029 Jun 2022
Site photograph, 1129 Jun 2022
Site photograph, 1229 Jun 2022
Site photograph, 1329 Jun 2022
Site photograph, 1429 Jun 2022
Site photograph, 1529 Jun 2022
Site photograph, 1629 Jun 2022
Site photograph, 1729 Jun 2022
Site photograph, 1829 Jun 2022
Site photograph, 1929 Jun 2022
Site photograph, 2029 Jun 2022
Site photograph, 2129 Jun 2022
Site photograph, 2229 Jun 2022
Site photograph, 2329 Jun 2022
Site photograph, 2429 Jun 2022
Site photograph, 2529 Jun 2022
Site photograph, 2629 Jun 2022
Site photograph, 2729 Jun 2022
Site photograph, 2829 Jun 2022
Site photograph, 2929 Jun 2022
Site photograph, 3029 Jun 2022
Site photograph, 3129 Jun 2022
Site photograph, 3229 Jun 2022
Site photograph, 3329 Jun 2022
Site photograph, 3429 Jun 2022
Site photograph, 3529 Jun 2022
Site photograph, 3629 Jun 2022
Site photograph, 3729 Jun 2022
Site photograph, 3829 Jun 2022
Site photograph, 3929 Jun 2022
Site photograph, 4029 Jun 2022
Site photograph, 4129 Jun 2022
Site photograph, 4229 Jun 2022
Site photograph, 4329 Jun 2022
Site photograph, 4429 Jun 2022
Site photograph, 4529 Jun 2022
Site photograph, 4629 Jun 2022
Site photograph, 4729 Jun 2022
Site photograph, 4829 Jun 2022
Site photograph, 4929 Jun 2022
Site photograph, 5029 Jun 2022
Site photograph, 5129 Jun 2022
Site photograph, 5229 Jun 2022
Site photograph, 5329 Jun 2022
Site photograph, 5429 Jun 2022
RERA registration certificate26 Mar 2018
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-

How this compares with Surat

78%of this project is bookeddistrict median 39%
15%of Surat projects moved their completion datethis one moved by 9 months

Computed across the 2,600+ Surat projects on ReraGenie, from their own filings.

Keep BEYOND VILLA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Jahangirabad2,600+ in Surat

2 kmBEYOND VILLAOther 149Dot size: filed unitsN

Filed coordinates, straight-line distance. 149 registered projects within 2 km.

Builder: SHREE HARI DEVELOPERS

SHREE HARI DEVELOPERS has 29 registrations on GujRERA, including AMBIKA DHAM and Shyam Shree. Read the full track record. See more projects on the Surat district page.

Frequently asked questions

What are my rights if BEYOND VILLA is delayed beyond 30 Jun 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of BEYOND VILLA?

The registered promoter entity is SHREE HARI DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in BEYOND VILLA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at BEYOND VILLA?

The professionals named in the filing: Architect: SANJAY JOSSHI; Engineer: Dharam Bhagat. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in BEYOND VILLA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About BEYOND VILLA. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save BEYOND VILLA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.